Project Q80137 in Poland
Language Label Description Also known as
English
Development of an innovative zinc recovery technology in a downstream process from mixtures of metallurgical waste together with treatment of post-processing slags for the form of a substitute for poor iron ore
Project Q80137 in Poland

    Statements

    0 references
    12,000,000.0 zloty
    0 references
    2,880,000.0 Euro
    13 January 2020
    0 references
    30,000,000.0 zloty
    0 references
    7,200,000.0 Euro
    13 January 2020
    0 references
    40.0 percent
    0 references
    1 March 2018
    0 references
    31 August 2020
    0 references
    ZAKŁADY GÓRNICZO-HUTNICZE "BOLESŁAW" SPÓŁKA AKCYJNA
    0 references
    0 references

    50°15'39.6"N, 19°26'10.3"E
    0 references
    Celem Projektu jest demonstracja i walidacja w warunkach operacyjnych innowacyjnej technologii odzysku cynku w procesie przewałowym z mieszanin odpadów hutniczych wraz z uzdatnieniem żużli poprocesowych do postaci substytutu ubogiej rudy żelaza (KIS 10). Rezultat Projektu stanowić będzie innowację procesową w skali świata i wydatnie przyczyni się do poprawy efektywności zagospodarowania odpadów przeróbczych z hutnictwa cynku i stali w procesie przewałowym, a tym samym do podniesienie konkurencyjności polskiego hutnictwa cynku na rynkach światowych. Wdrożenie rezultatów Projektu będzie zarazem stanowić przełom w sektorze stalowym, gdyż dodatkowym efektem, dzięki wykorzystaniu szlamów stalowniczych w mieszance wsadowej, będzie otrzymywanie żużla będącego substytutem ubogiej rudy żelaza zdatnego do produkcji stali, co stworzy dla całej branży możliwość efektywnego ekonomicznie zagospodarowania składowisk szlamów stalowniczych. W celu weryfikacji autorskiej koncepcji technologii, wypracowanej w toku wieloletnich badań i symulacji, uzyskanie ostatecznego potwierdzenia jej skuteczności jest możliwe jedynie w drodze prób i testów optymalizacyjnych w skali zbliżonej do przemysłowej, na obecnej infrastrukturze technologicznej Spółki (przemysłowe piece przewałowe). Wdrożenie rezultatów Projektu nastąpi w Zakładzie Wnioskodawcy w Bukownie, w woj. małopolskim, przyczyniając się do rozwoju gospodarczego i podniesienia konkurencyjności polskiej gospodarki. Spółka zabezpieczyła niezbędne zasoby do realizacji Projektu, w tym pozyskała Podwykonawcę – IMN w Gliwicach. Spółka posiada wyłączne prawa własności intelektualnej niezbędne do realizacji Projektu i wdrożenia jego rezultatów, jednocześnie zakłada dyfuzję innowacji na zewnątrz poprzez współpracę z licznymi przedsiębiorstwami. Rezultaty P (Polish)
    0 references
    The aim of the project is to demonstrate and validate under operational conditions innovative zinc recovery technology in the overflow process of metallurgical waste mixtures together with the treatment of post-processing slags for the form of a poor iron ore substitute (KIS 10). The result of the project will be a process innovation in the world and will contribute significantly to improving the efficiency of processing waste from zinc and steel metallurgy in the downstream process, thus increasing the competitiveness of the Polish zinc metallurgy on global markets. The implementation of the project’s results will also constitute a breakthrough in the steel sector, as the additional effect, thanks to the use of steel sludges in the batch mix, will be to obtain slag as a substitute for poor iron ore suitable for steel production, which will create the possibility for the entire industry to efficiently manage steel sludge landfills. In order to verify the proprietary concept of technology developed in the course of many years of research and simulation, it is possible to obtain a final confirmation of its effectiveness only by means of tests and optimisation tests on a scale similar to the industrial scale, on the present technological infrastructure of the Company (industrial industrial furnaces). Implementation of the project results will take place in the Applicant’s Plant in Bukowno, Małopolska Voivodeship, contributing to economic development and improving the competitiveness of the Polish economy. The Company secured the necessary resources for the implementation of the Project, including the Subcontractor – IMN in Gliwice. The Company has exclusive intellectual property rights necessary to implement the Project and implement its results, at the same time it assumes the diffusion of innovations outside through cooperation with numerous companies. Results P (English)
