Construction and modernisation of the power grid with voltage SN and nn enabling connection of units of electricity generation from RES in the commune of Żukowice, Kotla, Głogów, Polkowice and Lubin. (Q95414)

From EU Knowledge Graph
Revision as of 23:19, 27 October 2022 by DG Regio (talk | contribs) (‎Changed an Item: Edited by the materialized bot - inferring region from the coordinates)
Jump to navigation Jump to search
Project Q95414 in Poland
Language Label Description Also known as
English
Construction and modernisation of the power grid with voltage SN and nn enabling connection of units of electricity generation from RES in the commune of Żukowice, Kotla, Głogów, Polkowice and Lubin.
Project Q95414 in Poland

    Statements

    0 references
    1,680,593.91 zloty
    0 references
    373,596.03 Euro
    13 January 2020
    0 references
    2,071,738.06 zloty
    0 references
    460,547.37 Euro
    13 January 2020
    0 references
    81.12 percent
    0 references
    9 June 2016
    0 references
    21 June 2019
    0 references
    TAURON DYSTRYBUCJA S.A.
    0 references
    0 references

    51°40'16.57"N, 16°5'21.37"E
    0 references

    51°26'29.47"N, 16°15'27.14"E
    0 references

    51°29'58.88"N, 15°59'38.08"E
    0 references
    Przedmiot projektu: W ramach projektu „Budowa i modernizacja sieci elektroenergetycznej o napięciu SN i nN umożliwiająca przyłączanie jednostek wytwarzania energii elektrycznej z OZE na terenie gminy Żukowice, Kotla, Głogów, Polkowice i Lubin” planowane są do realizacji roboty budowlane obejmujące 5 zadań: Zadanie 1 - Modernizacja sieci SN w gminie Żukowice - L-812 w zakresie: przebudowy linii napowietrznej SN 3xBLL-T 70 mm2 i 3xBLL-T 50 mm2, montażu linii kablowej SN 3xXRUHAKXS 1x240/25 mm2 W ramach Zadania 1 powstanie: 3,2 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 2 - Modernizacja sieci SN w gminie Kotla L-805 w zakresie: demontażu obecnej linii napowietrznej i przebudowy na linię kablową SN 3xXRUHAKXS 1x120/25 mm2 oraz budowy dwóch złączy kablowych SN. W ramach Zadania 2 powstanie: 2,3 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 3 - Modernizacja sieci SN w miejscowości Głogów L-814 na linię typu 3x XRUHAKXS 1x120/25mm2 W ramach Zadania 3 powstanie: 0,9 km zmodernizowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 4 - Budowa powiązania SN relacji L-404 z GPZ-POLKOWICE STREFA do R-917-2 w miejscowości Polkowice L-404 w zakresie budowy linii SN typu 3x XRUHAKXS 1x120/25mm2 W ramach Zadania 4 powstanie: 1,2 km nowobudowanej sieci elektroenergetycznej średniego napięcia dla OZE Zadanie 5 - Budowa sieci SN w miejscowości Osiek - Kłopotów L-961-40 i L-953 w zakresie: budowa linii kablowej SN 20 kV XRUHAKXS 1x120mm2/25mm2 oraz zabudowy szafki telemechaniki. W ramach Zadania 5 powstanie: 2,1 km nowobudowanej sieci elektroenergetycznej średniego napięcia dla OZE Celem projektu jest umożliwienie przyłączenia do sieci TAURON Dystrybucja 15 elektrowni OZE o potencjalnej mocy 12.753 kW oraz przyszłych wnioskodawców o przyłączenie OZE. Zrealizowanie tych przyłączeń nie jest możliwe bez realizacji przedmiotowego projektu, ze względu na brak wystarczając (Polish)
    0 references
    Subject matter of the project: As part of the project “Construction and modernisation of the power grid with SN and nN voltages enabling connection of electricity generation units from RES in the commune of Żukowice, Kotla, Głogów, Polkowice and Lubin” the construction works covering 5 tasks are planned: Task 1 – Modernisation of the SN network in Żukowice commune – L-812 in the scope of: reconstruction of overhead line SN 3xBLL-T 70 mm² and 3xBLL-T 50 mm², installation of cable line SN 3xXXRUHAKXS 1x240/25 mm² As part of Task 1 will be created: 3.2 km of modernised medium voltage electricity grid for RES Task 2 – Modernisation of the SN network in Kotla L-805 commune in the scope of: dismantling the current overhead line and conversion into the cable line SN 3xXXRUHAKXS 1x120/25 mm² and the construction of two SN cable connectors. As part of Task 2, the following will be created: 2.3 km of modernised medium voltage electricity grid for RES Task 3 – Modernisation of the SN network in Głogów L-814 for a line of type 3x XRUHAKXS 1x120/25 mm² As part of Task 3 will be created: 0.9 km of modernised medium voltage power grid for RES Task 4 – Construction of the connection of SN between L-404 and GPZ-Polkowice STREFA to R-917-2 in Polkowice L-404 in the scope of construction of SN line type 3x XRUHAKXS 1x120/25 mm² As part of Task 4, there will be: 1.2 km of newly built medium voltage electricity grid for RES Task 5 – Construction of the SN network in Osiek – Kłopotów L-961-40 and L-953 in the scope of: construction of cable line SN 20 kV XRUHAKXS 1x120 mm²/25 mm² and telemechanics cabinets. As part of Task 5, the following will be created: 2.1 km of newly built medium voltage electricity grid for RES The aim of the project is to enable connection to the TAURON network Distribution of 15 RES power plants with a potential power of 12.753 kW and future applicants for RES connection. These connections cannot be realised without the project being implemented, due to lack of sufficient (English)
    15 October 2020
    0 references
    Objet du projet: Dans le cadre du projet «Construction et modernisation du réseau électrique avec une tension de SN et de NN permettant le raccordement d’unités de production d’électricité à partir de SER dans les municipalités de Uukowice, Kotla, Głogów, Polkowice et Lubin», des travaux de construction comportant 5 tâches sont prévus pour: Activité 1 — Modernisation du réseau SN dans la commune de Žukowice — L-812 dans le cadre de: reconstruction de la ligne aérienne SN 3xBLL-T 70 mm² et 3xBLL-T 50 mm², montage de la ligne de câble SN 3xXRUHAKXS 1x240/25 mm² Dans le cadre de la réalisation de la tâche 1: 3,2 km de réseau électrique à moyenne tension modernisé pour la tâche SER 2 — Modernisation du réseau SN dans la commune de Kotla L-805 dans le cadre de: démontage de la ligne aérienne actuelle et conversion en ligne SN 3xXRUHAKXS 1x120/25 mm² et construction de deux connecteurs de câble SN. Dans le cadre de la tâche 2, les éléments suivants seront créés: Tâche 3 — Modernisation du réseau SN à Głogów L-814 pour 3x XRUHAKXS 1x120/25 mm² Dans le cadre de la création de la tâche 3: 0,9 km de réseau électrique à moyenne tension modernisé pour la tâche 4 RES — Construire la liaison entre SN entre L-404 et GPZ-POLKOWICE STREFA à R-917-2 à Polkowice L-404 pour la construction de la ligne 3x SN XRUHAKXS 1x120/25 mm² 1,2 km de réseau électrique à moyenne tension nouvellement construit pour la tâche SER 5 — Construction du réseau SN à Osiek — Kłopotów L-961-40 et L-953 dans le cadre: construction de la ligne de câble SN 20 kV XRUHAKXS 1x120 mm²/25 mm² et installation d’armoire télémécanique. Dans le cadre de la tâche 5, les éléments suivants seront créés: 2,1 km de réseau électrique moyenne tension nouvellement construit pour les SER L’objectif du projet est de permettre la connexion au réseau TAURON Distribution de 15 centrales SER d’une capacité potentielle de 12,753 kW et de futurs candidats au raccordement SER. Il n’est pas possible de réaliser ces connexions sans la mise en œuvre du projet en question, car il n’est pas suffisant (French)
    1 December 2021
    0 references
    Gegenstand des Projekts: Im Rahmen des Projekts „Bau und Modernisierung des Stromnetzes mit einer Spannung von SN und NN zur Anbindung von Stromerzeugungsanlagen aus RES in den Gemeinden Żukowice, Kotla, Głogów, Polkowice und Lubin“ sind Bauarbeiten mit 5 Aufgaben geplant für: Aktivität 1 – Modernisierung des SN-Netzes in der Gemeinde Żukowice – L-812 im Rahmen von: Rekonstruktion der Oberleitung SN 3xBLL-T 70 mm² und 3xBLL-T 50 mm², Montage der Kabellinie SN 3xXRUHAKXS 1x240/25 mm² Im Rahmen der Aufgabe 1 Erstellung: 3,2 km modernisiertes Mittelspannungsnetz für RES Task 2 – Modernisierung des SN-Netzes in der Gemeinde Kotla L-805 im Rahmen von: Demontage der Stromoberleitung und Umwandlung auf SN 3xXRUHAKXS 1x120/25 mm² Kabelleitung und Bau von zwei SN-Kabelanschlüssen. Im Rahmen von Aufgabe 2 wird Folgendes erstellt: Aufgabe 3 – Modernisierung des SN-Netzes in Głogów L-814 für 3x XRUHAKXS 1x120/25 mm² Im Rahmen der Erstellung von Aufgabe 3: 0,9 km modernisiertes Mittelspannungsnetz für RES Task 4 – Bau der Verbindung zwischen SN zwischen L-404 und GPZ-POLKOWICE STREFA nach R-917-2 in Polkowice L-404 für den Bau der 3x SN Linie XRUHAKXS 1x120/25 mm² 1,2 km neu gebautes Mittelspannungsnetz für RES Aufgabe 5 – Bau des SN-Netzes in Osiek – Kłopotów L-961-40 und L-953 im Rahmen von: Bau der Kabellinie SN 20 kV XRUHAKXS 1x120 mm²/25 mm² und Installation von Telemechanik-Schrank. Im Rahmen von Aufgabe 5 wird Folgendes erstellt: 2,1 km neu gebautes Mittelspannungsnetz für RES Ziel des Projekts ist es, den Anschluss an das TAURON-Netz zu ermöglichen Verteilung von 15 RES-Kraftwerken mit einer Kapazität von 12,753 kW und zukünftigen Antragstellern für den RES-Anschluss. Es ist nicht möglich, diese Verbindungen ohne die Durchführung des betreffenden Projekts zu realisieren, da es nicht ausreicht, (German)
    7 December 2021
    0 references
    Onderwerp van het project: In het kader van het project „Bouw en modernisering van het elektriciteitsnet met een spanning van SN en NN voor de aansluiting van elektriciteitscentrales uit hernieuwbare energiebronnen in de gemeenten Șukowice, Kotla, Głogów, Polkowice en Lubin” zijn bouwwerkzaamheden gepland voor: Activiteit 1 — Modernisering van het SN-netwerk in de gemeente Șukowice — L-812 binnen het toepassingsgebied van: reconstructie van bovenleiding SN 3xBLL-T 70 mm² en 3xBLL-T 50 mm², montage van kabelbaan SN 3xXRUHAKXS 1x240/25 mm² Als onderdeel van taak 1 creatie: 3,2 km gemoderniseerd middenspanningsnet voor RES Task 2 — Modernisering van het SN-netwerk in de gemeente Kotla L-805 binnen het toepassingsgebied van: het demonteren van de huidige bovenleiding en het omzetten naar SN 3xXRUHAKXS 1x120/25 mm² kabellijn en de bouw van twee SN-kabelconnectoren. In het kader van taak 2 wordt het volgende gecreëerd: Taak 3 — Modernisering van het SN-netwerk in Głogów L-814 voor 3x XRUHAKXS 1x120/25 mm² Als onderdeel van taak 3 creatie: 0,9 km gemoderniseerd middenspanningsnet voor RES taak 4 — Bouwen van de verbinding tussen SN tussen L-404 en GPZ-POLKOWICE STREFA naar R-917-2 in Polkowice L-404 voor de bouw van de 3x SN lijn XRUHAKXS 1x120/25 mm² 1,2 km nieuw aangelegd middenspanningsnet voor RES taak 5 — Bouw van het SN-netwerk in Osiek — Kłopotów L-961-40 en L-953 in het kader van: bouw van kabelbaan SN 20 kV XRUHAKXS 1x120 mm²/25 mm² en installatie van telemechanische kast. In het kader van taak 5 wordt het volgende gecreëerd: 2,1 km nieuw aangelegd middenspanningsnet voor RES Het doel van het project is de aansluiting op het TAURON-netwerk van 15 RES-centrales met een potentiële capaciteit van 12,753 kW en toekomstige aanvragers van RES-aansluitingen mogelijk te maken. Het is niet mogelijk om deze verbindingen uit te voeren zonder de uitvoering van het project in kwestie, omdat het niet voldoende is (Dutch)
    16 December 2021
    0 references
    Oggetto del progetto: Nell'ambito del progetto "Costruzione e ammodernamento della rete elettrica con una tensione di SN e NN che consente il collegamento di unità di produzione di energia da fonti rinnovabili nei comuni di Żukowice, Kotla, Głogów, Polkowice e Lubin", sono previsti lavori di costruzione che comportano 5 compiti per: Attività 1 — Ammodernamento della rete SN nel comune di Żukowice — L-812 nell'ambito di: ricostruzione della linea aerea SN 3xBLL-T 70 mm² e 3xBLL-T 50 mm², montaggio della linea cavo SN 3xXRUHAKXS 1x240/25 mm² Come parte della creazione task 1: 3,2 km di rete elettrica a media tensione modernizzata per il compito 2 delle fonti energetiche rinnovabili — Ammodernamento della rete SN nel comune di Kotla L-805 nell'ambito di: smantellamento dell'attuale linea aerea e conversione in linea di cavo SN 3xXRUHAKXS 1x120/25 mm² e costruzione di due connettori per cavi SN. Nell'ambito dell'attività 2, verranno creati i seguenti elementi: Compito 3 — Ammodernamento della rete SN a Głogów L-814 per 3x XRUHAKXS 1x120/25 mm² Nell'ambito della creazione del task 3: 0,9 km di rete elettrica a media tensione modernizzata per il compito 4 di RES — Costruire il collegamento tra SN tra L-404 e GPZ-POLKOWICE STREFA a R-917-2 a Polkowice L-404 per la costruzione della linea 3x SN XRUHAKXS 1x120/25 mm² 1,2 km di rete elettrica a media tensione di nuova costruzione per l'attività 5 FER — Costruzione della rete SN a Osiek — Kłopotów L-961-40 e L-953 nell'ambito di: costruzione della linea di cavi SN 20 kV XRUHAKXS 1x120 mm²/25 mm² e installazione di armadietti telemeccanici. Nell'ambito dell'attività 5, verranno creati i seguenti elementi: 2,1 km di rete elettrica a media tensione di nuova costruzione per le FER L'obiettivo del progetto è consentire il collegamento alla rete TAURON Distribuzione di 15 centrali elettriche da fonti rinnovabili con una capacità potenziale di 12,753 kW e futuri richiedenti per la connessione alle fonti energetiche rinnovabili. Non è possibile effettuare questi collegamenti senza l'attuazione del progetto in questione, perché non è sufficiente (Italian)
