CONSTRUCTION OF THE LINE KRZEWINA – PLEWISKA LINE WITH THE EXTENSION OF THE STATION IN THIS LINE (Q86135)
Jump to navigation
Jump to search
Project Q86135 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | CONSTRUCTION OF THE LINE KRZEWINA – PLEWISKA LINE WITH THE EXTENSION OF THE STATION IN THIS LINE |
Project Q86135 in Poland |
Statements
207,912,301.53 zloty
0 references
207,912,301.53 zloty
0 references
100.0 percent
0 references
1 January 2014
0 references
31 December 2022
0 references
POLSKIE SIECI ELEKTROENERGETYCZNE S.A
0 references
W ramach projektu przewidziano budowę linii dwutorowej 400 kV Piła Krzewina – Plewiska (czasowo pracującej na napięciu 220 kV) wraz z rozbudową stacji SE Piła Krzewina oraz SE Plewiska. Bezpośrednim celem Projektu jest: a) poprawa bezpieczeństwa sieci w północno - zachodnim obszarze kraju, poprawa zasilania obszaru Wielkopolski, b) poprawa warunków wyprowadzenia mocy z PGE Górnictwo i Energetyka Konwencjonalna S.A. Oddział Zespół Elektrowni Dolna Odra (zwana dalej: Elektrownia Dolna Odra) w kierunku SE Plewiska (poprzez SE Baczyna w budowie), c) stworzenie warunków do możliwego późniejszego przyłączenia OZE, d) poprawa przesyłu dla wymiany transgranicznej pomiędzy systemami elektroenergetycznymi Polski i Niemiec. e) realizacja Projektu umożliwi zwiększenie zdolności przesyłowych, poprawi bezpieczeństwo pracy sieci w północno-zachodnim obszarze kraju. Celem Projektu jest również: a) zmniejszenie ograniczeń przesyłowych w KSE, celem umożliwienia bezpiecznej i niezawodnej wymiany energii elektrycznej. b) poprawa jakości przesyłu energii elektrycznej. c) poprawa niezawodności pracy całego KSE. (Polish)
0 references
The project included the construction of a two-track line of 400 kV Piła Krzewina – Plewiska (temporarily working at a voltage of 220 kV) together with the expansion of the SE Piła Krzewina and SE Plewiska stations. The direct objective of the Project is to: a) improvement of network safety in the north-western area of the country, improvement of power supply of the Wielkopolska area, b) improving the conditions for power extraction from PGE Mining and Energetyka Konwencjonalna S.A. Branch Zespół Elektrowni Dolna Odra (hereinafter referred to as: Lower Odra Power Plant) towards SE Plewiska (through SE Baczyna under construction), c) creating conditions for possible subsequent connection of RES, d) improving transmission for cross-border exchanges between the electricity systems of Poland and Germany. e) implementation of the Project will enable increased transmission capacity, improve the safety of the network operation in the north-western area of the country. The aim of the project is also to: a) Reducing transmission congestion in the CEA, in order to allow safe and reliable exchange of electricity. b) improve the quality of transmission of electricity. c) Improve the reliability of the operation of the entire KSE. (English)
14 October 2020
0 references
Le projet prévoyait la construction d’une ligne à double voie de 400 kV Piła Krzewina — Plewiska (traduite temporairement à 220 kV) ainsi que l’extension des stations SE Piła Krzewina et Plewiska. L’objectif direct du projet est de: a) l’amélioration de la sécurité du réseau dans la zone nord-ouest du pays, l’amélioration de l’alimentation électrique de la région de Wielkopolska, b) l’amélioration des conditions de production d’électricité de la centrale électrique PGE Górnictwo i Energetyka Konwencjonalna S.A. (ci-après dénommée: La centrale électrique basse d’Odra) en direction de la SE Plewiska (par l’intermédiaire de SE Baczyna en construction), c) la création des conditions d’une éventuelle connexion SER ultérieure, d) l’amélioration du transport pour les échanges transfrontaliers entre les réseaux électriques polonais et allemands. L’objectif du projet est également de: a) réduire la congestion des KSE afin de permettre un échange sûr et fiable d’électricité. b) améliorer la qualité du transport d’électricité. c) améliorer la fiabilité du fonctionnement de l’ensemble du KSE. (French)
30 November 2021
0 references
Identifiers
POIS.07.01.00-00-0017/17
0 references