(Created claim: summary (P836): The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English) | |||||||||||||||
Property / summary: The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English) / qualifier | |||||||||||||||
point in time: 7 July 2021
|
Revision as of 09:52, 7 July 2021
Project Q2877804 in Portugal
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q2877804 in Portugal |
Statements
51,859.14 Euro
0 references
85.0 percent
0 references
21 August 2017
0 references
31 December 2019
0 references
MUNICÍPIO DE ALMEIDA
0 references
A empreitada consignada a 21-08-2017, com a primeira fatura emitida a 7-11-2017, tinha o fim previsto para 18/05/2017. Porém o significativo atraso na montagem das instalações provisórias e respetivas infraestruturas dos Serviços das Finanças (concluída a 31-12-2017) condicionaram o andamento dos trabalhos. A situação está justificada e assinalada na Informação Interna da Câmara Municipal de 24/05/2018. (Portuguese)
0 references
The contract signed on 21-08-2017, with the first invoice issued on 7-11-2017, was due for 18/05/2017. However, the significant delay in setting up the temporary installations and their infrastructure of the Finance Services (completed 31-12-2017) made the progress of the work conditional. The situation is justified and marked in the Internal Information of the City Council of 24/05/2018. (English)
7 July 2021