Execution of two 40 kWp photovoltaic installations located in Lidzbark Warmiński (Q132063)

From EU Knowledge Graph
Revision as of 09:22, 2 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): Le projet consiste en deux installations photovoltaïques d’une capacité de 40kWp pour deux stations d’épuration situées sur des parcelles: 48/2 dans la zone cadastrale 3 à ul. Dąbrowskiego 22A et 69/2 dans la zone cadastrale 8 à ul. Kalinowski 11A à Lidzbark Warminski. Le projet mettra en œuvre les éléments suivants nécessaires au bon fonctionnement de la centrale photovoltaïque: travaux de construction, travaux géodésiques, travaux de démontage...)
Jump to navigation Jump to search
Project Q132063 in Poland
Language Label Description Also known as
English
Execution of two 40 kWp photovoltaic installations located in Lidzbark Warmiński
Project Q132063 in Poland

    Statements

    0 references
    414,962.84 zloty
    0 references
    99,591.08 Euro
    13 January 2020
    0 references
    488,191.58 zloty
    0 references
    117,165.98 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    9 March 2016
    0 references
    31 March 2019
    0 references
    PRZEDSIĘBIORSTWO WODOCIĄGÓW I KANALIZACJI, SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    54°7'50.2"N, 20°33'53.6"E
    0 references
    Projekt polega na wykonaniu dwóch instalacji fotowoltaicznych o mocach 40kWp na potrzeby dwóch stacji uzdatniania wody znajdujących się na działkach: 48/2 w obrębie ewidencyjnym 3 przy ul. Dąbrowskiego 22A oraz 69/2 w obrębie ewidencyjnym 8 przy ul. Kalinowskiego 11A w Lidzbarku Warmińskim. W ramach projektu wykonane zostaną następujące elementy niezbędnej do prawidłowego funkcjonowania elektrowni fotowoltaicznej: prace budowlane, prace geodezyjne, prace demontażowe, moduły fotowoltaiczne (panele), falowniki, konstrukcja, zabezpieczenia DC, zabezpieczenia AC, instalacja odgromowa, materiały montażowe, montaż, monitoring (system IT) oraz przewody stało i zmiennoprądowe. Projekt przyczyni się do zwiększenia udziału odnawialnych źródeł energii w ogólnym bilansie energetycznym regionu poprzez budowę infrastruktur do wytwarzania i dystrybucji energii pochodzącej ze źródeł odnawialnych. Projekt przyczyni się również do rozwiązania problemów przedsiębiorstwa w zakresie energii. Projekt przyczynia się do zaspokojenia wszystkich zdiagnozowanych problemów wszystkich wskazanych interesariuszy. Wnioskodawca jest przygotowany do rozpoczęcia inwestycji. Posiada dokumentację techniczną, pozwolenie na budowę, ani zgłoszenie prac budowlanych nie jest wymagane. Posiada również uregulowany stosunek prawny do nieruchomości zabudowanych i niezabudowanych, na których realizowany będzie projekt. Projekt przyczynia się do rozwiązania wszystkich problemów kluczowych interesariuszy zdiagnozowanych i opisanych w studium wykonalności. (Polish)
    0 references
    The project consists of two 40kWp photovoltaic installations for two water treatment stations located on the plots: 48/2 within the registration area 3 at ul. Dąbrowskiego 22A and 69/2 within the registration area 8 at ul. Kalinowski 11A in Lidzbark Warmiński. The project will produce the following elements necessary for the proper functioning of the photovoltaic power plant: construction works, surveying works, dismantling works, photovoltaic modules (panels), inverters, construction, DC security, AC security, lightning installation, assembly materials, assembly, monitoring (IT system) and fixed and fluctuating cables. The project will contribute to increasing the share of renewable energy sources in the overall energy balance of the region by building infrastructures for the generation and distribution of renewable energy sources. The project will also help solve the company’s energy problems. The project contributes to addressing all the identified problems of all the stakeholders identified. The applicant is prepared to start the investment. It has no technical documentation, a construction permit or a construction work application is required. It also has a regulated legal relationship to built-up and unbuilt real estate on which the project will be implemented. The project contributes to addressing all the problems of key stakeholders diagnosed and described in the feasibility study. (English)
    21 October 2020
    0 references
    Le projet consiste en deux installations photovoltaïques d’une capacité de 40kWp pour deux stations d’épuration situées sur des parcelles: 48/2 dans la zone cadastrale 3 à ul. Dąbrowskiego 22A et 69/2 dans la zone cadastrale 8 à ul. Kalinowski 11A à Lidzbark Warminski. Le projet mettra en œuvre les éléments suivants nécessaires au bon fonctionnement de la centrale photovoltaïque: travaux de construction, travaux géodésiques, travaux de démontage, modules photovoltaïques (panels), onduleurs, construction, protection CC, sécurité AC, système de protection contre la foudre, matériaux d’assemblage, assemblage, surveillance (système informatique) et conduits à courant fixe et variable. Le projet contribuera à accroître la part des sources d’énergie renouvelables dans le bilan énergétique global de la région en construisant des infrastructures pour la production et la distribution d’énergie à partir de sources renouvelables. Le projet contribuera également à résoudre les problèmes énergétiques de l’entreprise. Le projet contribue à résoudre tous les problèmes diagnostiqués de tous les intervenants identifiés. Le demandeur est prêt à lancer l’investissement. Il dispose d’une documentation technique, d’un permis de construire ou d’une notification des travaux de construction. Elle a également une relation juridique réglementée avec les propriétés bâties et non aménagées sur lesquelles le projet sera réalisé. Le projet contribue à résoudre tous les problèmes des principaux intervenants diagnostiqués et décrits dans l’étude de faisabilité. (French)
    2 December 2021
    0 references

    Identifiers

    RPWM.04.01.00-28-0484/16
    0 references