(Created claim: summary (P836): The project will consist of the installation of a 26 kW photovoltaic installation in the ‘Sowarp Uroczysko’ building in Firleju (21-136 Firleu, Serock 35, parcel number 458/3). The purpose of the project is to improve the competitiveness of the company by reducing the cost of electricity. At present, the meeting does not have its own source of electricity and the entire demand is covered from the network by PGE Obacka S.A. The consumption of ele...) |
||
Property / summary | |||
The project will consist of the installation of a 26 kW photovoltaic installation in the ‘Sowarp Uroczysko’ building in Firleju (21-136 Firleu, Serock 35, parcel number 458/3). The purpose of the project is to improve the competitiveness of the company by reducing the cost of electricity. At present, the meeting does not have its own source of electricity and the entire demand is covered from the network by PGE Obacka S.A. The consumption of electricity in 2016 at the facility was more than 39 MWh. The installation planned for fitting should cover more than 2/3 of the needs, which will drastically reduce the annual cost of purchasing electricity. The panels will be mounted on the roof of the building by means of a special structure (steppe) made up of aluminium profiles. In total, 100 units of photovoltaic panels with a unit 260W power unit will be installed. In addition to the correct operation of the entire installation, it will be necessary to set up an inverter in the inverter and the boxes of the securities, together with the necessary cabling and connection to the electrical installation of the building. (English) | |||
Property / summary: The project will consist of the installation of a 26 kW photovoltaic installation in the ‘Sowarp Uroczysko’ building in Firleju (21-136 Firleu, Serock 35, parcel number 458/3). The purpose of the project is to improve the competitiveness of the company by reducing the cost of electricity. At present, the meeting does not have its own source of electricity and the entire demand is covered from the network by PGE Obacka S.A. The consumption of electricity in 2016 at the facility was more than 39 MWh. The installation planned for fitting should cover more than 2/3 of the needs, which will drastically reduce the annual cost of purchasing electricity. The panels will be mounted on the roof of the building by means of a special structure (steppe) made up of aluminium profiles. In total, 100 units of photovoltaic panels with a unit 260W power unit will be installed. In addition to the correct operation of the entire installation, it will be necessary to set up an inverter in the inverter and the boxes of the securities, together with the necessary cabling and connection to the electrical installation of the building. (English) / rank | |||
Normal rank |
Revision as of 09:27, 9 March 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a 26 kW photovoltaic installation at the ‘Sosnew Uroczysko’ meeting in Firleju |
Project in Poland financed by DG Regio |
Statements
86,898.5 zloty
0 references
164,438.7 zloty
0 references
65.0 percent
0 references
1 April 2018
0 references
30 June 2018
0 references
PRZEDSIĘBIORSTWO USŁUGOWO HANDLOWE ROGALSKA ANETA
0 references
Projekt polegał będzie na montażu instalacji fotowoltaicznej o mocy 26 kW w budynku zajazdu "Sosnowe Uroczysko" w Firleju (21-136 Firlej, Serocka 35, numer działki 458/3). Celem realizacji projektu jest poprawa konkurencyjności przedsiębiorstwa, poprzez obniżenie kosztów energii elektrycznej. W chwili obecnej budynek zajazdu nie posiada własnego źródła energii elektrycznej i całe zapotrzebowanie pokrywane jest z sieci przez PGE Obrót S.A. Zużycie energii elektrycznej w 2016 roku w obiekcie wyniosło ponad 39 MWh. Planowana do zamontowania instalacja powinna pokryć ponad 2/3 zapotrzebowania co radykalnie obniży roczne koszty zakupu energii elektrycznej. Panele zostaną zamontowane na dachu budynku za pomocą specjalnej konstrukcji (stelażu) złożonej z profili aluminiowych. Łącznie zamontowanych zostanie 100 szt. paneli fotowoltaicznych o mocy jednostkowej 260W. Dodatkowo do poprawnego działania całej instalacji konieczne będzie zamontowanie w budynku inwertera oraz skrzynek zabezpieczeń, wraz z niezbędnym okablowaniem i przyłączeniem do instalacji elektrycznej budynku. (Polish)
0 references
The project will consist of the installation of a 26 kW photovoltaic installation in the ‘Sowarp Uroczysko’ building in Firleju (21-136 Firleu, Serock 35, parcel number 458/3). The purpose of the project is to improve the competitiveness of the company by reducing the cost of electricity. At present, the meeting does not have its own source of electricity and the entire demand is covered from the network by PGE Obacka S.A. The consumption of electricity in 2016 at the facility was more than 39 MWh. The installation planned for fitting should cover more than 2/3 of the needs, which will drastically reduce the annual cost of purchasing electricity. The panels will be mounted on the roof of the building by means of a special structure (steppe) made up of aluminium profiles. In total, 100 units of photovoltaic panels with a unit 260W power unit will be installed. In addition to the correct operation of the entire installation, it will be necessary to set up an inverter in the inverter and the boxes of the securities, together with the necessary cabling and connection to the electrical installation of the building. (English)
0 references
Identifiers
RPLU.04.02.00-06-0003/17
0 references