Comprehensive extension and reconstruction of sewage treatment plants and water and sewage networks in the Bogoria Agglomeration (Q127779)
Jump to navigation
Jump to search
Project Q127779 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Comprehensive extension and reconstruction of sewage treatment plants and water and sewage networks in the Bogoria Agglomeration |
Project Q127779 in Poland |
Statements
2,489,031.75 zloty
0 references
3,111,289.7 zloty
0 references
80.0 percent
0 references
16 November 2017
0 references
31 December 2019
0 references
GMINA BOGORIA
0 references
Projektu ma za zadanie uporządkowanie gospodarki wodno-ściekowej na terenie Gminy Bogoria poprzez przebudowę oczyszczalni ścieków oraz przebudowę sieci wodno-kanalizacyjnej na terenie aglomeracji. Maksymalna przepustowość oczyszczalni ścieków wynosi 600 m3/d. Cel projektu wpisuje się w cel szczegółowy Działania 4.3 Gospodarka wodnościekowa w ramach RPOWŚ 2014-2020, tj. „Zwiększony odsetek ludności korzystającej z systemu oczyszczania ścieków zgodnego z dyrektywą dotyczącą ścieków komunalnych”. Działania objęte projektem przyczynia się do likwidacji istniejących niedoborów w zakresie systemów odprowadzania ścieków i doprowadzania wody na terenie aglomeracji. Okres realizacji projektu: 03.2018-12.2019. 100% RLM korzysta z sieci kanalizacji w aglomeracji Bogoria. Projekt realizowany na terenie aglomeracji 4933 RLM, ujęty jest w KPOŚK i Master Planie. Wpisuje się w Program ochrony środowiska WŚ w priorytet Zasoby wodne i gospodarka wodna (ZW). Wnioskodawca posiada Program Funkcjonalno Użytkowy warunkujących realizację inwestycji od strony formalno-prawnej, Wskaźniki: Wielkość ładunku ścieków poddanych ulepszonemu oczyszczaniu - 4933 RLM, Liczba dodatkowych osób korzystających z ulepszonego oczyszczania ścieków - 4933 RLM, Liczba przebudowanych oczyszczalni ścieków komunalnych - 1 szt., Długość przebudowanej kanalizacji sanitarnej - 2,5 km, Długość przebudowanej sieci wodociągowej - 2,7 km. (Polish)
0 references
The project is designed to organise water and sewage management in the municipality of Bogoria by rebuilding the sewage treatment plant and rebuilding the water and sewage network in the agglomeration area. The maximum throughput of the sewage treatment plant is 600 m³/d. The project’s objective is in line with the specific objective of Measure 4.3 Water management within RPOWŚ 2014-2020, i.e. ‘Increased proportion of the population using a waste water treatment system in accordance with the Urban Waste Water Directive’. The activities covered by the project contribute to the elimination of existing shortages of sewage and water supply systems in the agglomeration area. Period of implementation of the project: 03.2018-12.2019. 100 % of RLM uses sewage networks in the Bogoria agglomeration. The project carried out in the agglomeration of 4933 RLM, is included in KPOŚK and Master Plan. It is part of the WW environmental programme as a priority for Water Resources and Water Management (ZW). The Applicant has a Functional User Program that determines the implementation of the investment on the formal and legal side, Indicators: Volume of waste water cargo undergoing improved treatment – 4933 RLM, Number of additional persons benefiting from improved waste water treatment – 4933 RLM, Number of reconstructed municipal waste water treatment plants – 1 pcs, Length of reconstructed sanitary sewage system – 2.5 km, Length of reconstructed water supply system – 2.7 km. (English)
21 October 2020
0 references
L’objectif du projet est d’organiser la gestion de l’eau et des eaux usées dans la municipalité de Bogoria par la reconstruction d’une station d’épuration et la reconstruction du réseau d’eau et d’assainissement de l’agglomération. Le débit maximal de la station d’épuration des eaux usées est de 600 m³/j. L’objectif du projet est conforme à l’objectif spécifique de la mesure 4.3 Gestion étanche dans le cadre du RPOWŚ 2014-2020, à savoir: «Augmentation de la part de la population utilisant un système de traitement des eaux usées conformément à la directive relative aux eaux urbaines résiduaires». Les activités couvertes par le projet contribuent à l’élimination des pénuries existantes de collecte des eaux usées et de systèmes d’approvisionnement en eau dans l’agglomération. Durée du projet: 03.2018-12.2019. 100 % des EH utilisent le réseau d’égouts dans l’agglomération de Bogoria. Le projet mis en œuvre dans l’agglomération de 4933 EH est inclus dans le KPOŚK et le plan directeur. Il fait partie du programme environnemental du WW avec la priorité des ressources en eau et de la gestion de l’eau (ZW). La requérante dispose d’un programme de services publics fonctionnels qui détermine la mise en œuvre de l’investissement du point de vue formel et juridique, Indicateurs: Volume de la charge des eaux usées traitées avec un traitement amélioré — 4933 EH, Nombre de personnes supplémentaires utilisant un traitement amélioré des eaux usées — 4933 EH, Nombre d’installations de traitement des eaux urbaines résiduaires reconstruites — 1 pcs., Longueur du système d’assainissement reconstruit — 2,5 km, longueur du réseau d’approvisionnement en eau reconstruit — 2,7 km. (French)
2 December 2021
0 references
Identifiers
RPSW.04.03.00-26-0009/17
0 references