Construction of sewage system in Wieliczka Municipality – stage IV (Q85159)

From EU Knowledge Graph
Revision as of 06:37, 29 October 2020 by DG Regio (talk | contribs) (‎Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement)
Jump to navigation Jump to search
Project Q85159 in Poland
Language Label Description Also known as
English
Construction of sewage system in Wieliczka Municipality – stage IV
Project Q85159 in Poland

    Statements

    0 references
    108,940,352.0 zloty
    0 references
    26,145,684.48 Euro
    13 January 2020
    0 references
    128,165,120.0 zloty
    0 references
    30,759,628.8 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    6 May 2015
    0 references
    31 December 2023
    0 references
    GMINA WIELICZKA
    0 references
    0 references
    Projekt jest realizowany na terenie Gminy Wieliczka, na obszarze Aglomeracji Kraków o wielkości 925.500 RLM. Zakres projektu obejmuje: - budowę 98,74 km sieci kanalizacji sanitarnej, - budowę 8,30 km sieci wodociągowej, - budowę ok. 1,99 km kanalizacji deszczowej, - budowę ZUW w Wieliczce o wydajności 360 m3/h (w celu zaopatrywania ok. 30 tys. osób) wraz z ujęciem głębinowym, - budowę ZUW w Węgrzcach Wielkich o wydajności 108 m3/h (w celu zaopatrywania ok. 8 tys. osób) - modernizację ZUW w Bieżanowie, - budowę zbiorników wody "Sułków I i II" z hydroforniami. W wyniku realizacji projektu dostęp do zbiorczej sieci kanalizacji sanitarnej uzyska ok. 6.850 osób. (Polish)
    0 references
    The project is implemented in Wieliczka Municipality, in the area of the Kraków Agglomeration with a size of 925.500 RLM. The scope of the project includes: — construction of 98.74 km of sanitary sewage system, – construction of 8.30 km of water supply network, – construction of approx. 1.99 km of rainwater drainage, – construction of ZUW in Wieliczka with a capacity of 360 m³/h (to supply approx. 30, people) together with deep-sea shot, – construction of ZUW in Węgrzce Wielki with a capacity of 108 m³/h (to supply approx. 8 thousand people) – modernisation of ZUW in Bieżanów, – construction of water reservoirs “Sułków I and II” with hydrofornias. As a result of the project, approx. 6,850 people. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.02.03.00-00-0003/17
    0 references