Installation of 5 photovoltaic power plants with a total capacity of 60.71 kW and installation of 9 heat pumps with a total capacity of 80.51 kW by the Cooperative Bank in Szczytno (Q131835)

From EU Knowledge Graph
Revision as of 21:46, 3 December 2021 by DG Regio (talk | contribs) (‎Removed claim: contained in NUTS (P1845): Olsztyński (Q2577186), Removing duplicate contained in NUTS)
Jump to navigation Jump to search
Project Q131835 in Poland
Language Label Description Also known as
English
Installation of 5 photovoltaic power plants with a total capacity of 60.71 kW and installation of 9 heat pumps with a total capacity of 80.51 kW by the Cooperative Bank in Szczytno
Project Q131835 in Poland

    Statements

    0 references
    0 references
    0 references
    0 references
    552,713.35 zloty
    0 references
    132,651.20 Euro
    13 January 2020
    0 references
    1,004,933.37 zloty
    0 references
    241,184.01 Euro
    13 January 2020
    0 references
    55.0 percent
    0 references
    4 November 2019
    0 references
    30 April 2020
    0 references
    BANK SPÓŁDZIELCZY W SZCZYTNIE
    0 references
    0 references

    53°42'31.0"N, 20°42'12.2"E
    0 references

    53°42'16.6"N, 20°57'39.2"E
    0 references

    53°31'47.3"N, 20°43'36.5"E
    0 references

    53°39'7.9"N, 20°47'30.1"E
    0 references

    53°33'49.3"N, 20°59'48.8"E
    0 references

    53°23'54.2"N, 20°56'46.7"E
    0 references
    Inwestycja objęta niniejszym projektem polega na uruchomieniu elektrowni fotowoltaicznych o mocy łącznej 60,71 kW i Montażu 9 pomp ciepła o mocy łącznej 80,51 kW w Wielbarku, Pasymiu, Purdzie, Dźwierzutach, Szczytnie, i Jedwabnie. Projekt spełnia wszystkie warunki brzegowe określone w SzOOP RPO WiM 2014-2020. Wnioskodawca posiada ważne dokumenty przyłączeniowe do sieci energetycznej. Przedmiotowy projekt nie wymaga zgłoszeń budowy. Niniejszy projekt zakłada dostawę i montaż instalacji fotowoltaicznych z wykorzystaniem technologii polikrystalicznej do produkcji energii elektrycznej. Inwestycja polega na montażu łącznie 199 szt. paneli fotowoltaicznych o mocy 60,71 kW. Panele fotowoltaiczne wykorzystują zjawisko fotowoltaiczne do przetwarzania promieniowania słonecznego na energię elektryczną. Za pomocą połączeń kablowych przekazują one energię do falowników, gdzie następuje zmiana prądu stałego w prąd zmienny. Projekt zakłada również montaż pomp ciepła o mocy grzewczej 80,51 kW. Pompa ciepła to urządzenie, które wykorzystuje podstawowe prawa fizyki - wymusza przepływ ciepła z obszaru o niższej temperaturze do miejsca gdzie ta temperatura jest wyższa. 1. Szczytno, ul. Łomżyńska 20 (działka 168/2, obręb 0005) - instalacja fotowoltaiczna o mocy 9,15 kW, 2 pompy powietrzne o mocy grzewczej 19,9kW 2. Dźwierzuty, ul. Kajki 1 (działka 592, obręb 0002)- instalacja fotowoltaiczna o mocy 19,52 kW, 2 pompy powietrzne o mocy grzewczej 19,9kW 3. Jedwabno, ul. Olsztyńska 2 (działka 256, obręb 0005) - instalacja fotowoltaiczna o mocy 6,41 kW, 1 pompa powietrzna o mocy grzewczej 7,8 kW 4. Pasym, ul. Krótka 1 (działka 145, obręb 0004)- instalacja fotowoltaiczna o mocy 13,42 kW, 2 pompy powietrzne o mocy grzewczej 19,9 kW 5. Wielbark, ul. Jagiełły 7 (działka 702, obręb 0020)- instalacja fotowoltaiczna o mocy 12.21 kW, powietrzna pompa o mocy grzewczej 7,8 kW 6. Purda 71B (działka 528/4, obręb 0023)powietrzna pompa ciepła o mocy grzewczej 5,21 kW (Polish)
    0 references
