Installation of photovoltaic cells for sewage treatment plants in Imielin (Q4427819)

From EU Knowledge Graph
Revision as of 00:08, 22 October 2022 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in en, and other parts: Adding translation)
Jump to navigation Jump to search
Project Q4427819 in Poland
Language Label Description Also known as
English
Installation of photovoltaic cells for sewage treatment plants in Imielin
Project Q4427819 in Poland

    Statements

    0 references
    517,905.0 zloty
    0 references
    115,130.28 Euro
    0 references
    609,300.0 zloty
    0 references
    135,447.39 Euro
    0 references
    85.0 percent
    0 references
    30 November 2017
    0 references
    30 November 2022
    0 references
    MIEJSKA SPÓŁKA KOMUNALNA SP. Z O.O.
    0 references
    Rzeczowy zakres projektu obejmuje zaprojektowanie, dostawę, montaż, uruchomienie i przeprowadzenie procedury włączenia do sieci OSD instalacji fotowoltaicznej przy obiekcie oczyszczalni ścieków w Imielinie. Zastosowano moduły o mocy 290 Wp o łącznej mocy 146,16 kWp. Projektowana instalacja fotowoltaiczna została usytuowana na gruncie i będzie produkować rocznie około 3,2 MWh energii elektrycznej. Składa się ona z 504 modułów fotowoltaicznych o mocy 290Wp każdy moduł. Moduły fotowoltaiczne będą współpracowały z 5 inwerterami (falownikami) o mocy 20kW i 30kW. Wyprodukowana energia elektryczna będzie dostarczana do wewnętrznej sieci energetycznej budynku. Energia będzie wykorzystywana na potrzeby własne obiektu. (Polish)
    0 references
    The substantive scope of the project includes the design, delivery, installation, commissioning and implementation of the procedure for the integration into the DSO system of a photovoltaic installation at the sewage treatment plant in Imielin. 290 Wp modules with a total power of 146.16 kWp were used. The planned photovoltaic installation is located on the ground and will produce about 3.2 MWh of electricity per year. It consists of 504 290Wp photovoltaic modules each module. Photovoltaic modules will work with 5 inverters (inverters) with a power of 20 kW and 30 kW. The electricity produced will be supplied to the building’s internal energy grid. The energy will be used for the own needs of the facility. (English)
    0 references
    WOJ.: ŚLĄSKIE, POW.: bieruńsko-lędziński
    0 references

    Identifiers

    RPSL.04.01.01-24-02A9/20
    0 references