Construction of the Ostrołęka — Stanisławów line, together with the construction of the station of the Wyszkow station and the expansion of the station within that line line (Q86104)
Jump to navigation
Jump to search
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of the Ostrołęka — Stanisławów line, together with the construction of the station of the Wyszkow station and the expansion of the station within that line line |
Project in Poland financed by DG Regio |
Statements
39,870,000.0 zloty
0 references
134,661,763.77 zloty
0 references
29.61 percent
0 references
1 January 2014
0 references
31 December 2023
0 references
POLSKIE SIECI ELEKTROENERGETYCZNE S.A
0 references
Przedmiotem projektu jest budowa dwutorowej linii elektroenergetycznej wysokiego napięcia 400kV o długości 110 km (220 km sieci prądowej) na odcinku Ostrołęka - Stanisławów. W tym odcinku zostanie wybudowana jedna stacja 400 (220)/110 kV Wyszków i rozbudowane dwie stacje: 400/220/110 kV Ostrołęka oraz 400 kV Stanisławów. Celem Projektu jest poprawa pewności i bezpieczeństwa pracy Krajowego Systemu Elektroenergetycznego w północno-wschodniej części Polski, poprawa pewności zasilania aglomeracji warszawskiej oraz sieci 110 kV Pośrednim celem Projektu jest: a) stworzenie warunków do zwiększenia możliwości wymiany energii elektrycznej z litewskim systemem elektroenergetycznym przy zapewnieniu bezpiecznej pracy tego połączenia b) stworzenie warunków do wyprowadzenia mocy z konwencjonalnych i odnawialnych źródeł energii (Polish)
0 references
The subject of the project is the construction of a two-track high voltage power line of 400 kV with a length of 110 km (220 km of electricity network) on the Ostrołęka-Stanisławów section. In this section, one station 400 (220)/110 kV Wyszków will be built and two stations will be expanded: 400/220/110 kV Ostrołęka and 400 kV Stanisławów. The aim of the project is to improve the safety and safety of the National Power System in the north-eastern part of Poland, to improve the power supply of the Warsaw agglomeration and the 110 kV network The indirect objective of the project is: a) creating the conditions for increasing the possibility of electricity exchanges with the Lithuanian electricity system while ensuring the safe operation of this connection (b) creating the conditions for power decommissioning from conventional and renewable energy sources (English)
14 October 2020
0 references
Identifiers
POIS.07.01.00-00-0002/18
0 references