    16 January 2022
    0 references
    Objeto del proyecto: En el marco del proyecto «Construcción y modernización de la red eléctrica con una tensión de SN y NN que permite la conexión de unidades de generación de energía de fuentes de energía renovables en los municipios de δukowice, Kotla, Głogów, Polkowice y Lubin», se prevén obras de construcción que impliquen 5 tareas para: Actividad 1 — Modernización de la red SN en el municipio de δukowice — L-812 en el ámbito de: reconstrucción de la línea aérea SN 3xBLL-T 70 mm² y 3xBLL-T 50 mm², montaje de la línea de cable SN 3xXRUHAKXS 1x240/25 mm² Como parte de la tarea 1 creación: 3,2 km de red eléctrica modernizada de media tensión para RES Task 2 — Modernización de la red SN en el municipio de Kotla L-805 en el ámbito de: desmontaje de la línea aérea actual y conversión a línea de cable SN 3xXRUHAKXS 1x120/25 mm² y la construcción de dos conectores de cable SN. Como parte de la tarea 2, se creará lo siguiente: Tarea 3 — Modernización de la red SN en Głogów L-814 para 3x XRUHAKXS 1x120/25 mm² Como parte de la creación de la Tarea 3: 0,9 km de red eléctrica modernizada de media tensión para RES Task 4 — Construyendo el enlace entre SN entre L-404 y GPZ-POLKOWICE STREFA a R-917-2 en Polkowice L-404 para la construcción de la línea 3x SN XRUHAKXS 1x120/25 mm² 1,2 km de red eléctrica de media tensión de nueva construcción para RES Task 5 — Construcción de la red SN en Osiek — Kłopotów L-961-40 y L-953 en el ámbito de: construcción de línea de cable SN 20 kV XRUHAKXS 1x120 mm²/25 mm² e instalación de gabinete telemecánico. Como parte de la Tarea 5, se creará lo siguiente: 2,1 km de red eléctrica de media tensión de nueva construcción para RES El objetivo del proyecto es permitir la conexión a la red TAURON Distribución de 15 centrales de energía RES con una capacidad potencial de 12,753 kW y futuros solicitantes de conexión RES. No es posible llevar a cabo estas conexiones sin la ejecución del proyecto en cuestión, porque no es suficiente (Spanish)
    19 January 2022
    0 references
    Projektets genstand: Som en del af projektet âEUROpførelse og modernisering af elnettet med SN- og nN-spændinger, der muliggør tilslutning af elproduktionsenheder fra vedvarende energikilder i kommunen Å"ukowice, Kotla, GÅogów, Polkowice og Lubin" planlægges bygge- og anlægsarbejder, der dækker 5 opgaver: Opgave 1â EUR Modernisering af SN-netværket i Å"ukowice kommune â EUR L-812 inden for rammerne af: rekonstruktion af køreledning SN 3xBLL-T 70 mm² og 3xBLL-T 50 mm², installation af kabellinje SN 3xXXRUHAKXS 1x240/25 mm² Som en del af opgave 1 vil blive oprettet: 3,2 km moderniseret mellemspændingsnet til VE-opgave 2 â EUR Modernisering af SN-nettet i Kotla L-805 kommune inden for rammerne af: demontering af den aktuelle luftledning og konvertering til kabellinjen SN 3xXXRUHAKXS 1x120/25 mm² og konstruktionen af to SN kabelstik. Som en del af opgave 2 oprettes følgende: 2,3 km moderniseret mellemspændingsnet til VE-opgave 3 â EUR Modernisering af SN-nettet i GÅogów L-814 for en linje af type 3x XRUHAKXS 1x120/25 mm² Som en del af opgave 3 vil blive oprettet: 0,9 km moderniseret mellemspændingsnet til RES opgave 4 â EUR Opførelse af tilslutning af SN mellem L-404 og GPZ-Polkowice STREFA til R-917-2 i Polkowice L-404 i anvendelsesområdet for konstruktionen af SN linje type 3x XRUHAKXS 1x120/25 mm² Som en del af opgave 4, vil der være: 1,2 km nybygget mellemspændingsnet til VE-opgave 5 âEUR Opførelse af SN-nettet i Osiek âEUR KÅopotów L-961-40 og L-953 inden for rammerne af: konstruktion af kabellinje SN 20 kV XRUHAKXS 1x120 mm²/25 mm² og telemekanikskabe. Som en del af opgave 5 oprettes følgende: 2,1 km nybygget mellemspændingselnet til vedvarende energikilder Formålet med projektet er at muliggøre tilslutning til TAURON-nettet Distribution af 15 VE-kraftværker med en potentiel effekt på 12,753 kW og fremtidige ansøgere til VE-tilslutning. Disse forbindelser kan ikke realiseres, uden at projektet gennemføres, på grund af mangel på tilstrækkelige (Danish)
    26 July 2022
    0 references
    Αντικείμενο του σχεδίου: Στο πλαίσιο του έργου â EUR Κατασκευή και εκσυγχρονισμός του δικτύου ηλεκτρικής ενέργειας με SN και nN τάσεις που επιτρέπουν τη σύνδεση των μονάδων παραγωγής ηλεκτρικής ενέργειας από ΑΠΕ στην κοινότητα Å"ukowice, Kotla, GÅogów, Polkowice και Lubinâ EUR προγραμματίζονται οι κατασκευαστικές εργασίες που καλύπτουν 5 εργασίες: Έργο 1 âEUR Εκσυγχρονισμός του δικτύου SN στην κοινότητα Å"ukowice â EUR L-812 στο πεδίο εφαρμογής: ανακατασκευή της εναέριας γραμμής SN 3xBLL-T 70 mm² και 3xBLL-T 50 mm², εγκατάσταση καλωδιακής γραμμής SN 3xXXRUHAKXS 1x240/25 mm² Ως μέρος της εργασίας 1 θα δημιουργηθεί: 3,2 km εκσυγχρονισμένου δικτύου ηλεκτρικής ενέργειας μέσης τάσης για την εργασία ΑΠΕ 2 â EUR Εκσυγχρονισμός του δικτύου SN στην Kotla L-805 κοινότητα στο πεδίο εφαρμογής: αποσυναρμολόγηση της τρέχουσας εναέριας γραμμής και μετατροπή σε καλωδιακή γραμμή SN 3xXXRUHAKXS 1x120/25 mm² και κατασκευή δύο συνδέσμων καλωδίων SN. Στο πλαίσιο του έργου 2, θα δημιουργηθούν τα ακόλουθα: 2.3 χλμ εκσυγχρονισμένου δικτύου ηλεκτρικής ενέργειας μέσης τάσης για την εργασία ΑΠΕ 3 â EUR Εκσυγχρονισμός του δικτύου SN στο GÅogów L-814 για μια γραμμή τύπου 3x XRUHAKXS 1x120/25 mm² Ως μέρος της εργασίας 3 θα δημιουργηθεί: 0,9 km εκσυγχρονισμένου δικτύου ηλεκτρικής ενέργειας μέσης τάσης για RES Εργασία 4 â EUR Κατασκευή της σύνδεσης SN μεταξύ L-404 και GPZ-Polkowice STREFA να R-917-2 στο Polkowice L-404 στο πεδίο της κατασκευής της γραμμής SN τύπου 3x XRUHAKXS 1x120/25 mm² Ως μέρος της εργασίας 4, θα υπάρχουν: 1,2 km νεόδμητου δικτύου ηλεκτρικής ενέργειας μέσης τάσης για RES Εργασία 5 â EUR Κατασκευή του δικτύου SN στο Osiek â EUR â EUR KÅopotów L-961-40 και L-953 στο πεδίο εφαρμογής: κατασκευή καλωδιακής γραμμής SN 20 kV XRUHAKXS 1x120 mm²/25 mm² και ντουλάπια τηλεμηχανικής. Στο πλαίσιο της εργασίας 5, θα δημιουργηθούν τα ακόλουθα: 2.1 χλμ νεόδμητου δικτύου ηλεκτρικής ενέργειας μέσης τάσης για ΑΠΕ Στόχος του έργου είναι η σύνδεση με το δίκτυο TAURON Διανομή 15 σταθμών ηλεκτροπαραγωγής από ΑΠΕ με δυνητική ισχύ 12,753 kW και μελλοντικούς αιτούντες σύνδεση ΑΠΕ. Οι συνδέσεις αυτές δεν μπορούν να υλοποιηθούν χωρίς την υλοποίηση του έργου, λόγω έλλειψης επαρκών (Greek)
