Construction of wind farm (ST1, ST3) in the municipality of Strzałkowo with a capacity of 4 MW (2 x 2 MW) together with infrastructure and power connection. (Q134741)

From EU Knowledge Graph
Revision as of 20:16, 2 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in fr: translated_label)
Jump to navigation Jump to search
Project Q134741 in Poland
Language Label Description Also known as
English
Construction of wind farm (ST1, ST3) in the municipality of Strzałkowo with a capacity of 4 MW (2 x 2 MW) together with infrastructure and power connection.
Project Q134741 in Poland

    Statements

    0 references
    6,296,181.47 zloty
    0 references
    1,511,083.55 Euro
    13 January 2020
    0 references
    16,551,476.0 zloty
    0 references
    3,972,354.24 Euro
    13 January 2020
    0 references
    38.04 percent
    0 references
    1 January 2018
    0 references
    31 December 2018
    0 references
    GÓLCZ I SYNOWIE SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references
    Planowane przedsięwzięcie polega na budowie elektrowni wiatrowej składającej się z dwóch turbin wiatrowych ST1 i ST3 o mocy 2 MW każda (4 MW łącznie) o maksymalnej wysokości do 160 m n.p.t., wraz z elementami towarzyszącymi (linią energetyczną SN, kablami sterowania i niezbędnymi urządzeniami elektroenergetycznymi). Elektrownie wiatrowe zalicza się do źródeł energii odnawialnej. W procesie produkcyjnym nie wykorzystuje się żadnego rodzaju paliw, jedynie energię wiatru. Podstawowymi elementami instalacji są rotor, który przekształca energię wiatru w energię mechaniczną oraz generator prądu umieszczony w gondoli, który zamienia energię mechaniczną w elektryczną. Zamiana energii następuje dzięki zjawisku indukcji elektromagnetycznej. Moc elektrowni jest wypadkową siły wiatru w miejscu jej lokalizacji, oraz konstrukcji elektrowni. Jednym z głównych czynników gospodarki każdego kraju jest bezpieczeństwo energetyczne. Wyrażenie to należy rozumieć jako stan gospodarki umożliwiający pokrycie bieżącego i perspektywicznego zapotrzebowania odbiorców na paliwa i energię w sposób technicznie i ekonomicznie uzasadniony, przy zachowaniu wymagań ochrony środowiska. Budowa naszej elektrowni wspiera takie działanie, a także zwiększa poziom produkcji energii ze źródeł odnawialnych, przez co efektywnie wspiera przejście polskiej gospodarki na niskoemisyjną.Aby ją wybudować niezbędne jest:1. Zakup usług i materiałów budowlanych niezbędnych do budowy dróg dojazdowych i placów montażowych, fundamentów pod wieże do turbin, a także przyłącza energetycznego, linii kablowej SN, uziemienia i kontenerowej stacji pomiarowej.2. Zakup środków trwałych w postaci kompletnych urządzeń elektro-energetycznych niezbędnych do przetwarzania energii wiatrowej na elektryczną - turbin wiatrowych.3. Posiadanie uprawnionego inspektora nadzoru inwestorskiegoEfektami projektu będą:Liczba wybudowanych jednostek wytwarzania energii elektrycznej z OZE – 2Liczba przedsiębiorstw otrzymujących wsparcie - 1. (Polish)
    0 references
    The planned project consists of the construction of a wind power plant consisting of two ST1 and ST3 wind turbines with a capacity of 2 MW each (4 MW in total) with a maximum height of up to 160 m above sea level, together with accompanying elements (SN power line, control cables and necessary power equipment). Wind farms are part of renewable energy sources. The production process does not use any kind of fuel, only wind energy. The main elements of the installation are a rotor, which converts wind energy into mechanical energy and a current generator placed in the gondola, which converts mechanical energy into electrical energy. The change of energy is due to the phenomenon of electromagnetic induction. The power plant is the resultant wind power at its location, and the construction of the power plant. One of the main factors in each country’s economy is energy security. This expression should be understood as the state of the economy enabling consumers to meet current and prospective fuel and energy needs in a technically and economically justified manner, while respecting environmental requirements. The construction of our power plant supports this activity and also increases the level of production of renewable energy sources, which effectively supports the transition of the Polish economy to low carbon. Purchase of services and building materials necessary for the construction of access roads and assembly sites, foundations for turbine towers, as well as power connection, cable line SN, grounding and container measuring station.2. Purchase of fixed assets in the form of complete electrical and energy equipment necessary for converting wind energy into electricity – wind turbines.3. Having an authorised investor supervision inspectorThe project effects will be:Number of built electricity generation units from RES – 2Number of enterprises receiving support – 1. (English)
    21 October 2020
    0 references

    Identifiers

    RPWP.03.01.01-30-0011/17
    0 references