Construction of a photovoltaic farm intended for the production of electricity from a renewable source in Pargovo (Q137700)
Jump to navigation
Jump to search
Project Q137700 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a photovoltaic farm intended for the production of electricity from a renewable source in Pargovo |
Project Q137700 in Poland |
Statements
3,075,916.29 zloty
0 references
3,903,612.7 zloty
0 references
78.8 percent
0 references
1 April 2016
0 references
15 February 2019
0 references
SGE SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Projekt zakłada wybudowanie nowej infrastruktury stanowiącej elektrownię do wytwarzania energii elektrycznej z odnawialnych źródeł energii w postaci promieniowania słonecznego tj. budowę farmy fotowoltaicznej o mocy 960 kW wraz z kontenerową stacją transformatorową oraz infrastrukturą towarzyszącą. Projekt posiada charakter stacjonarny-farma zostanie wybudowana na części działki nr 9/17 w miejscowości Pargowo. Spółka legitymuje się długoterminową umową dzierżawy, zawartą w celu zrealizowania przedmiotowego projektu. Rozpoczęcie realizacji projektu na etapie prac przygotowawczych przypada na II i III kwartał br. Spółka przewiduje rozpoczęcie rzeczowe projektu w III kwartale 2017 roku (zakup niezbędnej infrastruktury do budowy farmy o mocy 960kW oraz roboty budowlane) a zakończenie realizacji w I kwartale 2018 r.. W ramach prac przygotowawczych podjęto czynności polegające na pozyskaniu niezbędnej dokumentacji prawnej w postaci wymaganych decyzji administracyjnych do budowy farmy oraz pozyskania niezbędnej dokumentacji technicznej, ponadto zlecono wykonanie studium wykonalności. W I kwartale 2017 r. Wnioskodawca przewiduje przeprowadzenie postępowania o udzielenie zamówienia w ramach projektu zgodnie z zasadami udzielania zamówień w projektach realizowanych w ramach RPO WZ 2014-2020 i podpisanie umowy z wykonawcą robót w I kwartale 2017 r.. Po wybudowaniu elektrowni zostanie ona podłączona do sieci OSD w celu sprzedaży całości wyprodukowanej zielonej energii. W ramach projektu Wnioskodawca planuje nabyć najlepsze dostępne rozwiązania technologiczne w postaci modułów polikrystalicznych o mocy 250W. Ponadto w ramach projektu Wnioskodawca przewiduje zakup beztransformatorowych inwerterów trójfazowych o mocy 20kW, z uwagi na ich liczne zalety, w szczególności z uwagi na ich 98-99 % sprawność. Zakup 48 inwerterów pozwoli na osiągniecie zakładanego poziomu produktywności zaprojektowanej farmy fotowoltaicznej (Polish)
0 references
The project involves the construction of a new infrastructure for the generation of electricity from renewable energy sources in the form of solar radiation, i.e. the construction of a 960 kW photovoltaic farm with a container transformer station and accompanying infrastructure. The project has a stationary character-farm will be built on part of plot No 9/17 in the town of Pargowo. The company has a long-term lease agreement concluded to carry out the project in question. The implementation of the project at the preparatory stage starts in the second and third quarters of this year. The company envisages launching a project in the third quarter of 2017 (purchase of the necessary infrastructure for the construction of a 960 kW farm and construction works) and completion in the first quarter of 2018. As part of the preparatory work, steps were taken to obtain the necessary legal documentation in the form of required administrative decisions for the construction of the farm and obtaining the necessary technical documentation, and a feasibility study was commissioned. In the first quarter of 2017, the applicant envisages carrying out a contract award procedure within the project in accordance with the rules for awarding contracts in projects carried out within the framework of the RPO WZ 2014-2020 and the signing of a contract with the contractor in the first quarter of 2017. Once the power plant is built, it will be connected to the OSD network to sell all the green energy produced. As part of the project, the applicant plans to acquire the best available technological solutions in the form of 250 W polycrystalline modules. In addition, under the project, the applicant envisages the purchase of non-transformer-free three-phase inverters with a capacity of 20 kW, due to their numerous advantages, in particular because of their 98-99 % efficiency. The purchase of 48 inverters will allow you to achieve the expected level of productivity of the designed photovoltaic farm (English)
21 October 2020
0 references
Le projet prévoit la construction d’une nouvelle infrastructure constituant une centrale électrique pour la production d’électricité à partir de sources d’énergie renouvelables sous forme de rayonnement solaire, c’est-à-dire la construction d’une exploitation photovoltaïque d’une capacité de 960 kW, ainsi que d’une station de transformation de conteneurs et des infrastructures associées. Le projet a un caractère stationnaire — la ferme sera construite sur une partie de la parcelle no 9/17 à Pargowo. L’entreprise dispose d’un contrat de location à long terme conclu pour mener à bien le projet en question. Le début du projet au stade préparatoire se situe aux 2e et 3e trimestres de cette année. L’entreprise envisage le lancement du projet physique au troisième trimestre 2017 (achat des infrastructures nécessaires à la construction d’une exploitation de 960 kW et travaux de construction) et l’achèvement au premier trimestre 2018. Dans le cadre des travaux préparatoires, des mesures ont été prises pour obtenir la documentation juridique nécessaire sous la forme des décisions administratives requises pour la construction de l’exploitation et pour obtenir la documentation technique nécessaire, en outre, une étude de faisabilité a été commandée. Au cours du premier trimestre 2017, la requérante envisage de mener une procédure de passation de marché dans le cadre du projet conformément aux règles d’attribution des marchés dans le cadre de projets réalisés dans le cadre du ROP WZ 2014-2020 et de signer un contrat avec le contractant au cours du premier trimestre 2017. Une fois la centrale construite, elle sera raccordée au réseau de GRD afin de vendre toute l’énergie verte produite. Dans le cadre du projet, la requérante prévoit d’acquérir les meilleures solutions technologiques disponibles sous la forme de modules polycristallins de 250 W. En outre, dans le cadre du projet, la requérante envisage l’achat d’onduleurs triphasés non transformateurs d’une puissance de 20 kW, compte tenu de leurs nombreux avantages, notamment en raison de leur efficacité de 98 à 99 %. L’achat de 48 onduleurs vous permettra d’atteindre le niveau de productivité attendu de la ferme photovoltaïque conçue (French)
2 December 2021
0 references
Identifiers
RPZP.02.10.00-32-A066/16
0 references