    26 July 2022
    0 references
    Predmet projekta: U okviru projekta âEURIzgradnja i modernizacija elektroenergetske mreže s naponima SN i nN koji omogućuju priključivanje jedinica za proizvodnju električne energije iz obnovljivih izvora energije u općini Š"ukowice, Kotla, Gögó³w, Polkowice i LubinâEUR planirani su građevinski radovi koji pokrivaju 5 poslova: Zadatak 1 âEUR Modernizacija SN mreže u Å"ukowice komune â EUR L-812 u opsegu: rekonstrukcija nadzemne linije SN 3xBLL-T 70 mm² i 3xBLL-T 50 mm², instalacija kabelske linije SN 3xXXRUHAKXS 1x240/25 mm² U sklopu Zadatka 1 bit će izrađena: 3,2 km modernizirane srednjenaponske elektroenergetske mreže za zadatak 2 za obnovljive izvore energije âEUR Modernizacija mreže SN u općini Kotla L-805 u području: rastavljanje strujnog nadzemnog voda i pretvorba u kabelsku liniju SN 3xXXRUHAKXS 1x120/25 mm² i izgradnja dvaju SN kabelskih priključaka. U okviru zadatka 2. izradit će se sljedeće: 2,3 km modernizirane srednjenaponske električne mreže za RES Zadatak 3 â EUR Modernizacija SN mreže u GÅogów L-814 za liniju tipa 3x XRUHAKXS 1x120/25 mm² U sklopu zadatka 3 bit će stvorena: 0,9 km modernizirane srednjenaponske elektroenergetske mreže za RES zadatak 4 â EUR Izgradnja veze SN između L-404 i GPZ-Polkowice STREFA do R-917 – 2 u Polkowice L-404 u okviru izgradnje SN linije tipa 3x XRUHAKXS 1x120/25 mm² Kao dio zadatka 4 bit će: 1,2 km novoizgrađene srednjenaponske elektroenergetske mreže za OIE Zadatak 5 â EUR Izgradnja SN mreže u Osiek â EUR KÅopotów L-961 – 40 i L-953 u opsegu: izgradnja kabelske linije SN 20 kV XRUHAKXS 1x120 mm²/25 mm² i telemehaničkih ormara. U okviru zadatka 5. izradit će se sljedeće: 2,1 km novoizgrađene srednjenaponske elektroenergetske mreže za obnovljive izvore energije Cilj projekta je omogućiti priključenje na mrežu TAURON Distribucija 15 obnovljivih elektrana s potencijalnom snagom od 12,753 kW i budućih podnositelja zahtjeva za priključenje na obnovljive izvore energije. Te se veze ne mogu ostvariti bez provedbe projekta zbog nedostatka dovoljnog broja (Croatian)
    26 July 2022
    0 references
    Obiectul proiectului: Ca parte a proiectului Construirea și modernizarea rețelei electrice cu tensiuni SN și nN care să permită conectarea unităților de generare a energiei electrice din SRE în comuna Å"ukowice, Kotla, GÅogĂ³w, Polkowice și Lubinâ EUR sunt planificate lucrări de construcție care acoperă 5 sarcini: Sarcina 1 â EUR Modernizarea rețelei SN în comuna Å"ukowice â EUR L-812 în domeniul de aplicare al: reconstrucția liniei aeriene SN 3xBLL-T 70 mm² și 3xBLL-T 50 mm², instalarea liniei de cablu SN 3xXXRUHAKXS 1x240/25 mm² Ca parte a sarcinii 1 va fi creată: 3,2 km de rețea electrică de medie tensiune modernizată pentru SRE Sarcina 2 â EUR Modernizarea rețelei SN în comuna Kotla L-805 în domeniul de aplicare al: demontarea liniei aeriene de curent și conversia în linia de cablu SN 3xXXRUHAKXS 1x120/25 mm² și construcția a doi conectori de cablu SN. Ca parte a sarcinii 2, vor fi create următoarele: 2,3 km de rețea electrică modernizată de medie tensiune pentru RES Sarcina 3 â EUR Modernizarea rețelei SN în GÅogĂ³w L-814 pentru o linie de tip 3x XRUHAKXS 1x120/25 mm² Ca parte a Sarcinii 3 vor fi create: 0,9 km de rețea electrică modernizată de medie tensiune pentru RES Sarcina 4 â EUR Construirea conexiunii SN între L-404 și GPZ-Polkowice STREFA la R-917-2 în Polkowice L-404 în domeniul de construcție a liniei SN tip 3x XRUHAKXS 1x120/25 mm² Ca parte a sarcinii 4, va exista: 1,2 km de rețea electrică de medie tensiune nou construită pentru SRE Task 5 â EUR Construirea rețelei SN în Osiek â EUR KÅopotów L-961-40 și L-953 în domeniul de aplicare al: construcția liniei de cablu SN 20 kV XRUHAKXS 1x120 mm²/25 mm² și dulapuri telemecanice. Ca parte a sarcinii 5, vor fi create următoarele: 2,1 km de rețea electrică de medie tensiune nou construită pentru RES Scopul proiectului este de a permite conectarea la rețeaua TAURON Distribuția a 15 centrale electrice din surse regenerabile cu o putere potențială de 12,753 kW și viitorii solicitanți pentru conectarea SRE. Aceste conexiuni nu pot fi realizate fără ca proiectul să fie pus în aplicare, din cauza lipsei de resurse suficiente. (Romanian)
    26 July 2022
    0 references
    Predmet projektu: V rámci projektu „Výstavba a modernizácia elektrickej siete s SN a nN napätiami umožňujúcimi pripojenie jednotiek na výrobu elektrickej energie z OZE v obci Š“ukowice, Kotla, GÅogów, Polkowice a Lubinâ EUR sa plánujú stavebné práce zahŕňajúce 5 úloh: Úloha 1 â EUR Modernizácia SN siete v Š"ukowice obce â EUR L-812 v rozsahu: rekonštrukcia nadzemného vedenia SN 3xBLL-T 70 mm² a 3xBLL-T 50 mm², inštalácia káblovej linky SN 3xXXRUHAKXS 1x240/25 mm² V rámci úlohy 1 bude vytvorená: 3,2 km modernizovanej siete stredného napätia pre RES Task 2 â EUR Modernizácia siete SN v obci Kotla L-805 v rozsahu: demontáž aktuálneho nadzemného vedenia a premena na káblovú linku SN 3xXXRUHAKXS 1x120/25 mm² a konštrukcia dvoch káblových konektorov SN. V rámci 2. úlohy sa vytvoria: 2,3 km modernizovanej siete stredného napätia pre RES Task 3 â EUR Modernizácia siete SN v GÅogów L-814 pre rad typu 3x XRUHAKXS 1x120/25 mm² V rámci úlohy 3 bude vytvorená: 0,9 km modernizovanej siete stredného napätia pre RES Task 4 â EUR Výstavba spojenia SN medzi L-404 a GPZ-Polkowice STREFA na R-917 – 2 v Polkowice L-404 v rozsahu výstavby SN typu 3x XRUHAKXS 1x120/25 mm² V rámci úlohy 4 budú: 1,2 km novovybudovanej vysokonapäťovej elektrickej siete pre RES Task 5 â EUR Výstavba siete SN v Osiek â EUR KÅopotów L-961 – 40 a L-953 v rozsahu: konštrukcia káblovej linky SN 20 kV XRUHAKXS 1x120 mm²/25 mm² a telemechanických skríň. V rámci úlohy č. 5 sa vytvoria: 2,1 km novovybudovanej vysokonapäťovej elektrickej siete pre OZE Cieľom projektu je umožniť pripojenie do siete TAURON 15 elektrární OZE s potenciálnou spotrebou 12,753 kW a budúcich žiadateľov o pripojenie OZE. Tieto spojenia nie je možné realizovať bez realizácie projektu z dôvodu nedostatku dostatočných (Slovak)
