Construction of a sanitary sewage system in the streets of: Skierniewice, the works station, the Gryfino, the parts of the market of the market and the town of Tyleft, and the reconstruction of the waste water treatment plants in the Basens. (Q137907)

From EU Knowledge Graph
Revision as of 14:45, 24 September 2020 by DG Regio (talk | contribs) (‎Removed claim: EU contribution (P835): 1,997,827.9031999998 euro)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a sanitary sewage system in the streets of: Skierniewice, the works station, the Gryfino, the parts of the market of the market and the town of Tyleft, and the reconstruction of the waste water treatment plants in the Basens.
Project in Poland financed by DG Regio

    Statements

    0 references
    8,324,282.93 zloty
    0 references
    9,793,274.2 zloty
    0 references
    2,350,385.81 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 April 2016
    0 references
    30 September 2020
    0 references
    GMINA BANIE
    0 references
    0 references
    Przedmiotem projektu jest budowa kanalizacji sanitarnej w Baniach w zakresie ulic: Baniewickiej, Dworcowej, Gryfińskiej, części ulicy Targowej i w miejscowości Tywica oraz przebudowa Oczyszczalni ścieków w Baniach. Realizację projektu podzielono na następujące wydatki: Zadanie nr 1. Prace przygotowawcze Zadanie nr 2. Prace budowlane przy Oczyszczalni ścieków Zadanie nr 3. Prace technologiczne Zadanie nr 4. Wykonanie sieci kanalizacji sanitarnej Zadanie nr 5. Zarządzanie projektem i promocja Okres realizacji projektu: wrzesień 2018 r. – grudzień 2019 r. Projekt ma charakter stacjonarny. Realizacja projektu będzie mieścić się w granicach Aglomeracji Banie, ujętej w V Aktualizacji KPOŚK. (Polish)
    0 references
    The object of the project is the construction of a sewerage system in the streets: Skierniewice, the works station, the Gryfino, the parts of the market of the market and the town of Tyleft, and the reconstruction of the waste water treatment plants in the Basens. The implementation of the project is divided into the following expenditure: Task 1. Preparatory work No 2. Construction work at OWWTP Task No 3. Technological work Task 4. Implementation of Task No 5. Project management and promotion period: September 2018 — December 2019. the project is stationary. The implementation of the project will be within the boundaries of the agglomeration of Breking in V. (English)
    0 references

    Identifiers

    RPZP.03.06.00-32-C006/17
    0 references