Construction of sanitary sewer system in Dynów at ul. Bartkówka along with the construction of the passage under the San River by a sanitary channel and extension of the municipal sewage treatment plant with a photovoltaic installation (Q4417852): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in en: Setting new description) |
(Changed label, description and/or aliases in en, and other parts) |
||||||||||||||
label / en | label / en | ||||||||||||||
Construction of sanitary sewer system in Dynów at ul. Bartkówka along with the construction of the passage under the San River by a sanitary channel and extension of the municipal sewage treatment plant with a photovoltaic installation | |||||||||||||||
Property / summary | |||||||||||||||
The direct objective of the project is to increase the population using the waste water treatment system in the Dynów Agglomeration.The general objectives of the project are: increasing the quality of life of the inhabitants of the municipality, improving the attractiveness of the area for economic investments, reduced environmental pollution with particular emphasis on the San River.The subject of the project is the construction of a sanitary sewage system in Dynów at ul. Bartkówka along with the construction of a passage under the San River floor with a sanitary channel and an extension of the municipal sewage treatment plant with a photovoltaic installation with a power of 36.9 kWp. Due to the different terrain, it is predicted to use a gravity and pressure sewer system with 3 sewage network pumping stations and 1 home pumping station. All waste water from the area under consideration will flow to the sewage pumping station through gravitational channels. The compression cable will be made from the pumping station to the place of inclusion in the pressing sewage system. Using this sewage system, sewage will be pumped to the main pumping station located next to the building of the Volunteer Fire Service in Dynów, from which they will then be pressed to the sanitary sewer at ul. Beach and then to the municipal sewage treatment plant in Dynowo. The total length of the planned sewerage network as part of this task will be 14 326.50 m, including 13 220 m of gravitational network and 1 106.5 m of the discharge network. The number of sewage connections will be 194 pieces.As a result of the project, the volume of the wastewater load undergoing improved treatment will be 852 p.e. (English) | |||||||||||||||
Property / summary: The direct objective of the project is to increase the population using the waste water treatment system in the Dynów Agglomeration.The general objectives of the project are: increasing the quality of life of the inhabitants of the municipality, improving the attractiveness of the area for economic investments, reduced environmental pollution with particular emphasis on the San River.The subject of the project is the construction of a sanitary sewage system in Dynów at ul. Bartkówka along with the construction of a passage under the San River floor with a sanitary channel and an extension of the municipal sewage treatment plant with a photovoltaic installation with a power of 36.9 kWp. Due to the different terrain, it is predicted to use a gravity and pressure sewer system with 3 sewage network pumping stations and 1 home pumping station. All waste water from the area under consideration will flow to the sewage pumping station through gravitational channels. The compression cable will be made from the pumping station to the place of inclusion in the pressing sewage system. Using this sewage system, sewage will be pumped to the main pumping station located next to the building of the Volunteer Fire Service in Dynów, from which they will then be pressed to the sanitary sewer at ul. Beach and then to the municipal sewage treatment plant in Dynowo. The total length of the planned sewerage network as part of this task will be 14 326.50 m, including 13 220 m of gravitational network and 1 106.5 m of the discharge network. The number of sewage connections will be 194 pieces.As a result of the project, the volume of the wastewater load undergoing improved treatment will be 852 p.e. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The direct objective of the project is to increase the population using the waste water treatment system in the Dynów Agglomeration.The general objectives of the project are: increasing the quality of life of the inhabitants of the municipality, improving the attractiveness of the area for economic investments, reduced environmental pollution with particular emphasis on the San River.The subject of the project is the construction of a sanitary sewage system in Dynów at ul. Bartkówka along with the construction of a passage under the San River floor with a sanitary channel and an extension of the municipal sewage treatment plant with a photovoltaic installation with a power of 36.9 kWp. Due to the different terrain, it is predicted to use a gravity and pressure sewer system with 3 