Construction of 110 kV line to Korczowa station and 110/15kV Korczowa station to connect customers and sources of renewable energy from the border area of Korczowa border area. (Q84408)

From EU Knowledge Graph
Revision as of 07:48, 18 February 2020 by DG Regio (talk | contribs) (‎Changed an Item: Label in wikidata changed)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of 110 kV line to Korczowa station and 110/15kV Korczowa station to connect customers and sources of renewable energy from the border area of Korczowa border area.
Project in Poland financed by DG Regio

    Statements

    0 references
    7,281,092.36 zloty
    0 references
    1,747,462.1664 Euro
    13 January 2020
    0 references
    26,440,990.51 zloty
    0 references
    6,345,837.7224 Euro
    13 January 2020
    0 references
    36.43 percent
    0 references
    29 April 2016
    0 references
    31 December 2017
    0 references
    PGE DYSTRYBUCJA S.A.
    0 references
    Przedmiotem Projektu jest budowa 12,3 km linii napowietrznej 110 kV od istniejącego słupa nr 104 linii Munina - Lubaczów do stacji 110/15 kV Korczowa oraz budowa stacji 110/15 kV Korczowa w celu przyłączenia odbiorców oraz źródeł energii odnawialnej - Farmy Wiatrowej WEL LS-36 „Młyny”. Projekt będzie realizowany na obszarze woj. podkarpackiego: - budowa linii 110 kV - powiat Jarosław (gminy Radymno i Laszki) i powiat Lubaczów (gmina Wielkie Oczy) - budowa stacji 110/15 kV - powiat Jarosław, gmina Radymno (działka nr 123/60, arkusz 8, obręb nr 9, Młyny). Projektowana linia 110 kV jest linią dwutorową od istniejącego słupa nr 104 linii Munina - Lubaczów do stacji 110/15 kV Korczowa. (Polish)
    0 references

    Identifiers

    POIS.01.01.02-00-0001/16
    0 references