Construction of WSS infrastructure in the separate area served by Water Supply and Sewerage EOOD, Vidin (Q3832241)

From EU Knowledge Graph
Revision as of 10:20, 2 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): In total, for the Vidin agglomeration, the following measures are foreseen:-by component Water supply: •replacement of the existing lead pipe ph900 mm with PVC_O pipes with diameter F630mm, L = 10.372 km with PN 12.5 atm;•replacement of the existing two etherite pipes f536 mm and of the existing two steel pipes f630 mm by f500 mm PVC_O pipes with PN 12.5 atm and total length L = 4.149 km; L total=14.521 km.-by component Wastewater collection is...)
Jump to navigation Jump to search
Project Q3832241 in Bulgaria
Language Label Description Also known as
English
Construction of WSS infrastructure in the separate area served by Water Supply and Sewerage EOOD, Vidin
Project Q3832241 in Bulgaria

    Statements

    0 references
    15,246,929.81 Bulgarian lev
    0 references
    7,775,934.2 Euro
    1 December 2021
    0 references
    19,722,445.83 Bulgarian lev
    0 references
    10,058,447.37 Euro
    1 December 2021
    0 references
    0.77 percent
    0 references
    5 September 2019
    0 references
    5 March 2024
    0 references
    0 references
    0 references
    Общо, за Агломерация Видин, се предвиждат следните мерки:-по компонент Водоснабдяване:•подмяна на съществуващия довеждащ водопровод ф900мм стомана с PVC_O тръби с диаметър Ф630mm, L = 10, 372 km с PN 12,5 atm;•подмяна на съществуващите две етернитови тръби ф536 mm и на съществуващите две стоманени тръби ф630 mm с ф500mm PVC_O тръби с PN 12,5 atm и обща дължина L = 4,149 km; L обща=14,521km.-по компонент Събиране на отпадъчни води се предвижда:•реконструкция на част от Главен Колектор II с яйцевиден профил 1520/2400 mm и 1120/2150 mm. Той ще бъде подменен с канал от GRP с ф1800mm с дължина L = 1,356km и участък с РР тръби 2xф1000mm с L =94m при преминаване под ж.п. линията; L обща=1,450 km.-по компонент Пречистване на отпадъчни води не са предвидени инвестиционни мерки. ПСОВ е в процес на изграждане. (Bulgarian)
    0 references
    In total, for the Vidin agglomeration, the following measures are foreseen:-by component Water supply: •replacement of the existing lead pipe ph900 mm with PVC_O pipes with diameter F630mm, L = 10.372 km with PN 12.5 atm;•replacement of the existing two etherite pipes f536 mm and of the existing two steel pipes f630 mm by f500 mm PVC_O pipes with PN 12.5 atm and total length L = 4.149 km; L total=14.521 km.-by component Wastewater collection is foreseen: •Reconstruction of a part of Master Collector II with an egg profile of 1520/2400 mm and 1120/2150 mm. It will be replaced by a GRP channel with f1800 mm with length L = 1.356 km and PP section 2x1000 mm with L =94 m when crossing the line; L total = 1.450 km.- by component Wastewater treatment no investment measures are foreseen. The WWTP is under construction. (English)
    2 December 2021
    0 references
    Видин
    0 references

    Identifiers

    BG16M1OP002-1.016-0006
    0 references