(‎Created claim: summary (P836): The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018., translated_summary)
Property / summary
 
The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English)
Property / summary: The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English) / rank
 
Normal rank
Property / summary: The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English) / qualifier
 
point in time: 7 July 2021
Timestamp+2021-07-07T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 09:52, 7 July 2021

Project Q2877804 in Portugal
Language Label Description Also known as
English
No label defined
Project Q2877804 in Portugal

    Statements

    0 references
    51,859.14 Euro
    0 references
    85.0 percent
    0 references
    21 August 2017
    0 references
    31 December 2019
    0 references
    MUNICÍPIO DE ALMEIDA
    0 references

    40°43'48.65"N, 6°53'58.92"W
    0 references
    A empreitada consignada a 21-08-2017, com a primeira fatura emitida a 7-11-2017, tinha o fim previsto para 18/05/2017. Porém o significativo atraso na montagem das instalações provisórias e respetivas infraestruturas dos Serviços das Finanças (concluída a 31-12-2017) condicionaram o andamento dos trabalhos. A situação está justificada e assinalada na Informação Interna da Câmara Municipal de 24/05/2018. (Portuguese)
    0 references
    The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English)
    7 July 2021
    0 references
    Almeida, Almeida
    0 references

    Identifiers

    CENTRO-07-2316-FEDER-000068
    0 references