    26 July 2022
    0 references
    Is-suġġett tal-proġett: Bħala parti mill-proġett âEURKostruzzjoni u l-modernizzazzjoni tal-grilja tal-enerġija ma ‘vultaġġi SN u nN jippermettu l-konnessjoni ta’ unitajiet ta ‘ġenerazzjoni tal-elettriku minn RES fil-komun ta’ Å"ukowice, Kotla, GÅogów, Polkowice u Lubinâ EUR ix-xogħlijiet ta ‘kostruzzjoni li jkopru 5 kompiti huma ppjanati: Kompitu 1 â EUR â EUR Modernizzazzjoni tan-netwerk SN fil Å"ukowice commune EUR â EUR L-812 fil-kamp ta ‘applikazzjoni ta’: rikostruzzjoni tal-linja overhead SN 3xBLL-T 70 mm² u 3xBLL-T 50 mm², installazzjoni tal-linja tal-kejbil SN 3xXXRUHAKXS 1x240/25 mm² Bħala parti mill-Kompitu 1 se tinħoloq: 3.2 km ta ‘grid ta’ elettriku ta ‘vultaġġ medju modernizzat għal RES Task 2 â EUR Modernizzazzjoni tan-netwerk SN fil Kotla L-805 komun fil-kamp ta’ applikazzjoni ta ': iż-żarmar tal-linja overhead kurrenti u l-konverżjoni fil-linja tal-kejbil SN 3xXXRUHAKXS 1x120/25 mm² u l-kostruzzjoni ta ‘żewġ konnetturi tal-kejbil SN. Bħala parti mill-Kompitu 2, se jinħoloq dan li ġej: 2.3 km ta ‘grid ta’ elettriku ta ‘vultaġġ medju modernizzat għal RES Task 3 â EUR Modernizzazzjoni tan-netwerk SN fil GÅogów L-814 għal linja tat-tip 3x XRUHAKXS 1x120/25 mm² Bħala parti mill-Kompitu 3 se jinħolqu: 0.9 km ta ‘grid ta’ enerġija ta ‘vultaġġ medju modernizzat għal RES Task 4 âEUR Kostruzzjoni tal-konnessjoni ta’ SN bejn L-404 u STREFA GPZ-Polkowice għal R-917–2 Polkowice L-404 fl-ambitu tal-kostruzzjoni ta ‘linja SN tip 3x XRUHAKXS 1x120/25 mm² Bħala parti mill-Kompitu 4, se jkun hemm: 1.2 km ta ‘grilja elettrika b’vultaġġ medju mibnija ġodda għal RES Task 5 â EUR Kostruzzjoni tan-netwerk SN f’Osiek â EUR KÅopotów L-961–40 u L-953 fil-kamp ta’ applikazzjoni ta ': kostruzzjoni ta ‘kejbil linja SN 20 kV XRUHAKXS 1x120 mm²/25 mm² u kabinetti telemekkanika. Bħala parti mill-Kompitu 5, se jinħoloq dan li ġej: 2.1 km ta’ grilja tal-elettriku b’vultaġġ medju mibni ġdid għal RES L-għan tal-proġett huwa li jippermetti l-konnessjoni man-netwerk TAURON Distribuzzjoni ta’ 15-il impjant tal-enerġija RES b’potenza potenzjali ta’ 12.753 kW u applikanti futuri għal konnessjoni RES. Dawn il-konnessjonijiet ma jistgħux jitwettqu mingħajr ma jiġi implimentat il-proġett, minħabba nuqqas ta’ (Maltese)
    26 July 2022
    0 references
    Objeto do projeto: No âmbito do projeto ›Construção e modernização da rede elétrica com tensões SN e nN que permitem a ligação de unidades de produção de eletricidade a partir de FER no município de Å"ukowice, Kotla, GÅogà³w, Polkowice e Lubinâ EUR as obras de construção que abrangem 5 tarefas estão previstas: Tarefa 1 âEUR Modernização da rede SN na comuna de Åukowice EUR L-812 no âmbito de: reconstrução da linha aérea SN 3xBLL-T 70 mm² e 3xBLL-T 50 mm², instalação da linha de cabos SN 3xXXRUHAKXS 1x240/25 mm² Como parte da Tarefa 1 será criada: 3,2 km de rede elétrica modernizada de média tensão para a tarefa FER 2 âEUR Modernização da rede SN na comuna de Kotla L-805 no âmbito de: desmontando a linha aérea de corrente e conversão na linha de cabos SN 3xXXRUHAKXS 1x120/25 mm² e a construção de dois conectores de cabo SN. No âmbito da Tarefa 2, serão criados os seguintes elementos: 2,3 km de rede elétrica modernizada de média tensão para a tarefa RES 3 âEUR Modernização da rede SN em GÅogów L-814 para uma linha do tipo 3x XRUHAKXS 1x120/25 mm² Como parte da tarefa 3 será criada: 0,9 km de rede elétrica modernizada de média tensão para a tarefa RES 4 âEUR Construção da ligação da SN entre L-404 e GPZ-Polkowice STREFA para R-917-2 em Polkowice L-404 no âmbito da construção da linha SN tipo 3x XRUHAKXS 1x120/25 mm² Como parte da Tarefa 4, haverá: 1,2 km de rede elétrica de média tensão recém-construída para a tarefa FER 5 âEUR Construção da rede SN em Osiek âEUR KÅopotÃw L-961-40 e L-953 no âmbito de: construção da linha de cabos SN 20 kV XRUHAKXS 1x120 mm²/25 mm² e cacifos de telemecânica. Como parte da Tarefa 5, será criado o seguinte: 2,1 km de rede elétrica de média tensão recém-construída para FER O objetivo do projeto é permitir a ligação à rede TAURON Distribuição de 15 centrais elétricas FER com uma potência potencial de 12,753 kW e futuros candidatos à ligação FER. Estas conexões não podem ser realizadas sem que o projeto seja implementado, devido à falta de (Portuguese)
    26 July 2022
    0 references
    Hankkeen kohde: Å”ukowicen, Kotlan, GÅog³win, Polkowicen ja Lubinin kunnassa Å”ukowicen, Kotlan, GÅogówin, Polkowicen ja Lubinin kunnassa sijaitsevien uusiutuvien energialähteiden tuotantoyksiköiden liittämisen mahdollistavien SN- ja nN-jännitteiden rakentaminen ja uudenaikaistaminen on osa hanketta, jossa suunnitellaan viiden työtehtävän rakennustöitä: Tehtävä 1 â EUR SN:n verkon nykyaikaistaminen Å”ukowicen kunnassa L-812:ssa rekonstruointi ajojohdon SN 3xBLL-T 70 mm² ja 3xBLL-T 50 mm², asennus kaapelilinja SN 3xXXRUHAKXS 1x240/25 mm² osana Tehtävä 1 luodaan: 3,2 km uudenaikaistettua keskijänniteverkkoa uusiutuvia energialähteitä varten Tehtävä 2 â EUR SN-verkon nykyaikaistaminen Kotla L-805 -kunnassa seuraavasti: nykyisen ilmajohdon purkaminen ja muuntaminen kaapelilinjaksi SN 3xXXRUHAKXS 1x120/25 mm² sekä kahden SN-kaapeliliittimen rakentaminen. Osana tehtävää 2 luodaan seuraavat toimet: 2,3 km nykyaikaistettua keskijänniteverkkoa uusiutuvia energialähteitä varten Tehtävä 3 â EUR SN-verkon nykyaikaistaminen GÅogów L-814:ssä tyypin 3x XRUHAKXS 1x120/25 mm²:n linjalle osana tehtävää 3 luodaan: 0,9 km modernisoitua keskijänniteverkkoa RES Tehtävä 4 â EUR SN yhteyden rakentaminen välillä L-404 ja GPZ-Polkowice STREFA R-917–2 Polkowice L-404 SN-linja tyyppi 3x XRUHAKXS 1x120/25 mm² osana Tehtävää 4 on: 1,2 km uutta keskijänniteverkkoa uusiutuvia energialähteitä varten Tehtävä 5 â EUR SN-verkon rakentaminen Osiekissa KÅopotów L-961–40 ja L-953 seuraavasti: rakentaminen kaapeli linja SN 20 kV XRUHAKXS 1x120 mm²/25 mm² ja telemekaniikka kaapit. Osana tehtävää 5 luodaan seuraavat toimet: 2,1 km uusiutuvaa energiaa varten rakennettua keskijänniteverkkoa Hankkeen tavoitteena on mahdollistaa liittäminen TAURON-verkkoon, joka käsittää 15 uusiutuvia energialähteitä käyttävää voimalaitosta, joiden potentiaalinen teho on 12,753 kW, ja tulevia uusiutuvia energialähteitä käyttäviä voimaloita. Näitä yhteyksiä ei voida toteuttaa ilman hankkeen toteuttamista, koska niitä ei ole riittävästi. (Finnish)
