Revision as of 21:13, 30 November 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): Le projet consiste en la construction de la voie express S5 sur l’odc. Nouveaux rêves — Bydgoszcz longueur totale 73,84 km, situé dans le centre-nord de la Pologne et passant par la voïvodie de Kujawsko-Pomorskie. Cette section est située dans le réseau global RTE-T. Grâce à la mise en œuvre du projet en 2019, l’indicateur de réalisation — la construction de 73,84 km de nouvelles routes sera atteint. Le projet se compose de 4 sections (contrats)...)
Jump to navigation Jump to search
Project Q85936 in Poland
Language Label Description Also known as
English
Construction of the S5 expressway. Nowy Marzy – Bydgoszcz
Project Q85936 in Poland

    Statements

    0 references
    0 references
    0 references
    1,083,417,200.5 zloty
    0 references
    260,020,128.12 Euro
    13 January 2020
    0 references
    1,274,608,471.18 zloty
    0 references
    305,906,033.08 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    31 December 2021
    0 references
    GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD
    0 references

    53°11'31.9"N, 17°49'31.8"E
    0 references

    53°28'51.2"N, 18°25'36.8"E
    0 references
    Przedsięwzięcie polega na budowie drogi ekspresowej S5 na odc. Nowe Marzy - Bydgoszcz o łącznej dł. 73,84 km, zlokalizowanej w północno–środkowej części Polski i przebiegającej przez obszar województwa kujawsko - pomorskiego. Przedmiotowy odcinek zlokalizowany jest w sieci kompleksowej TEN-T. W wyniku realizacji projektu w 2019 r. zostanie osiągnięty wskaźnik produktu – wybudowanie 73,84 km nowych dróg. Projekt składa się z 4 odcinków (kontraktów): 1: Projekt i budowa drogi ekspresowej S5 na odc. od w. „Nowe Marzy” (bez węzła) do w. „Dworzysko” (z węzłem) o dł. ok. 23,3 km; od km 1+798,08 do km 25+108,48, 2: Projekt i budowa drogi ekspresowej S5 na odc. od w. „Dworzysko” (bez węzła) do w. „Aleksandrowo” (z węzłem) o dł. ok. 22,4 km; od km -0+021,00 do km 22+339,41, 3 - Projekt i budowa drogi ekspresowej S5 na odc. od w. „Aleksandrowo” (z węzłem) do w. „Tryszczyn” (z węzłem) o dł. ok. 14,7 km; od km -0+015,43 do km 14+678,76, 4 - Projekt i budowa drogi ekspresowej S5 na odc. od w. „Tryszczyn” (bez węzła) do w. „Białe Błota” (bez węzła) o dł. ok. 13,5 km; od km 14+678,76 do km 28+151,79. Na całym odcinku drogi S5 przewidziano przekrój 2-jezdniowy z 2 pasami ruchu, z wyjątkiem fragmentu z jezdniami zbierająco-rozprowadzającymi, pasem dzielącym oraz pasem awaryjnym, dostosowany do prognozowanego poziomu ruchu. Założona rezerwa terenowa umożliwia dalszą rozbudowę przekroju drogi do 3 pasów ruchu w każdym kierunku. (Polish)
    0 references
    The project consists of the construction of the S5 expressway on pc. Nowy Marzy – Bydgoszcz with total length. 73.84 km, located in the north-central part of Poland and passing through the Kujawsko-Pomorskie Voivodeship. This section is located in the TEN-T comprehensive network. As a result of the project in 2019, the output indicator – construction of 73.84 km of new roads will be achieved. The project consists of 4 sections (contracts): 1: Design and construction of the S5 expressway from St. “Nowe Marzy” (without a junction) to “Dworzysko” (with a junction) approx. 23,3 km; from km 1 + 798.08 to km 25 + 108,48, 2: The design and construction of the S5 expressway from St. “Dworzysko” (without a junction) to “Aleksandrowo” (with a junction) approx. 22,4 km; from km -0+ 021.00 to km 22 + 339.41, 3 – Design and construction of the S5 expressway on the section from “Aleksandrowo” (with a junction) to “Tryszczyn” (with a junction) length approx. 14,7 km; from km -0+ 015.43 to km 14 + 678.76, 4 – Design and construction of the S5 express road at the intersection from “Tryszczyn” (without a junction) to the “White Błota” (without a junction) approx. 13,5 km; from km 14 + 678.76 to km 28 + 151,79. A 2-lane cross-section with 2 lanes is provided throughout the S5 road, with the exception of a section with collection and distribution routes, a dividing belt and an emergency lane, adapted to the projected traffic level. The established field reserve allows further extension of the cross-section of the road to 3 lanes in each direction. (English)
    14 October 2020
    0 references
    Le projet consiste en la construction de la voie express S5 sur l’odc. Nouveaux rêves — Bydgoszcz longueur totale 73,84 km, situé dans le centre-nord de la Pologne et passant par la voïvodie de Kujawsko-Pomorskie. Cette section est située dans le réseau global RTE-T. Grâce à la mise en œuvre du projet en 2019, l’indicateur de réalisation — la construction de 73,84 km de nouvelles routes sera atteint. Le projet se compose de 4 sections (contrats): 1: Conception et construction de l’autoroute S5 de «Nowe Marzy» (sans jonction) à «Dworzysko» (avec une jonction) env. 23,3 km; du km 1+ 798.08 au km 25+ 108,48, 2: Conception et construction de l’autoroute S5 du c. «Dworzysko» (sans la jonction) au «Aleksandrovovo» c. 22,4 km; du km -0 + 021,00 au km 22 + 339.41, 3 — Conception et construction de l’autoroute S5 sur la section du c. «Aleksandrovo» (avec une jonction) au w. «Tryszczyn» (avec une jonction) environ. 14,7 km; du km -0+ 015.43 au km 14 + 678.76, 4 — Conception et construction de l’autoroute S5 sur la section du c. «Tryszczyn» (sans la jonction) au w. «Białe Błota» (sans nœud) environ. 13,5 km; du km 14 + 678.76 au km 28 + 151,79. Pour l’ensemble du tronçon de la route S5, il y a un tronçon à 2 voies avec 2 voies, à l’exception du tronçon de collecte et de distribution des chaussées, de la voie de partage et de la voie d’urgence, adapté au niveau de trafic prévu. La réserve hors route établie permet d’étendre le tronçon routier à 3 voies dans chaque direction. (French)