sewage network pumping stations and 1 home pumping station. All waste water from the area under consideration will flow to the sewage pumping station through gravitational channels. The compression cable will be made from the pumping station to the place of inclusion in the pressing sewage system. Using this sewage system, sewage will be pumped to the main pumping station located next to the building of the Volunteer Fire Service in Dynów, from which they will then be pressed to the sanitary sewer at ul. Beach and then to the municipal sewage treatment plant in Dynowo. The total length of the planned sewerage network as part of this task will be 14 326.50 m, including 13 220 m of gravitational network and 1 106.5 m of the discharge network. The number of sewage connections will be 194 pieces.As a result of the project, the volume of the wastewater load undergoing improved treatment will be 852 p.e. (English) / qualifier | |||||||||||||||
point in time: 21 October 2022
|
Revision as of 14:06, 21 October 2022
Project Q4417852 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of sanitary sewer system in Dynów at ul. Bartkówka along with the construction of the passage under the San River by a sanitary channel and extension of the municipal sewage treatment plant with a photovoltaic installation |
Project Q4417852 in Poland |
Statements
4,618,363.2 zloty
0 references
1,026,662.14 Euro
0 references
5,433,368.49 zloty
0 references
1,207,837.82 Euro
0 references
85.0 percent
0 references
28 November 2017
0 references
15 March 2023
0 references
GMINA MIEJSKA DYNÓW
0 references
Cel bezpośrednim projektu jest wzrost liczby ludności korzystającej z systemu oczyszczania ścieków w Aglomeracji Dynów.Cele ogólne projektu to : wzrost jakości życia mieszkańców gminy, poprawa atrakcyjności obszaru dla inwestycji gospodarczych, zmniejszone zanieczyszczenie środowiska naturalnego ze szczególnym uwzględnieniem rzeki San.Przedmiotem projektu jest budowa kanalizacji sanitarnej w Dynowie przy ul. Bartkówka wraz z budową przejścia pod dnem rzeki San kanałem sanitarnym i rozbudową miejskiej oczyszczalni ścieków o instalację fotowoltaiczną o mocy 36,9 kWp. Ze względu na zróżnicowane ukształtowanie terenu przewidywane jest zastosowanie systemu kanalizacji grawitacyjno-ciśnieniowego z 3 przepompowniami sieciowymi ścieków i 1 przepompownią przydomową. Wszystkie ścieki z rozpatrywanego terenu dopływały będą do przepompowni ścieków kanałami grawitacyjnymi. Przewód tłoczny wykonany będzie od przepompowni do miejsca włączenia w kanalizację tłoczną. Za pomocą tej kanalizacji ścieki przepompowywane będą do głównej przepompowni zlokalizowanej przy budynku Ochotniczej Straży Pożarnej w Dynowie, z której następnie tłoczone będą do kanalizacji sanitarnej przy ul. Plażowej a następnie do miejskiej oczyszczalni ścieków w Dynowie. Łączna długość planowanej do wykonania sieci kanalizacyjnej w ramach przedmiotowego zadania wynosić będzie 14 326,50 m, w tym 13 220 m sieci grawitacyjnej i 1 106,5 m sieci tłocznej. Ilość przyłączy kanalizacyjnych będzie wynosić 194 sztuki.W wyniku realizacji projektu wielkość ładunku ścieków poddanych ulepszonemu oczyszczaniu wyniesie 852 RLM. (Polish)
0 references
The direct objective of the project is to increase the population using the waste water treatment system in the Dynów Agglomeration.The general objectives of the project are: increasing the quality of life of the inhabitants of the municipality, improving the attractiveness of the area for economic investments, reduced environmental pollution with particular emphasis on the San River.The subject of the project is the construction of a sanitary sewage system in Dynów at ul. Bartkówka along with the construction of a passage under the San River floor with a sanitary channel and an extension of the municipal sewage treatment plant with a photovoltaic installation with a power of 36.9 kWp. Due to the different terrain, it is predicted to use a gravity and pressure sewer system with 3 sewage network pumping stations and 1 home pumping station. All waste water from the area under consideration will flow to the sewage pumping station through gravitational channels. The compression cable will be made from the pumping station to the place of inclusion in the pressing sewage system. Using this sewage system, sewage will be pumped to the main pumping station located next to the building of the Volunteer Fire Service in Dynów, from which they will then be pressed to the sanitary sewer at ul. Beach and then to the municipal sewage treatment plant in Dynowo. The total length of the planned sewerage network as part of this task will be 14 326.50 m, including 13 220 m of gravitational network and 1 106.5 m of the discharge network. The number of sewage connections will be 194 pieces.As a result of the project, the volume of the wastewater load undergoing improved treatment will be 852 p.e. (English)
21 October 2022
0 references
WOJ.: PODKARPACKIE, POW.: rzeszowski
0 references
Identifiers
RPPK.04.03.01-18-0026/17
0 references