Comprehensive preparation of investment areas of the Economic Activity Zone – Nowa Huta of the Future (Q111678)

From EU Knowledge Graph
Revision as of 15:50, 7 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
Jump to navigation Jump to search
Project Q111678 in Poland
Language Label Description Also known as
English
Comprehensive preparation of investment areas of the Economic Activity Zone – Nowa Huta of the Future
Project Q111678 in Poland

    Statements

    0 references
    58,892,560.64 zloty
    0 references
    14,134,214.55 Euro
    13 January 2020
    0 references
    69,285,365.55 zloty
    0 references
    16,628,487.73 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 October 2017
    0 references
    31 December 2021
    0 references
    KRAKÓW NOWA HUTA PRZYSZŁOŚCI SPÓŁKA AKCYJNA
    0 references
    0 references
    Przedmiotem projektu jest budowa infrastruktury drogowej oraz sieciowej na potrzeby funkcjonowania Strefy Aktywności Gospodarczej.Powierzchnia całkowita SAG 39,298 ha.Teren, podzielony jest na trzy niezależne podobszary:Podobszar Igołomska Północ, Podobszar Igołomska Południe, Podobszar Igołomska Zachód.W ramach projektu zostanie zrealizowany następujący zakres rzeczowy:1. Uporządkowanie istniejącej zieleni niezbędna wycinka drzew, karczowanie, trzebież2. Likwidacja kolidujących obiektów i infrastruktury:3. Doprowadzenie infrastruktury technicznej do granic wyznaczonego SAG 4. Budowa infrastruktury drogowej i komunikacji wewnętrznej SAG drogi, chodniki wraz z oświetleniem, w tym: drogi wewnętrzne SAG o pow. 27 912,4 m2 jezdni, kanalizacja deszczowa odwodnienie dróg o dł. 5,8 km; sieci wodociągowe o dł. 6,89 km, sieci kanalizacyjne o dł. 4,7 km, 4 przepompownie ścieków, oświetlenie drogowe o dł. 5,59 km, kanał technologiczny dla linii telekomunikacyjnych5. Zagospodarowanie terenu mała architektura, trawniki, nasadzeniaTym samym strefa będzie kompletnie wyposażonym SAG.Dla znacznej części obszaru planowanego do objęcia SAG obowiązuje aktualny Miejscowy Plan Zagospodarowania Przestrzennego. Ponadto sporządzany jest nowy MPZP. W zakresie nieobjętym aktualnym MPZP projekt jest zgodny z zapisami dokumentu równoważnego tj. Studium uwarunkowań i kierunków zagospodarowania przestrzennego Miasta Kraków. Projekt spełnia więc kryterium: zgodność z planem zagospodarowanie przestrzennego lub innym dokumentem równoważnym.Na obszarze Gminy Kraków funkcjonuje Specjalna Strefa Ekonomiczna. Jej obszar jest w pełni wykorzystany przez inwestorów, tak więc projekt spełnia kryterium wyczerpania limitu pow. inwestycyjnej.Dodatkowe informacje w cz.Q (Polish)
    0 references
    The subject of the project is the construction of road and network infrastructure for the functioning of the Economic Activity Zone.The total area of SAG 39.298 ha.The area is divided into three independent sub-areas: Igołomska North Subarea, Igołomsk Sub-area South, Igołomsk Subarea West.The following material scope will be implemented within the project:1. Ordering the existing greenery necessary for woodcutting, grubbing-up, debris2. Decommissioning of conflicting facilities and infrastructure:3. Bringing the technical infrastructure to the boundaries of the designated SAG 4. Construction of road infrastructure and internal communication of SAG roads, sidewalks with lighting, including: internal roads SAG o pow. 27912.4 m² of roadways, drainage of rainy roads long. 5,8 km; water supply networks long. 6.89 km, sewerage networks long. 4.7 km, 4 sewage pumping stations, road lighting length. 5.59 km, technological channel for telecommunication lines5. Land development small architecture, lawns and plantingThe same zone will be fully equipped SAG.For a significant part of the area planned to include SAG, the current Local Spatial Plan applies. In addition, a new MPZP is being prepared. To the extent not covered by the current MPZP, the project complies with the provisions of the equivalent document, i.e. A study of the conditions and directions of spatial development of the City of Kraków. The project therefore satisfies the criterion: compliance with the spatial planning plan or other equivalent document.The Special Economic Zone operates in the Municipality of Kraków. Its area is fully utilised by investors, so the project fulfils the criterion of exhaustion of the limit of investment area.Additional information in part Q (English)