    14 October 2020
    0 references
    L’objectif du projet est de démontrer et de valider dans des conditions opérationnelles une technologie innovante pour la récupération du zinc dans le processus de renversement à partir de mélanges de déchets métallurgiques et le traitement des scories post-traitement sous la forme d’un substitut du minerai de fer pauvre (KIS 10). Le projet aboutira à une innovation de procédé à l’échelle mondiale et contribuera de manière significative à améliorer l’efficacité du traitement des déchets de la métallurgie du zinc et de l’acier dans le processus de renversement, augmentant ainsi la compétitivité de la métallurgie du zinc polonaise sur les marchés mondiaux. La mise en œuvre des résultats du projet constituera également une percée dans le secteur de l’acier, car un effet supplémentaire, grâce à l’utilisation de boues d’acier dans le mélange de lots, consistera à obtenir du laitier en remplacement du minerai de fer pauvre adapté à la production d’acier, ce qui donnera à l’ensemble de l’industrie la possibilité de gérer efficacement les décharges de boues d’acier. Afin de vérifier le concept original de technologie développé au cours de nombreuses années de recherche et de simulation, il n’est possible d’obtenir une confirmation définitive de son efficacité qu’au moyen de tests d’optimisation et de tests à une échelle similaire à l’échelle industrielle, sur l’infrastructure technologique actuelle de l’entreprise (fourneaux de renversement industriels). La mise en œuvre des résultats du projet aura lieu dans l’usine de la requérante à Bukowno, dans la province de Małopolska, ce qui contribuera au développement économique et améliorera la compétitivité de l’économie polonaise. La société a obtenu les ressources nécessaires à la mise en œuvre du projet, y compris l’obtention d’un sous-traitant – IMN à Gliwice. La Société détient les droits exclusifs de propriété intellectuelle nécessaires à la mise en œuvre du projet et à la mise en œuvre de ses résultats, tout en assurant la diffusion de l’innovation à l’extérieur par la coopération avec de nombreuses entreprises. Résultats P (French)
    30 November 2021
    0 references
    Ziel des Projekts ist es, unter betrieblichen Bedingungen eine innovative Technologie zur Rückgewinnung von Zink im Roll-over-Verfahren aus Gemischen aus metallurgischen Abfällen und die Behandlung von Nachprozessschlacken in Form eines Ersatzes für schlechtes Eisenerz (KIS 10) zu demonstrieren und zu validieren. Das Ergebnis des Projekts wird eine Prozessinnovation im globalen Maßstab sein und wesentlich dazu beitragen, die Effizienz der Verarbeitung von Abfällen aus Zink- und Stahlmetallurgie im Roll-over-Verfahren zu verbessern und damit die Wettbewerbsfähigkeit der polnischen Zinkmetallurgie auf den Weltmärkten zu erhöhen. Die Umsetzung der Projektergebnisse wird auch einen Durchbruch im Stahlsektor darstellen, da ein zusätzlicher Effekt durch den Einsatz von Stahlschlamm im Chargenmix darin besteht, Schlacke als Ersatz für schlechtes Eisenerz zu erhalten, das für die Stahlproduktion geeignet ist, wodurch die gesamte Industrie die Möglichkeit bietet, Stahlschlammdeponien effizient zu verwalten. Um das ursprüngliche Konzept der Technologie zu überprüfen, das im Laufe von vielen Jahren der Forschung und Simulation entwickelt wurde, ist es möglich, die Wirksamkeit nur durch Optimierungstests und Tests auf einem dem industriellen Maßstab ähnlichen Maßstab auf der aktuellen technologischen Infrastruktur des Unternehmens (industrielle Umsturzöfen) zu bestätigen. Die Projektergebnisse werden im Werk des Antragstellers in Bukowno (Provinz Małopolska) umgesetzt, was zur wirtschaftlichen Entwicklung und zur Verbesserung der Wettbewerbsfähigkeit der polnischen Wirtschaft beiträgt. Das Unternehmen sicherte die notwendigen Ressourcen für die Durchführung des Projekts, einschließlich der Beschaffung eines Subunternehmers – IMN in Gliwice. Das Unternehmen besitzt die ausschließlichen Rechte an geistigem Eigentum, die für die Durchführung des Projekts und die Umsetzung seiner Ergebnisse erforderlich sind, während es die Verbreitung von Innovationen nach außen durch Zusammenarbeit mit zahlreichen Unternehmen übernimmt. Ergebnisse P (German)
    7 December 2021
    0 references

    Identifiers

    POIR.01.02.00-00-0206/17
    0 references