    26 July 2022
    0 references
    Predmet projekta: V okviru projekta Gradnja in posodobitev električnega omrežja z napetostmi SN in nN, ki omogočajo priključitev enot za proizvodnjo električne energije iz obnovljivih virov v občini Å"ukowice, Kotla, GÅogów, Polkowice in Lubinâ EUR, so načrtovana gradbena dela, ki zajemajo 5 nalog: Naloga 1 â EUR Posodobitev omrežja SN v Å"ukowice commune â EUR L-812 v okviru: rekonstrukcija voznega voda SN 3xBLL-T 70 mm² in 3xBLL-T 50 mm², montaža kabelske linije SN 3xXXRUHAKXS 1x240/25 mm² Kot del naloge 1 bo ustvarjen: 3,2 km posodobljenega srednjenapetostnega električnega omrežja za RES Task 2 â EUR Posodobitev omrežja SN v Kotli L-805 občini v okviru: demontaža toka voznega voda in pretvorba v kabelsko linijo SN 3xXXRUHAKXS 1x120/25 mm² in konstrukcija dveh SN kabelskih konektorjev. V okviru naloge 2 bo ustvarjeno naslednje: 2,3 km posodobljenega srednjenapetostnega električnega omrežja za RES Task 3 â EUR Posodobitev SN omrežja v GÅogów L-814 za linijo tipa 3x XRUHAKXS 1x120/25 mm² Kot del naloge 3 bo ustvarjen: 0,9 km posodobljenega srednjenapetostnega električnega omrežja za RES Task 4 â EUR Izgradnja povezave SN med L-404 in GPZ-Polkowice STREFA do R-917–2 v Polkowice L-404 v obsegu gradnje linije SN tipa 3x XRUHAKXS 1x120/25 mm² Kot del naloge 4 bo: 1,2 km novozgrajenega srednjenapetostnega električnega omrežja za RES Task 5 â EUR Izgradnja omrežja SN v Osiek â EUR KÅopotów L-961–40 in L-953 v okviru: gradnja kabelske linije SN 20 kV XRUHAKXS 1x120 mm²/25 mm² in telemehanike omare. V okviru naloge 5 bo ustvarjeno naslednje: 2,1 km novozgrajenega srednjenapetostnega električnega omrežja za OVE Cilj projekta je omogočiti priključitev na omrežje TAURON za distribucijo 15 elektrarn iz obnovljivih virov s potencialno močjo 12,753 kW in bodoče prijavitelje za priključitev na OVE. Teh povezav ni mogoče uresničiti brez izvedbe projekta zaradi pomanjkanja zadostnih (Slovenian)
    26 July 2022
    0 references
    Předmět projektu: V rámci projektu „Výstavba a modernizace elektrické sítě s napětím SN a nN umožňující připojení jednotek na výrobu elektřiny z OZE v obci Šukowice, Kotla, GÅogów, Polkowice a Lubin“ jsou plánovány stavební práce zahrnující 5 úkolů: Úkol 1 â EUR Modernizace sítě SN v Å"ukowice obec â EUR L-812 v rozsahu: rekonstrukce nadzemního vedení SN 3xBLL-T 70 mm² a 3xBLL-T 50 mm², instalace kabelové linky SN 3xXXRUHAKXS 1x240/25 mm² V rámci úkolu 1 vznikne: 3,2 km modernizované elektrické sítě středního napětí pro OZE úkol 2 › Modernizace sítě SN v obci Kotla L-805 v rozsahu: demontáž proudu trolejového vedení a konverze na kabelové vedení SN 3xXXRUHAKXS 1x120/25 mm² a konstrukce dvou kabelových konektorů SN. V rámci úkolu 2 budou vytvořeny tyto prvky: 2,3 km modernizované elektrické sítě středního napětí pro RES úkol 3 › Modernizace sítě SN v GÅogów L-814 pro linku typu 3x XRUHAKXS 1x120/25 mm² V rámci úkolu 3 bude vytvořena: 0,9 km modernizované elektrické sítě středního napětí pro RES Task 4 â EUR Výstavba připojení SN mezi L-404 a GPZ-Polkowice STREFA na R-917–2 v Polkowice L-404 v rozsahu výstavby linky SN typu 3x XRUHAKXS 1x120/25 mm² V rámci úkolu 4 bude: 1,2 km nově postavené elektrické sítě středního napětí pro OZE úkol 5 › Stavba sítě SN v Osiku › KÅopotów L-961–40 a L-953 v rozsahu: konstrukce kabelové linky SN 20 kV XRUHAKXS 1x120 mm²/25 mm² a telemechanických skříní. V rámci úkolu 5 budou vytvořeny tyto prvky: 2,1 km nově postavené elektrické sítě středního napětí pro OZE Cílem projektu je umožnit připojení k síti TAURON Distribuce 15 elektráren OZE s potenciálním výkonem 12,753 kW a budoucích žadatelů o připojení OZE. Tato spojení nemohou být realizována bez realizace projektu, a to z důvodu nedostatku dostatečného (Czech)
    26 July 2022
    0 references
    Projekto dalykas: Įgyvendinant projektą „Elektros energijos tinklo statyba ir modernizavimas naudojant SN ir nN įtampas, suteikiančias galimybę prijungti elektros energijos gamybos vienetus iš AEI Å“ukvicų, Kotlos, GÅogów, Polkowice ir Lubin’e komunoje, planuojami statybos darbai, apimantys 5 užduotis: Užduotis 1 â EUR SN tinklo modernizavimas Å"ukowice komuna â EUR L-812 į taikymo sritį: orinės linijos SN 3xBLL-T 70 mm² ir 3xBLL-T 50 mm² rekonstrukcija, kabelių linijos SN 3xXXRUHAKXS 1x240/25 mm² įrengimas. 3,2 km modernizuoto vidutinės įtampos elektros tinklo, skirto AEI 2-ajam uždaviniui â EUR SN tinklo modernizavimas Kotla L-805 komunoje: išmontuoti esamą orinę liniją ir konvertuoti į kabelinę liniją SN 3xXXRUHAKXS 1x120/25 mm² ir dviejų SN kabelių jungčių konstrukciją. Kaip 2 užduoties dalis, bus sukurta: 2,3 km modernizuoto vidutinės įtampos elektros tinklo RES uždaviniui Nr. 3 ā EUR SN tinklo modernizavimas GÅogów L-814 3x XRUHAKXS 1x120/25 mm² tipo linijai. 0,9 km modernizuoto vidutinės įtampos elektros tinklo RES užduotis 4 â EUR SN prijungimo tarp L-404 ir GPZ-Polkowice STREFA į R-917–2 Polkowice L-404 statybos apimtis SN linijos tipas 3x XRUHAKXS 1x120/25 mm² Kaip 4 užduoties dalis, bus: 1,2 km naujai pastatyto vidutinės įtampos elektros tinklo AEI uždaviniui 5 ā EUR SN tinklo statyba Osiek ā EUR KÅopotów L-961–40 ir L-953 taikymo sritis: kabelių linijos SN 20 kV XRUHAKXS 1x120 mm²/25 mm² ir telemechaninių spintų statyba. Įgyvendinant 5 užduotį bus sukurta: 2,1 km naujai pastatyto vidutinės įtampos elektros tinklo AEI Projekto tikslas – sudaryti sąlygas prijungti prie TAURON tinklo 15 AEI jėgainių, kurių galia gali būti 12,753 kW, ir būsimų pareiškėjų prisijungti prie AEI. Šios jungtys negali būti įgyvendintos, jei projektas nebus įgyvendintas, nes nepakanka (Lithuanian)
