Reconstruction of thermal networks in Cieszyn with the construction of connections and district nodes to liquidate group nodes. (Q85005)

From EU Knowledge Graph
Revision as of 09:22, 7 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
Jump to navigation Jump to search
Project Q85005 in Poland
Language Label Description Also known as
English
Reconstruction of thermal networks in Cieszyn with the construction of connections and district nodes to liquidate group nodes.
Project Q85005 in Poland

    Statements

    0 references
    8,396,296.13 zloty
    0 references
    2,015,111.07 Euro
    13 January 2020
    0 references
    18,276,716.5 zloty
    0 references
    4,386,411.96 Euro
    13 January 2020
    0 references
    45.94 percent
    0 references
    29 May 2017
    0 references
    31 January 2021
    0 references
    ENERGETYKA CIESZYŃSKA SP. Z O.O.
    0 references
    0 references
    0 references
    Projektowane przedsięwzięcie realizowane będzie poprzez wymianę kanałowej sieci cieplnej na preizolowaną podziemną cieć cieplną, budowę preizolowanej sieci cieplnej na nowych odcinkach lub przez wymianę izolacji termicznej na istniejących napowietrzonych rurociągach sieci cieplnej wraz z wykonaniem niezbędnych konserwacji i napraw konstrukcji wsporczej stalowej i żelbetowej rurociągów. W ramach przedsięwzięcia wykonana zostanie likwidacja komór ciepłowniczych podziemnej cieci cieplnej. Ponadto zostaną wybudowane przyłącza do istniejących budynków wraz z węzłami indywidulanymi, dzięki czemu możliwa będzie likwidacja węzłów grupowych. (Polish)
    0 references
    The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the underground heat cut will be carried out. In addition, connections to existing buildings with individual nodes will be built, so that group nodes can be removed. (English)
    14 October 2020
    0 references
    Le projet sera mis en œuvre en remplaçant le réseau de chaleur gainée par de la chaleur souterraine pré-isolée, en construisant un réseau thermique pré-isolé sur de nouveaux tronçons ou en remplaçant l’isolation thermique sur les canalisations existantes du réseau de chaleur souterraine ainsi que l’entretien et la réparation nécessaires des conduites en acier et en béton armé. Dans le cadre du projet, le déclassement des chambres de chauffage urbain du coupe-chauffage souterrain sera réalisé. En outre, des connexions avec des bâtiments existants ainsi que des jonctions individuelles seront construites afin que les nœuds de groupe puissent être supprimés. (French)
    30 November 2021
    0 references
    Das Projekt wird durchgeführt, indem das Leitungswärmenetz durch vorisolierte unterirdische Wärmewärme ersetzt, ein vorisoliertes Wärmenetz auf neuen Abschnitten errichtet wird oder die Wärmedämmung auf bestehenden Freileitungsleitungen ersetzt wird, sowie die notwendige Wartung und Reparatur von Stahl- und Stahlbetonleitungen. Im Rahmen des Projekts wird die Stilllegung der Fernwärmekammern des unterirdischen Wärmeschneiders durchgeführt. Darüber hinaus werden Verbindungen zu bestehenden Gebäuden zusammen mit einzelnen Kreuzungen gebaut, so dass Gruppenknoten entfernt werden können. (German)
    7 December 2021
    0 references

    Identifiers

    POIS.01.07.02-00-0001/17
    0 references