Construction of an urban park in a factory in Łomianki (Q85735)

From EU Knowledge Graph
Revision as of 20:41, 15 July 2020 by DG Regio (talk | contribs) (‎Changed an Item)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of an urban park in a factory in Łomianki
Project in Poland financed by DG Regio

    Statements

    0 references
    4,786,945.05 zloty
    0 references
    1,148,866.812 Euro
    13 January 2020
    0 references
    5,631,700.09 zloty
    0 references
    1,351,608.02 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    30 November 2018
    0 references
    GMINA ŁOMIANKI
    0 references
    0 references

    52°20'7.8"N, 20°53'42.0"E
    0 references
    Projekt polega na budowie parku miejskiego przy jez. Fabrycznym w Łomiankach na terenach uprzednio poddanych rekultywacji wraz z renowacją cieku wodnego wymagającego zagospodarowania pod kątem hydrologicznym i hydrotechnicznym.Podstawowym celem projektu jest przywrócenie wartości przyrodniczych obszaru wokół jez. F. poprzez utworzenie nowej zielonej przestrzeni publicznej służącej celom środowiskowym i społecznym. Zakres projektu obejmuje płn-wsch część gminy należącej do WOF.Obszar objęty projektem wynosi 6,57 ha. Tereny te obecnie określone są jako nieużytki w części zadrzewione, które tworzą niezagospodarowaną, nieuporządkowaną przestrzeń o znacznym stopniu degradacji. Jez. ma zróżnicowaną szerokość (10-50 m). Projekt został podzielony na dwa etapy. Pierwszy rozpoczął się od prac rekultyw. (28/10/2015 – 15/12/2015) na terenach wokół jez. (ponadnorm. stężenia metali ciężkich - chromu, arsenu – pozostałość po zamkniętej garbarni, oraz baru, miedzi, niklu, ołowiu i cynku – efekt prowadzonych napraw prywatnych samochodów). (Polish)
    0 references
    The project consists of the construction of an urban park at Łomianki factory in land that has been cleaned up with the renovation of a watercourse that needs to be managed in a hydrological and hydrological environment. the main objective of the project is to restore the natural value of the area around the site. F. by creating a new green public space for environmental and social purposes.The project covers a proportion of the WOF.area owned by the WF.Area project area of 6.57 ha.These areas are currently defined as uncultivated land in wooded areas which form an unmanaged, heavily degraded area.If it has a differentiated width (10-50 m).The project has been divided into two phases.The first started from the development of the recovery.(28/10/2015-15/12/2015) in the area around the jez (above the concentration of heavy metals — chromium, arsenic — residue from the closed tannery, and barium, copper, nickel, lead and zinc — effect of repair of private cars). (English)
    0 references

    Identifiers

    POIS.02.05.00-00-0114/16
    0 references