Closure of Wastewater Sanitation Systems Connection to the Wastewater Treatment Plant of the Vila de Figueiró dos Vinhos (Q2982762)

From EU Knowledge Graph
Revision as of 09:23, 20 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations)
Jump to navigation Jump to search
Project Q2982762 in Portugal
Language Label Description Also known as
English
Closure of Wastewater Sanitation Systems Connection to the Wastewater Treatment Plant of the Vila de Figueiró dos Vinhos
Project Q2982762 in Portugal

    Statements

    0 references
    2,227,613.0 Euro
    0 references
    2,620,722.0 Euro
    0 references
    85.0 percent
    0 references
    6 January 2020
    0 references
    31 August 2022
    0 references
    APIN - EMPRESA INTERMUNICIPAL DE AMBIENTE DO PINHAL INTERIOR, E.I.M., S.A.
    0 references
    Q3054883 (Deleted Item)
    0 references
    0 references

    39°54'8.82"N, 8°16'31.08"W
    0 references
    A operação consiste na execução de 42,91 km de rede de drenagem, 670 ramais de ligação e 12 Estações Elevatórias com ligação ao Subsistema de Saneamento da ETAR da Vila de Figueiró dos Vinhos e tratamento final na ETAR da Vila de Figueiró dos Vinhos, com descarga para a linha de água que se encontra nas imediações da ETAR. (Portuguese)
    0 references
    The operation consists of the execution of 42.91 km of drainage network, 670 connecting branches and 12 Elevatory Stations with connection to the Sanitation Subsystem of the Water Treatment Plant of the Vila de Figueiró dos Vinhos and final treatment at the treatment plant of the Vila de Figueiró dos Vinhos, with discharge to the waterline that is in the vicinity of the treatment plant. (English)
    9 July 2021
    0 references
    L’opération comprend l’exécution de 42,91 km de réseau de drainage, 670 branches de raccordement et 12 stations d’Elevatória avec raccordement au sous-système d’assainissement de la station d’épuration de Vila de Figueiró dos Vinhos et le traitement final à la station d’épuration des eaux usées de Vila de Figueiró dos Vinhos, avec décharge dans la conduite d’eau à proximité de la station d’épuration des eaux usées. (French)
    7 December 2021
    0 references
    Der Betrieb besteht in der Ausführung von 42,91 km Drainagenetz, 670 Anschlusszweigen und 12 Elevatória Stationen mit Anschluss an das Sanitation Subsystem der Kläranlage von Vila de Figueiró dos Vinhos und abschließende Behandlung in der Kläranlage Vila de Figueiró dos Vinhos, mit Einleitung zur Wasserleitung in der Nähe des WWTP. (German)
    16 December 2021
    0 references
    De exploitatie bestaat uit de uitvoering van 42,91 km afvoernet, 670 verbindingstakken en 12 Elevatória-stations met aansluiting op het Sanitatiesubsysteem van de rioolwaterzuiveringsinstallatie van Vila de Figueiró dos Vinhos en de eindbehandeling in de zuiveringsinstallatie van Vila de Figueiró dos Vinhos, met lozing naar de waterleiding in de nabijheid van de RWZI. (Dutch)