Redesign the network to Smart Grid standards by installing smart metering and automating networks to activate customers to improve energy efficiency and efficient management of the electricity system to improve security of supply. Basic implementation in the area of Energa – Operator SA.
Project Q84760 in Poland

    Statements

    0 references
    166,258,506.14 zloty
    0 references
    36,959,265.91 Euro
    13 January 2020
    0 references
    195,598,242.51 zloty
    0 references
    43,481,489.31 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    2 February 2017
    0 references
    30 November 2023
    0 references
    ENERGA-OPERATOR SPÓŁKA AKCYJNA
    0 references
    0 references
    0 references

    53°19'19.20"N, 18°20'21.44"E
    0 references

    52°32'46.28"N, 21°12'26.42"E
    0 references

    54°14'44.02"N, 18°6'35.64"E
    0 references

    53°55'52.28"N, 21°7'33.89"E
    0 references

    52°8'45.06"N, 17°23'51.61"E
    0 references

    53°32'42.29"N, 15°33'58.18"E
    0 references

    51°28'19.81"N, 19°20'45.82"E
    0 references
    Głównym elementem projektu jest wymiana wraz z montażem - rozłączników napowietrznych SN : 1180 szt. - rozdzielnic wnętrzowych SN: 1148 szt. (Polish)
    0 references
    The main element of the project is the replacement with installation – SN overhead disconnectors: 1180 pcs — internal switchgear SN: 1148 pcs (English)
    14 October 2020
    0.0038273090865643
    0 references
    L’élément principal du projet est le remplacement par l’installation — déconnecteurs aériens SN: 1180 pcs. — appareillage intérieur SN: 1148 pcs. (French)
    30 November 2021
    0 references
    Das Hauptelement des Projekts ist der Austausch durch Installation – Überkopftrennschalter SN: 1180 Stk. — Innenschaltanlagen SN: 1148 Stk. (German)
    7 December 2021
    0 references
    Het belangrijkste element van het project is de vervanging door installatie — overheadscheiders SN: 1180 stuks. — binnenschakelaar SN: 1148 stuks. (Dutch)
    16 December 2021
    0 references
    L'elemento principale del progetto è la sostituzione con l'installazione — sezionatori sopraelevati SN: 1180 pz. — quadri interni SN: 1148 pz. (Italian)
    16 January 2022
    0 references
    El elemento principal del proyecto es el reemplazo por instalación — desconectores aéreos SN: 1180 piezas. — conmutador interior SN: 1148 piezas. (Spanish)
    19 January 2022
    0 references
    Projekti põhielement on asendamine paigaldusega – õhuliinide lahtiühendamine SN: 1180 tk. – sisejaotusseadmed SN: 1148 tk. (Estonian)
    13 August 2022
    0 references
    Pagrindinis projekto elementas yra pakeitimas įrengimu – antžeminiais atjungikliais SN: 1180 vnt. – vidaus perjungimo įrenginiai SN: 1148 vnt. (Lithuanian)
    13 August 2022
    0 references
    Glavni element projekta je zamjena s instalacijom – nadzemni rastavljači SN: 1180 komada. — unutarnja rasklopna postrojenja SN: 1148 komada. (Croatian)
    13 August 2022
    0 references
    Το κύριο στοιχείο του έργου είναι η αντικατάσταση με την εγκατάσταση — εναέριες αποσύνδεση SN: 1180 τεμ. — εσωτερικός εξοπλισμός μεταγωγής SN: 1148 τεμ. (Greek)
    13 August 2022
    0 references
    Hlavným prvkom projektu je výmena za inštaláciu – nadzemné odpojovače SN: 1180 ks. — vnútorné rozvádzače SN: 1148 ks. (Slovak)
    13 August 2022
    0 references
    Hankkeen pääelementti on korvaaminen asennuksella – ilma-aukoilla SN: 1180 kpl. — sisäkytkinlaitteet SN: 1148 kpl. (Finnish)
    13 August 2022
    0 references
    A projekt fő eleme a telepítés – felső leválasztókkal való helyettesítés SN: 1180 db. – belső kapcsolóberendezések SN: 1148 db. (Hungarian)
    13 August 2022
    0 references
    Hlavním prvkem projektu je výměna za instalaci – režijní odpojovače SN: 1180 ks. — vnitřní rozvaděče SN: 1148 ks. (Czech)
    13 August 2022
    0 references
    Galvenais projekta elements ir nomaiņa ar uzstādīšanu — gaisvadu atvienotājiem SN: 1180 gab. — iekšējās sadales iekārtas SN: 1148 gab. (Latvian)
    13 August 2022
    0 references
    Is é príomhghné an tionscadail suiteáil a athsholáthar — dícheangail lastuas SN: 1180 ríomhaire. — lascthrealamh taobh istigh SN: 1148 ríomhaire. (Irish)
    13 August 2022
    0 references
    Glavni element projekta je zamenjava z namestitvijo – nadzemni odklopniki SN: 1180 kosov. — notranja stikalna naprava SN: 1148 kosov. (Slovenian)
    13 August 2022
    0 references
    Основният елемент на проекта е подмяната с монтаж — режийни разединители SN: 1180 бр. — вътрешна комутационна апаратура SN: 1148 бр. (Bulgarian)
    13 August 2022
    0 references
    L-element ewlieni tal-proġett huwa s-sostituzzjoni b’installazzjoni — skonnetturi overhead SN: 1180 biċċa. — switchgear ta’ ġewwa SN: 1148 biċċa. (Maltese)
    13 August 2022
    0 references
    O principal elemento do projeto é a substituição com instalação — desconectores aéreos SN: 1180 PCes. — aparelhagem interior SN: 1148 PCes. (Portuguese)
    13 August 2022
    0 references
    Hovedelementet i projektet er udskiftning med installation — overhead-afbrydere SN: 1180 stk. — indvendigt koblingsudstyr SN: 1148 stk. (Danish)
    13 August 2022
    0 references
    Elementul principal al proiectului este înlocuirea cu instalarea – deconectatoare aeriene SN: 1180 buc. — comutație interioară SN: 1148 buc. (Romanian)
    13 August 2022
    0 references
    Huvudelementet i projektet är utbytet med installation – omkopplingsdon SN: 1180 st. — inre ställverk SN: 1148 st. (Swedish)
    13 August 2022
    0 references
    WOJ.: KUJAWSKO-POMORSKIE
    0 references
    WOJ.: MAZOWIECKIE
    0 references
    WOJ.: POMORSKIE
    0 references
    WOJ.: WARMIŃSKO-MAZURSKIE
    0 references
    WOJ.: WIELKOPOLSKIE
    0 references
    WOJ.: ZACHODNIOPOMORSKIE
    0 references
    WOJ.: ŁÓDZKIE
    0 references
    The SCADA control system used to monitor the smart grid (English)
    Energa-Operator SA
    0 references
    24 May 2023
    0 references

    Identifiers

    POIS.01.04.01-00-0012/17
    0 references
    4743