    The investment covered by this project consists of the launch of photovoltaic power plants with a total capacity of 60.71 kW and the assembly of 9 heat pumps with a total capacity of 80.51 kW in Wielbark, Pasymi, Purda, Dźwiejet, Szczytnie, and silk. The project meets all the shore conditions specified in the SHOOP RPO WiM 2014-2020. The applicant shall have valid connection documents to the power grid. This project does not require construction notifications. This project involves the supply and assembly of photovoltaic installations using polycrystalline technology for the production of electricity. The investment consists of mounting a total of 199 units of photovoltaic panels with a capacity of 60.71 kW. Photovoltaic panels use the photovoltaic phenomenon to convert solar radiation into electricity. By means of cable connections, they transmit energy to inverters, where the direct current changes to alternating current. The project also includes the installation of heat pumps with a heating power of 80.51 kW. Heat pump is a device that uses basic laws of physics – it forces heat flow from a lower temperature area to a place where the temperature is higher. 1. Szczytno, str. Lomżyńska 20 (part 168/2, perimeter 0005) is a photovoltaic installation with a power of 9.15 kW, 2 air pumps with a heating power of 19.9 kW 2. Violets, st. Kaiki 1 (Chalot 592, Circuit 0002) – photovoltaic installation with a power of 19.52 kW, 2 air pumps with heating power 19,9 kW 3. Jedwabno, ul. Olsztyńska 2 (part 256, perimeter 0005) – photovoltaic installation with a power of 6.41 kW, 1 air pump with heating power 7.8 kW 4. Pasym, str. Short 1 (gun 145, perimeter 0004) – photovoltaic installation with a power of 13.42 kW, 2 air pumps with heating power 19,9 kW 5. Wielbark, str. Jagiełły 7 (part 702, perimeter 0020) – photovoltaic installation with a power of 12.21 kW, air pump with heating power 7.8 kW 6. Purda 71B (gun 528/4, perimeter 0023)air heat pump with heating power 5,21 kW (English)
    21 October 2020
    0 references
    L’investissement couvert par ce projet consiste à lancer des centrales photovoltaïques d’une capacité totale de 60,71 kW et à installer 9 pompes à chaleur d’une capacité totale de 80,51 kW à Wielbark, Pasymi, Purda, Cranes, Peaks et soie. Le projet répond à toutes les conditions limites fixées dans le SzOOP ROP WiM 2014-2020. Le demandeur possède des documents de connexion valides au réseau électrique. Le projet en question ne nécessite pas de notification de la construction. Ce projet concerne la fourniture et l’assemblage d’installations photovoltaïques utilisant la technologie polycristalline pour la production d’électricité. L’investissement consiste à assembler un total de 199 panneaux photovoltaïques d’une capacité de 60,71 kW. Les panneaux photovoltaïques utilisent le phénomène photovoltaïque pour convertir le rayonnement solaire en électricité. Au moyen de connexions par câble, ils transmettent de l’énergie aux onduleurs, où il y a un changement de courant continu en courant alternatif. Le projet prévoit également l’installation de pompes à chaleur d’une puissance calorifique de 80,51 kW. Une pompe à chaleur est un dispositif qui utilise les lois de base de la physique — il force le flux de chaleur d’une zone avec une température inférieure à un endroit où cette température est plus élevée. 1. Szczytno, St. Łomżyńska 20 (plot 168/2, surface 0005) — installation photovoltaïque de 9,15 kW, 2 pompes à air d’une puissance de chauffage de 19,9 kW 2. Bocaux de circulation, st. Kajki 1 (plot 592, surface 0002) — installation photovoltaïque d’une puissance de 19,52 kW, 2 pompes à air d’une puissance de 19,9 kW 3. Jedwabno, St. Olsztyńska 2 (plot 256, surface 0005) — installation photovoltaïque d’une puissance de 6,41 kW, 1 pompe à air d’une puissance de 7,8 kW 4. Pasym, St. Court 1 (plot 145, surface 0004) — système photovoltaïque de 13,42 kW, 2 pompes à air d’une puissance de chauffage de 19,9 kW 5. Wielbark, St. Jagiełły 7 (plot 702, périmètre 0020) — 12,21 kW installation photovoltaïque, pompe à air d’une puissance de chauffage de 7,8 kW 6. Pompe à chaleur à air Purda 71B (plot 528/4, volume 0023) d’une puissance calorifique de 5,21 kW (French)
    2 December 2021
    0 references

    Identifiers

    RPWM.04.01.00-28-0216/17
    0 references