    26 July 2022
    0 references
    Projekta priekšmets: Projekta ietvaros elektrotīkla būvniecība un modernizācija ar SN un nN spriegumu, kas ļauj pieslēgt elektroenerģijas ražošanas iekārtas no AER Å’ukowice, Kotla, GÅogów, Polkowice un Lubinâ EUR komūnā, tiek plānoti būvdarbi, kas aptver 5 uzdevumus: Uzdevums 1 â EUR modernizācija SN tīkla Å’ukowice komūnā â L-812 jomā: gaisvadu līnijas SN 3xBLL-T 70 mm² un 3xBLL-T 50 mm² rekonstrukcija, kabeļu līnijas SN 3xXXRUHAKXS 1x240/25 mm² uzstādīšana 1. uzdevuma ietvaros: 3,2 km modernizēts vidēja sprieguma elektrotīkls RES 2. uzdevumam SN tīkla modernizācija Kotla L-805 komūnā: pašreizējās gaisvadu līnijas demontāža un pārveidošana par kabeļu līniju SN 3xXXRUHAKXS 1x120/25 mm² un divu SN kabeļu savienotāju izbūve. 2. uzdevuma ietvaros tiks izveidots: 2,3 km modernizēts vidēja sprieguma elektrotīkls RES uzdevumam 3 â EUR SN tīkla modernizācija GÅogów L-814 līnijai 3x XRUHAKXS 1x120/25 mm² Kā daļa no 3. uzdevuma tiks izveidota: 0,9 km modernizēta vidēja sprieguma elektrotīklu RES uzdevums 4 â EUR būvniecība savienojuma SN starp L-404 un GPZ-Polkowice STREFA uz R-917–2 in Polkowice L-404 jomā būvniecības SN līnijas tips 3x XRUHAKXS 1x120/25 mm² Kā daļa no uzdevuma 4 būs: 1,2 km no jauna uzbūvēta vidēja sprieguma elektrotīklu RES uzdevums 5 â EUR būvniecība SN tīkla Osiek â EUR KÅopotów L-961–40 un L-953 ietvaros: kabeļu līnijas SN 20 kV XRUHAKXS 1x120 mm²/25 mm² un telemehānikas skapju izbūve. 5. uzdevuma ietvaros tiks izveidots: 2,1 km no jauna izbūvētā vidēja sprieguma elektrotīkla AER. Projekta mērķis ir nodrošināt pieslēgumu TAURON tīklam 15 AER spēkstaciju ar potenciālo jaudu 12,753 kW un nākotnes AER pieslēguma pieprasītāju sadalei. Šos savienojumus nevar izveidot, ja projekts netiek īstenots, jo trūkst pietiekamu (Latvian)
    26 July 2022
    0 references
    Предмет на проекта: Като част от проекта âEURИзграждане и модернизация на електрическата мрежа с напрежения SN и nN, позволяващи свързването на електрогенериращи агрегати от ВЕИ в община Å"ukowice, Kotla, GÅogów, Polkowice и LubinâEUR, са планирани строителни работи, обхващащи 5 задачи: Задача 1 — Модернизиране на мрежата SN в община Å"ukowice â EUR L-812 в обхвата на: реконструкция на въздушна линия SN 3xBLL-T 70 mm² и 3xBLL-T 50 mm², монтаж на кабелна линия SN 3xXXRUHAKXS 1x240/25 mm² Като част от Задача 1 ще бъде създадена: 3,2 км модернизирана електропреносна мрежа за средно напрежение за ВЕИ задача 2 â EUR Модернизиране на мрежата SN в община Kotla L-805 в обхвата на: демонтиране на текущата въздушна линия и преобразуване в кабелна линия SN 3xXXRUHAKXS 1x120/25 mm² и изграждане на два SN кабелни конектора. Като част от задача 2 ще бъде създадено следното: 2,3 км модернизирана електрическа мрежа за средно напрежение за RES Задача 3 â EUR Модернизиране на мрежата SN в GÅogów L-814 за линия от тип 3x XRUHAKXS 1x120/25 mm² Като част от задача 3 ще бъде създадена: 0,9 км модернизирана мрежа за средно напрежение за RES Задача 4 âEUR Изграждане на свързването на SN между L-404 и GPZ-Polkowice STREFA до R-917—2 в Polkowice L-404 в обхвата на изграждането на SN линия тип 3x XRUHAKXS 1x120/25 mm² Като част от задача 4 ще има: 1,2 km новоизградена електропреносна мрежа със средно напрежение за RES Задача 5 â EUR Изграждане на мрежата SN в Osiek â EUR KÅopotów L-961—40 и L-953 в обхвата на: изграждане на кабелна линия SN 20 kV XRUHAKXS 1x120 mm²/25 mm² и телемеханични шкафове. Като част от задача 5 ще бъде създадено следното: 2,1 км новоизградена електропреносна мрежа със средно напрежение за ВЕИ Целта на проекта е да се даде възможност за присъединяване към мрежата TAURON Разпределение на 15 ВЕИ централи с потенциална мощност 12,753 kW и бъдещи кандидати за ВЕИ. Тези връзки не могат да бъдат осъществени без изпълнението на проекта поради липса на достатъчно (Bulgarian)
    26 July 2022
    0 references
    A projekt tárgya: A projekt részeként az Å’ukowice, Kotla, GÅogów, Polkowice és Lubin településen a megújuló energiaforrásokból származó villamosenergia-termelő egységek összekapcsolását lehetővé tevő SN és nN feszültségű villamosenergia-hálózat építése és korszerűsítése az alábbi 5 feladatra kiterjedő építési munkálatokat tervezi: Feladat Az SN hálózat korszerűsítése Å’ukowice településen L-812 a következő területeken: SN 3xBLL-T 70 mm² és 3xBLL-T 50 mm² felsővezeték rekonstrukciója, SN 3xXXRUHAKXS 1x240/25 mm² kábelvonal telepítése Az 1. feladat részeként jön létre: 3,2 km korszerűsített középfeszültségű villamosenergia-hálózat a megújuló energiaforrások 2. feladatához Kotla L-805 településen az SN-hálózat korszerűsítése a következő területeken: a jelenlegi felsővezeték lebontása és átalakítása az SN 3xXXRUHAKXS 1x120/25 mm² kábelvonalra és két SN kábelcsatlakozó építése. A 2. feladat részeként a következők jönnek létre: 2,3 km korszerűsített középfeszültségű villamosenergia-hálózat a RES Task 3 â EUR Modernizálása SN hálózat GÅogów L-814 egy típusú vonal 3x XRUHAKXS 1x120/25 mm² A 3. feladat részeként jön létre: 0,9 km korszerűsített középfeszültségű elektromos hálózat a RES Task 4 számára Az SN kapcsolatának építése az L-404 és a GPZ-Polkowice STREFA és az R-917–2 között Polkowice L-404-ben, a 3x XRUHAKXS 1x120/25 mm² SN vonaltípusú 3x XRUHAKXS 1x120/25 mm² építési területén A 4. feladat részeként: 1,2 km újonnan épített középfeszültségű villamosenergia-hálózat a megújuló energiaforrások számára 5. feladat Az SN hálózat építése Osiek â EUR KÅopotów L-961–40 és L-953 területén a következő területeken: SN 20 kV XRUHAKXS kábelvonal építése 1x120 mm²/25 mm² és telemechanikai szekrények. Az 5. feladat részeként a következők jönnek létre: 2,1 km újonnan épített középfeszültségű villamosenergia-hálózat a megújuló energiaforrások számára A projekt célja, hogy lehetővé tegye a csatlakozást a TAURON hálózathoz 15,12753 kW potenciális teljesítményű megújuló energiaforrással rendelkező erőmű és a jövőbeli megújulóenergia-csatlakozási jelentkezők számára. Ezek az összeköttetések nem valósíthatók meg a projekt végrehajtása nélkül, mivel nem áll rendelkezésre elegendő (Hungarian)
