Property / intervention field: Renewable energy: solar / rank | |||
Normal rank |
Revision as of 15:41, 24 October 2022
Project Q4427819 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Installation of photovoltaic cells for sewage treatment plants in Imielin |
Project Q4427819 in Poland |
Statements
517,905.0 zloty
0 references
115,130.28 Euro
0 references
609,300.0 zloty
0 references
135,447.39 Euro
0 references
85.0 percent
0 references
30 November 2017
0 references
30 November 2022
0 references
MIEJSKA SPÓŁKA KOMUNALNA SP. Z O.O.
0 references
Rzeczowy zakres projektu obejmuje zaprojektowanie, dostawę, montaż, uruchomienie i przeprowadzenie procedury włączenia do sieci OSD instalacji fotowoltaicznej przy obiekcie oczyszczalni ścieków w Imielinie. Zastosowano moduły o mocy 290 Wp o łącznej mocy 146,16 kWp. Projektowana instalacja fotowoltaiczna została usytuowana na gruncie i będzie produkować rocznie około 3,2 MWh energii elektrycznej. Składa się ona z 504 modułów fotowoltaicznych o mocy 290Wp każdy moduł. Moduły fotowoltaiczne będą współpracowały z 5 inwerterami (falownikami) o mocy 20kW i 30kW. Wyprodukowana energia elektryczna będzie dostarczana do wewnętrznej sieci energetycznej budynku. Energia będzie wykorzystywana na potrzeby własne obiektu. (Polish)
0 references
The substantive scope of the project includes the design, delivery, installation, commissioning and implementation of the procedure for the integration into the DSO system of a photovoltaic installation at the sewage treatment plant in Imielin. 290 Wp modules with a total power of 146.16 kWp were used. The planned photovoltaic installation is located on the ground and will produce about 3.2 MWh of electricity per year. It consists of 504 290Wp photovoltaic modules each module. Photovoltaic modules will work with 5 inverters (inverters) with a power of 20 kW and 30 kW. The electricity produced will be supplied to the building’s internal energy grid. The energy will be used for the own needs of the facility. (English)
0 references
WOJ.: ŚLĄSKIE, POW.: bieruńsko-lędziński
0 references
Identifiers
RPSL.04.01.01-24-02A9/20
0 references