AVKF St. Joseph College Energy Renovation (Q3943933)
Jump to navigation
Jump to search
Project Q3943933 in Hungary
Language | Label | Description | Also known as |
---|---|---|---|
English | AVKF St. Joseph College Energy Renovation |
Project Q3943933 in Hungary |
Statements
143,167,000 forint
0 references
685,306.746 Euro
0.0027336256 Euro
15 December 2021
0 references
250,695,174.056 forint
0 references
57.108354 percent
0 references
20 July 2020
0 references
30 June 2021
0 references
Apor Vilmos Katolikus Főiskola
0 references
A pályázó, az Apor Vilmos Katolikus Főiskola, mint a Váci Egyházmegye önálló jogi személye. A fejlesztéssel érintett intézmény az Apor Vilmos Katolikus Főiskola fenntartásában álló Szent József Kollégium. Az épület egy 55 férőhelyes kollégium, melyben oktatási tevékenység is folyik 6 tanteremben, 179 fős férőhellyel, így az épület kihasználtsága folyamatos. Az épület energetikai felmérése alapján a külső határoló felületeinek rétegrendi hőátbocsátási tényezője nem megfelelő (pl. homlokzat, a külső nyílászárók, födém). A 7/2006. (V.24.) TNM rendelet az érintett épületek energetikai besorolása jelenlegi állapotuk szerint nem felelnek meg az előírtaknak. Ezt tovább rontja, hogy az épület rendkívüli életkora, tekintve, hogy 1776-ban épült, így az energetikai tényezők fokozott romlása prognosztizálható. Az épület valamennyi külső nyílászárója elavult, cseréjük szükséges. Az épület felújítását a pályázó nem képes önerőből megvalósítani. A projektet megalapozó eredeti műszaki dokumentumok 2015-ben készültek el a Váci Egyházmegye és a Don Bosco Szalézi Társaságának konzorciuma keretében a „Váci Egyházmegye és a Don Bosco Szalézi Társasága energetikai előkészítő munkái” című, KEOP-7.13.0/15-2015-0023 projekt keretében. A terveket felülvizsgáltuk, és annak tükrében írtuk ki a feltételes közbeszerzési eljárást, és kötöttük meg a feltételes vállalkozási szerződést. A sem a KEOP-7.13.0/15-2015-0023 projekt keretében készített terveket, sem annak felülvizsgálatának költségét nem kívánjuk a projekt keretében elszámolni, így kettős finanszírozás nem áll fenn. A fejlesztéssel érintett épület helyi védettség alatt áll, a településképi hozzájáruló nyilatkozatokat. A projekt elsődleges célcsoportja a fejlesztéssel érintett intézmények valamennyi dolgozója, lakója és tanulója. A projekt az ország energiaellátásának biztonságát és versenyképességének javítását, valamint a környezeti állapot megőrzését is szolgálja. A projekt közvetlen eredményei Az épület fejlesztése révén megtakarított éves elsődleges (primer) energiahordozó mennyisége összesen: 339.490 kW/év. Az épületek beavatkozással érintett épületrészei meg fognak felelni a TNM rendeletben foglalt határértékeknek, a felújítás előtti GG szintekről BB kategóriákba kerül. Célcsoport életkörülményei jelentősen javulnak. A projekt közvetett eredményei Javul az Intézmények gazdasági háttere, az intézmény munkavállaló-megtartó képessége, a település lakosságmegtartó képessége, a célcsoport esélyegyenlőségi helyzete, az oktatásra és kollégiumi elszállásolásra alkalmas környezet. Elősegíti a fenntartható fejlődést és szemléletváltást. Közreműködik az éghajlatváltozás mérséklésében, az energiafüggőség csökkentésében és az ország versenyképességének javításában. Megvalósítandó műszaki fejlesztések Külső fal utólagos hőszigetelése 1.531,1 m2 Padlásfödém utólagos hőszigetelése 1140,7 m2 Külső nyílászárók cseréje: ALU ablak 10 db, ALU portál 4 db, Fa ablak 45 db, Műanyag ablak 36 db. Termosztatikus szelepek cseréje: 94 db. Napelemes rendszer telepítése 21,06 kW összteljesítményben,78 db, egyenként 270 Wp/db névleges teljesítményű polikristályos napelemtáblákkal. A kivitelezés megkezdésére 2020. májusában kerül sor, a befejezésére pedig 2020. októberében, minimálisra csökkentve az intézményben folyó tevékenység megzavarását. Az épület üzemeltetését a fejlesztést követően továbbra is maga a Pályázó szervezete látja majd el. (Hungarian)
0 references
The applicant, the Vilmos Apor Catholic College, is an independent legal entity of the Vác Diocese. The institution involved in the development is the Saint Joseph College, which is maintained by the Apor Vilmos Catholic College. The building is a 55-seat dormitory, in which educational activities are also carried out in 6 classrooms, with 179 people, so the building is continuously occupied. According to the energy assessment of the building, the layered heat transfer factor of the external boundaries is not adequate (e.g. facade, exterior windows, slab). SECTION NO 7/2006. According to their current state, the energy classification of the buildings concerned does not comply with the requirements. This is further worsened by the exceptional age of the building, since it was built in 1776, so that an increased deterioration in energy factors can be expected. All the exterior doors and windows of the building are outdated and need to be replaced. The refurbishment of the building cannot be carried out on its own initiative. The original technical documents underpinning the project were drawn up in 2015 in the framework of the consortium of the Vác Diocese and Don Bosco Salesian Society in the framework of the project KEOP-7.13.0/15-2015-0023 entitled “Energy Preparation Works of the Diocese of Váci and the Salesian Society of Don Bosco”. The plans were reviewed and the conditional procurement procedure was drawn up in the light of it and the conditional contract was concluded. The plans prepared in the framework of project KEOP-7.13.0/15-2015-0023 and the cost of its revision are not to be declared under the project, so there is no double financing. The building affected by the development is subject to local protection, declarations of consent for the municipal image. The main target group of the project is all employees, residents and students of the institutions involved in the development. The project also serves the security and competitiveness of the country’s energy supply and the preservation of the environmental status. Direct results of the project Total annual primary energy source saved through the development of the building: 339.490 kW/year. The parts of the buildings affected by intervention will comply with the limit values laid down in the Decree of the Minister for National Development and will be moved from GG levels prior to renovation to BB. The living conditions of the target group are significantly improved. The indirect results of the project Improved the economic background of the Institutions, the capacity of the institution to retain employees, the population retention capacity of the settlement, the equal opportunities position of the target group, the environment suitable for education and dormitory accommodation. It promotes sustainable development and change of mindset. It contributes to climate change mitigation, reducing energy dependency and improving the country’s competitiveness. Technical developments Exterior wall thermal insulation of 1 531.1 m² attic floor retrofitting 1 140.7 m² Replacement of external doors and windows: Alu window 10 pcs, ALU portal 4 pcs, Wooden window 45 pcs, Plastic window 36 pcs. Replacement of thermostatic valves: 94 pcs. Installation of a solar system at 21.06 kW with 78 polycrystalline solar panels with a nominal output of 270 Wp/pcs. The construction will start in May 2020 and will be completed in October 2020, minimising disruption of the institution’s activities. The operation of the building will continue to be carried out by the Applicant’s organisation after the development. (English)
9 February 2022
0 references
Vác, Pest
0 references
Identifiers
KEHOP-5.2.13-19-2019-00002
0 references