    26 July 2022
    0 references
    Ábhar an tionscadail: Mar chuid den tionscadal â EURTógáil agus nuachóiriú ar an eangach cumhachta le SN agus nN voltais a chumasú nasc na n-aonad giniúna leictreachais ó RES sa commune de Å»ukowice, Kotla, GÅogów, Polkowice agus Lubinâ EUR na hoibreacha tógála a chlúdaíonn 5 tascanna atá beartaithe: Tasc 1 â EUR Nuachóiriú ar an líonra SN i Å»ukowice commune â EUR L-812 i raon feidhme: atógáil líne lastuas SN 3xBLL-T 70 mm² agus 3xBLL-T 50 mm², suiteáil líne cábla SN 3xXXRUHAKXS 1x240/25 mm² Mar chuid de Thasc 1 a chruthú: 3.2 km de eangach leictreachais meánvoltais nuachóirithe do Thasc RES 2 âEUR Nuachóiriú an líonra SN i Kotla L-805 commune faoi raon feidhme: díchóimeáil an líne lasnairde atá ann faoi láthair agus comhshó isteach sa líne cábla SN 3xXXRUHAKXS 1x120/25 mm² agus tógáil dhá chónaisc cábla SN. Mar chuid de Thasc 2, cruthófar an méid seo a leanas: 2.3 km d’eangach leictreachais meánvoltais nuachóirithe do Thasc RES 3 âEUR Nuachóiriú an líonra SN i GÅogów L-814 do líne de chineál 3x XRUHAKXS 1x120/25 mm² Mar chuid de Thasc 3 a chruthú: 0.9 km de ghreille cumhachta meánvoltais nuachóirithe do RES Tasc 4 âEUR Tógáil an nasc SN idir L-404 agus GPZ-Polkowice STREFA go R-917-2 i Polkowice L-404 i raon feidhme na tógála de chineál líne SN 3x XRUHAKXS 1x120/25 mm² Mar chuid de Thasc 4, beidh: 1.2 km de ghreille leictreachais meánvoltais nua-thógtha le haghaidh RES Task 5 âEUR Tógáil an líonra SN i Osiek â EUR KÅopotów L-961-40 agus L-953 faoi raon feidhme: tógáil líne cábla SN 20 kV XRUHAKXS 1x120 mm²/25 mm² agus caibinéid telemechanics. Mar chuid de Thasc 5, cruthófar an méid seo a leanas: 2.1 km de ghreille leictreachais mheánvoltais nuathógtha le haghaidh RES Is é aidhm an tionscadail nascadh le líonra TAURON a chumasú Dáileadh gléasraí cumhachta 15 RES a bhfuil cumhacht fhéideartha 12.753 kW acu agus iarratasóirí ar nasc RES amach anseo. Ní féidir na naisc seo a bhaint amach gan an tionscadal a chur i bhfeidhm, mar gheall ar easpa leordhóthanach (Irish)
    26 July 2022
    0 references
    Projektets syfte: Som en del av projektet âEURKonstruktion och modernisering av elnätet med SN- och nN-spänningar som möjliggör anslutning av elproduktionsenheter från förnybara energikällor i kommunen Å”ukowice, Kotla, GÅogów, Polkowice och Lubinâ EUR planeras byggnadsarbeten som omfattar fem uppgifter: Uppgift 1 â Modernisering av SN-nätet i Å”ukowice kommun â EUR L-812 inom ramen för: rekonstruktion av kontaktledningen SN 3xBLL-T 70 mm² och 3xBLL-T 50 mm², installation av kabelledning SN 3xXXRUHAKXS 1x240/25 mm² Som en del av uppgift 1 kommer att skapas: 3,2 km moderniserat mellanspänningsnät för el från förnybara energikällor â Modernisering av SN-nätet i Kotla L-805 kommun inom ramen för demontering av nuvarande kontaktledning och konvertering till kabelledningen SN 3xXXRUHAKXS 1x120/25 mm² och konstruktionen av två SN-kabelanslutningar. Som en del av uppgift 2 kommer följande att skapas: 2,3 km moderniserat medelspänningsnät för RES-uppgift 3 â Modernisering av SN-nätet i GÅogów L-814 för en linje av typ 3x XRUHAKXS 1x120/25 mm² Som en del av uppgift 3 kommer att skapas: 0,9 km moderniserat medelspänningsnät för RES Task 4 â EUR Konstruktion av anslutningen av SN mellan L-404 och GPZ-Polkowice STREFA till R-917–2 i Polkowice L-404 inom ramen för konstruktion av SN linje typ 3x XRUHAKXS 1x120/25 mm² Som en del av uppgift 4 kommer det att finnas: 1,2 km nybyggt medelspänningsnät för RES Task 5 â Byggandet av SN-nätet i Osiek › KÅopotów L-961–40 och L-953 inom ramen för: konstruktion av kabelledning SN 20 kV XRUHAKXS 1x120 mm²/25 mm² och telemekanikskåp. Som en del av uppgift 5 kommer följande att skapas: 2,1 km nybyggt mellanspänningsnät för förnybara energikällor Syftet med projektet är att möjliggöra anslutning till TAURON-nätet Distribution av 15 förnybara kraftverk med en potentiell effekt på 12,753 kW och framtida sökande av el från förnybara energikällor. Dessa förbindelser kan inte förverkligas utan att projektet genomförs, på grund av brist på tillräckliga (Swedish)
    26 July 2022
    0 references
    Projekti sisu: Osana projektist Å"ukowice’i, Kotla, GÅogów, Polkowice’i ja Lubin’i kommuunis elektrivõrgu ehitamine ja moderniseerimine SN-i ja nN-pingega, mis võimaldavad ühendada taastuvatest energiaallikatest toodetud elektri tootmisüksused, on kavandatud ehitustöödeks, mis hõlmavad viit ülesannet: Ülesanne 1 â EUR moderniseerimine SN võrgu Å"ukowice kommuunis âEUR L-812 ulatuses: õhuliini SN 3xBLL-T 70 mm² ja 3xBLL-T 50 mm² rekonstrueerimine, kaabliliini SN 3xXXRUHAKXS 1x240/25 mm² paigaldamine ülesande 1 raames: 3,2 km moderniseeritud keskpinge elektrivõrku taastuvate energiaallikate jaoks 2. ülesanne âEUR Kotla L-805 kommuunis asuva SNi võrgu moderniseerimine: praeguse õhuliini demonteerimine ja muutmine kaabliliiniks SN 3xXXRUHAKXS 1x120/25 mm² ja kahe SN-kaabli pistikühenduse ehitamine. Ülesande nr 2 raames luuakse järgmised ülesanded: 2,3 km moderniseeritud keskpinge elektrivõrk RES Task 3 âEUR moderniseerimine SN võrgu GÅogów L-814 liini tüüp 3x XRUHAKXS 1x120/25 mm² Osana ülesanne 3 luuakse: 0,9 km moderniseeritud keskpinge elektrivõrgu RES ülesanne 4 âEUR Ehitus SN ühendus L-404 ja GPZ-Polkowice STREFA kuni R-917–2 Polkowice L-404 ulatuses ehituse SN liini tüüp 3x XRUHAKXS 1x120/25 mm² Osana ülesanne 4, on: 1,2 km uut taastuvatest energiaallikatest toodetud keskpinge elektrivõrku âEUR SN-võrgu ehitamine Osiekis âEUR KÅopotów L-961–40 ja L-953: kaabliliini SN 20 kV XRUHAKXS ehitus 1x120 mm²/25 mm² ja telemehaanikakapid. Ülesande nr 5 raames luuakse järgmised ülesanded: 2,1 km uut taastuvenergia keskpinge elektrivõrku Projekti eesmärk on võimaldada liitumist TAURONi võrguga 15 taastuvenergiajaama potentsiaalse võimsusega 12,753 kW ja tulevaste taastuvate energiaallikate ühenduse taotlejate vahel. Neid ühendusi ei ole võimalik ellu viia ilma projekti rakendamiseta, kuna puudub piisavus. (Estonian)
    26 July 2022
    0 references
    WOJ.: DOLNOŚLĄSKIE, POW.: głogowski
    0 references
    WOJ.: DOLNOŚLĄSKIE, POW.: lubiński
    0 references
    WOJ.: DOLNOŚLĄSKIE, POW.: polkowicki
    0 references

    Identifiers

    RPDS.03.01.00-02-0128/16
    0 references