Management of rainwater through the construction of rainwater drainage and reservoirs in Białystok (Q85097)

From EU Knowledge Graph
Revision as of 16:36, 30 November 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): L’objectif principal du projet est d’améliorer le système de gestion des eaux de pluie dans la ville de Białystok, qui n’est pas adapté à l’évolution des conditions climatiques. Le champ d’application matériel du projet est: 1. Travaux de construction comprenant: La tâche no 1 consiste à construire un système d’eau de pluie à l’intersection des rues Al. Jean-Paul II — Forces armées nationales; Tâche no 2 construction d’un réservoir de rétention...)
Jump to navigation Jump to search
Project Q85097 in Poland
Language Label Description Also known as
English
Management of rainwater through the construction of rainwater drainage and reservoirs in Białystok
Project Q85097 in Poland

    Statements

    0 references
    12,084,591.69 zloty
    0 references
    2,900,302.01 Euro
    13 January 2020
    0 references
    14,217,166.7 zloty
    0 references
    3,412,120.01 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    31 August 2020
    0 references
    MIASTO BIAŁYSTOK
    0 references
    0 references
    0 references
    Celem głównym projektu jest poprawa systemu gospodarowania wodami opadowymi w Mieście Białystok niedostosowanym do zmieniających się warunków klimatycznych. Do zakresu rzeczowego projektu należą: 1. Roboty budowlane obejmujące: Zadanie nr 1 budowa kanalizacji deszczowej na skrzyżowaniu ulic Al. Jana Pawła II - Narodowych Sił Zbrojnych; Zadanie nr 2 budowa zbiornika retencyjnego przy ul. Kleeberga ; Zadanie nr 3 budowa zespołu urządzeń podczyszczających ul. Łagodna; Zadanie nr 4 budowa kanalizacji deszczowej na ul. Polnej; Zadanie nr 5 budowa przepustu na ul. Wiewiórczej; Zadanie nr 6 budowa kanału deszczowego (wzdłuż torów) na ul Sitarskiej. 2. Promocja projektu obejmująca - dostawę i montaż 6 tablic informacyjnych i 6 tablic pamiątkowych. (Polish)
    0 references
    The main objective of the project is to improve the rainwater management system in Białystok, which is not adapted to changing climatic conditions. The project’s material scope includes: 1. Construction works including: Task 1 to build rainwater drains at the intersection of Al Streets. John Paul II – National Armed Forces; Task No. 2 construction of storage tank at ul. Mr Kleeberg; Task No. 3 to build a team of cleaning appliances ul. It’s mild; Task No. 4 to build rainwater drainage on ul. Field; Task No. 5 to build a culvert on ul. A squirrel; Task No. 6 to build a rain canal (along the tracks) on Sitarska Street. 2. Project promotion including delivery and installation of 6 information boards and 6 commemorative plaques. (English)
    14 October 2020
    0 references
    L’objectif principal du projet est d’améliorer le système de gestion des eaux de pluie dans la ville de Białystok, qui n’est pas adapté à l’évolution des conditions climatiques. Le champ d’application matériel du projet est: 1. Travaux de construction comprenant: La tâche no 1 consiste à construire un système d’eau de pluie à l’intersection des rues Al. Jean-Paul II — Forces armées nationales; Tâche no 2 construction d’un réservoir de rétention à ul. Kleeberg; Tâche no 3 de construire un ensemble d’équipements de nettoyage sur ul. Doux; Tâche no 4 de construire un système d’eau de pluie sur ul. Champ; Tâche no 5 pour construire un ponceau à ul. Écureuil; Tâche no 6 de construire un canal de pluie (le long des voies ferrées) sur la rue Sitarska. 2. Promotion du projet, y compris la prestation et l’installation de 6 panneaux d’information et de 6 conseils commémoratifs. (French)
    30 November 2021
    0 references

    Identifiers

    POIS.02.01.00-00-0022/18
    0 references