Construction and modernisation of the power grid with voltage SN and nn enabling connection of electricity generation units from RES in the commune Legnica, Legnickie Pole and Prochowice. (Q95407)

From EU Knowledge Graph
Revision as of 08:52, 29 October 2020 by DG Regio (talk | contribs) (‎Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement)
Jump to navigation Jump to search
Project Q95407 in Poland
Language Label Description Also known as
English
Construction and modernisation of the power grid with voltage SN and nn enabling connection of electricity generation units from RES in the commune Legnica, Legnickie Pole and Prochowice.
Project Q95407 in Poland

    Statements

    0 references
    2,073,850.09 zloty
    0 references
    497,724.02 Euro
    13 January 2020
    0 references
    2,503,138.31 zloty
    0 references
    600,753.19 Euro
    13 January 2020
    0 references
    82.85 percent
    0 references
    9 June 2016
    0 references
    31 December 2018
    0 references
    TAURON DYSTRYBUCJA S.A.
    0 references
    0 references
    ramach projektu „Budowa i modernizacja sieci elektroenergetycznej o napięciu SN i nN umożliwiająca przyłączanie jednostek wytwarzania energii elektrycznej z OZE na terenie gminy Legnica, Legnickie Pole i Prochowice” planowane są do realizacji roboty budowlane obejmujące 6 zadań:Zadanie 1 - Budowa sieci SN w miejscowości Legnica - LGS Przybków - R275-2-Lotnisko W ramach Zadania 1 powstanie: 4,74 km nowo wybudowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 2 - Modernizacja linii kablowej SN L-265 w miejscowości Legnica - L-265. W ramach Zadania 2 powstanie: 1,1 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 3 - Budową i modernizacją sieci SN w miejscowości Strachowice - L-263. W ramach zadania wybudowana zostanie linia napowietrzna SN 3xBLL- T- 70mm2, linia kablowa SN 3xXRUHAKXS1x120/25mm2 oraz linia napowietrzna SN GREENPAS 70mm2. Zmodernizowana będzie również słupowa stacja transformatorowa 20/0,4kV R-263-42. Demontażowi ulegnie linia napowietrzna SN AFL-6 3x35mm2, cechująca się mniejszym przekrojem przewodów.W ramach Zadania 3 powstanie: 2,43 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZEZadanie 4 - Modernizacja sieci SN w miejscowości Prochowice - L-262. Zmodernizowana zostanie linia kablowa SN na typu 3xXRUHAKXS 1x120/25 mm2.W ramach Zadania 4 powstanie:0,59 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE. Zadanie 5 - Budowa i modernizacja sieci SN w gminie Prochowice - L-261. Zmodernizowana i wybudowana zostanie linia kablowa SN na typu 3xXRUHAKXS 1x120/25 mm2.W ramach Zadania 5 powstanie:0,78 km nowo wybudowanej sieci elektroenergetycznej średniego napięcia dla OZE, 1,06 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE. Zadanie 6. Modernizacja sieci SN i nN w miejscowości Kwiatkowice - L-268 wraz z budową stacji transformatorowej 20/0,4kV W ramach Zadania 6 powstanie:0,69 km zmodernizowanej sieci elektroenergetycznej średniego napię (Polish)
    0 references
    as part of the project “Construction and modernisation of electricity grid with voltage of SN and nN, enabling connection of electricity generation units from RES in the commune Legnica, Legnickie Pole i Prochowice” are planned to carry out construction works covering 6 tasks:Task 1 – Construction of the SN network in Legnica – LGS Przybków – R275-2-Airport As part of Task 1, there will be: 4.74 km of newly built medium voltage power grid for RES Task 2 – Modernisation of cable line SN L-265 in Legnica – L-265. As part of Task 2, the following will be created: 1.1 km of modernised medium voltage power grid for RES Task 3 – Construction and modernisation of the SN network in Strachowice – L-263. The task will include an overhead line SN 3xBLL-T-70 mm², cable line SN 3xXRUHAKXS1x120/25 mm² and overhead line SN GREENPAS 70 mm². The 20/0.4 kV R-263-42 pole transformer station will also be modernised. The overhead line SN AFL-6 3x35 mm² will be dismantled, characterised by a smaller section of the cables. 2.43 km of modernised medium voltage power grid for RESTask 4 – Modernisation of the SN network in Prochowice – L-262. The cable line SN on type 3xXRUHAKXS 1x120/25 mm² will be modernised.As part of Task 4, there will be:0,59 km of modernised medium voltage power grid for RES. Task 5 – Construction and modernisation of the SN network in the commune of Prochowice – L-261. The SN cable line on type 3xXRUHAKXS 1x120/25 mm² will be modernised and built.As part of Task 5, there will be:0,78 km of newly built medium voltage electricity grid for RES, 1.06 km of modernised medium voltage electricity grid for RES. Task 6. Modernisation of the SN and nN network in Kwiatkowice – L-268 together with the construction of a 20/0.4 kV transformer station In the frame of Task 6, there will be: 0,69 km of modernised medium voltage power grid (English)
    15 October 2020
    0 references

    Identifiers

    RPDS.03.01.00-02-0121/16
    0 references