    20 October 2020
    0 references
    L’objet du projet est la construction d’infrastructures routières et de réseau pour le fonctionnement de la zone d’activité économique. La superficie totale de SAG 39,298 ha. La zone est divisée en trois indépendants podobszary:Podobszar Igołomska Nord, Igołomska Południe sous-zone, Igołomska Ouest sous-zone.Le champ d’application matériel ci-après sera mis en œuvre dans le cadre du projet:1. Commander la verdure existante abattage nécessaire des arbres, arrachage, éclaircir2. Déclassement d’installations et d’infrastructures conflictuelles:3. Ramener l’infrastructure technique aux limites du GSC désigné 4. Construction d’infrastructures routières et communication interne de la route SAG, chaussées et éclairage, y compris: routes intérieures SAG avec zone. 27 912,4 m² de chaussée, drainage des eaux de pluie des routes. 5,8 km; réseaux d’approvisionnement en eau 6,89 km, réseaux d’assainissement. 4,7 km, 4 stations de pompage des eaux usées, éclairage routier. 5,59 km, canal technologique pour les lignes de télécommunication5. Développement de la zone petite architecture, pelouses, plantationLa même zone sera entièrement équipée SAG.Pour une partie importante de la zone prévue pour être couverte par le SAG, le plan de développement local actuel s’applique. En outre, un nouveau MPZP est en cours d’élaboration. Dans la mesure où le PMZP actuel n’est pas couvert, le projet est conforme aux dispositions du document équivalent, à savoir: Étude des conditions et des orientations du développement spatial de la ville de Cracovie. Le projet remplit donc le critère suivant: respect du plan de zonage ou d’un autre document équivalent.La zone économique spéciale opère dans la zone de la municipalité de Cracovie. Sa zone est pleinement exploitée par les investisseurs, de sorte que le projet répond au critère d’épuisement de la limite de la zone d’investissement. (French)
    1 December 2021
    0 references
    Gegenstand des Projekts ist der Bau von Straßen- und Netzinfrastrukturen für den Betrieb der Wirtschaftstätigkeitszone. Die Gesamtfläche von SAG 39,298 ha. Das Gebiet ist in drei unabhängige podobszary:Podobszar Igołomska North, Igołomska Południe Teilgebiet, Igołomska West Untergebiet unterteilt.Der folgende Materialumfang wird im Rahmen des Projekts umgesetzt:1. Bestellung des vorhandenen Grünes nötiges Abholzen von Bäumen, Rodung, Ausdünnung2. Stilllegung widersprüchlicher Anlagen und Infrastrukturen:3. Die technische Infrastruktur an die Grenzen der benannten SAG 4 zu bringen. Bau der Straßeninfrastruktur und interne Kommunikation der SAG, Straßenbeläge und Beleuchtung, einschließlich: interne Straßen SAG mit Fläche. 27 912,4 m² Fahrbahn, Regenwasserentwässerung von Straßen. 5,8 km; Wasserversorgungsnetze 6,89 km, Kanalisationsnetze. 4,7 km, 4 Abwasserpumpenstationen, Straßenbeleuchtung. 5,59 km, Technologiekanal für Telekommunikationslinien5. Entwicklung des Bereichs kleine Architektur, Rasen, PflanzungDie gleiche Zone wird komplett ausgestattet sein SAG.Für einen wesentlichen Teil der von der SAG abgedeckten Fläche gilt der aktuelle lokale Raumentwicklungsplan. Darüber hinaus wird ein neues MPZP erstellt. Soweit das aktuelle MPZP nicht erfasst ist, entspricht das Projekt den Bestimmungen des gleichwertigen Dokuments, d. h. Studium der Bedingungen und Richtungen der räumlichen Entwicklung der Stadt Krakau. Das Projekt erfüllt daher das Kriterium: Einhaltung des Zonierungsplans oder eines anderen gleichwertigen Dokuments.Besondere Wirtschaftszone ist im Gebiet der Gemeinde Kraków tätig. Sein Gebiet wird von den Investoren voll ausgeschöpft, so dass das Projekt das Kriterium der Erschöpfung des Investitionsgebiets erfüllt. (German)
    7 December 2021
    0 references

    Identifiers

    RPMP.03.01.01-12-0476/17
    0 references