Construction of 2 photovoltaic micro-installation by ZPD company Piotr Żemojtel. (Q132002)
Jump to navigation
Jump to search
Project Q132002 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of 2 photovoltaic micro-installation by ZPD company Piotr Żemojtel. |
Project Q132002 in Poland |
Statements
405,501.0 zloty
0 references
477,060.0 zloty
0 references
85.0 percent
0 references
1 March 2018
0 references
29 June 2018
0 references
ZAKŁAD PRZEMYSŁU DRZEWNEGO PIOTR ŻEMOJTEL ZAKŁAD PRODUKCYJNY W GODKOWIE
0 references
Inwestycja polega na zakupie i montażu 2 elektrowni fotowoltaicznych o łącznej mocy 79,51kW. Będzie ona realizowana w jednej lokalizacji w Godkowie 43 na działce 88/3 o mocy 39,75 kW i działce 88/15 o 39,76 kW. Instalacje zajmą do 250 m2 powierzchni dachu każda. Projekt wpisuje się w typ projektu wymieniony w SzOOP dla działania 4.1 - instalacji wykorzystujących energię słońca - do 2 MWe/MWth. Instalacja zgodnie z możliwością opisaną w SzOOP będzie służyła potrzebom własnym przedsiębiorstwa i będzie podłączona do sieci, jednakże ze względu na moc instalacji (do 40 kW) zgodnie z art. 5 ustawy o odnawialnych źródłach energii (Dz.U. 2015) oraz Art. 7 ust. 8d ze znaczkiem 4-9 ustawy – Prawo energetyczne (Dz.U.1997) będzie ona dokonywana na podstawie zgłoszenia bez konieczności posiadania przez beneficjenta ważnych technicznych warunków przyłączenia wszystkich ujętych w projekcie źródeł wytwarzania energii do sieci elektroenergetycznej. Wnioskodawca posiada obecnie przyłącze gdzie moc umowna wynosi 250 kW – działka 88/3 oraz 40kW-działka 88/15. Projekt spełnia wszystkie warunki brzegowe określone w SzOOP. Inwestycja polega na montażu: działka 88/3-150 szt paneli polikrystalicznych, działka 88/15-150 szt paneli polikrystalicznych połączonych w samodzielne układy wraz z falownikami i z niezbędnym okablowaniem i osprzętem. Elektrownie będą podłączone do sieci, natomiast nie będzie potrzeby instalowania akumulatorów oraz regulatorów ładowania, ponieważ sieć jest w stanie przyjąć całą energię wyprodukowaną przez systemy fotowoltaiczne. Wyprodukowana energia elektryczna będzie wykorzystywana bezpośrednio na potrzeby własne a ewentualna nadwyżka będzie wprowadzana do sieci. (Polish)
0 references
The investment consists of the purchase and assembly of 2 photovoltaic power plants with a total capacity of 79.51 kW. It will be carried out in one location in Godków 43 on plot 88/3 with the power of 39.75 kW and plot 88/15 by 39.76 kW. Installations will cover up to 250 m² of roof surface each. The project fits into the type of project mentioned in the SzOOP for action 4.1 – solar energy installations – up to 2 MWe/MWth. The installation in accordance with the possibility described in the SzOOP will serve the company’s own needs and will be connected to the grid, however due to the capacity of the installation (up to 40 kW) in accordance with Article 5 of the Renewable Energy Sources Act (OJ 2015) and Art. 7 paragraph. 8d with stamp 4-9 of the Energy Law (Journal of Laws 1997) will be made on the basis of the notification without the need for the beneficiary to have important technical conditions for connecting all energy generation sources included in the project to the electricity grid. The applicant now has a connection where the contractual power is 250 kW – parcel 88/3 and 40 kW- parcel 88/15. The project meets all the shore conditions specified in the Shoop. The investment consists of the assembly of: cannon 88/3-150 pcs of polycrystalline panels, cannon 88/15-150 pcs of polycrystalline panels connected in self-contained circuits with inverters and necessary wiring and fittings. Power plants will be connected to the grid, but there will be no need to install batteries and charging regulators, as the network is able to absorb all the energy produced by photovoltaic systems. The electricity produced will be used directly for own use and any surplus will be introduced into the grid. (English)
21 October 2020
0 references
L’investissement consiste en l’achat et l’installation de 2 centrales photovoltaïques d’une capacité totale de 79,51 kW. Il sera mis en œuvre en un seul endroit à Godkowo 43 sur la parcelle 88/3 avec une capacité de 39,75 kW et la parcelle 88/15 par 39,76 kW. Les installations occuperont jusqu’à 250 m² de toiture chacune. Le projet s’inscrit dans le type de projet indiqué dans SzOOP pour la mesure 4.1 — installations d’énergie solaire — jusqu’à 2 MWe/MWth. L’installation selon la possibilité décrite dans SzOOP répondra aux besoins propres de l’entreprise et sera raccordée au réseau, cependant, en raison de la capacité de l’installation (jusqu’à 40 kW) conformément à l’article 5 de la loi sur les sources d’énergie renouvelables (Journal officiel 2015) et à l’article 7, paragraphe. 8d avec un cachet 4-9 de la loi sur l’énergie (Journal des lois de 1997) sera faite sur la base d’une notification sans que le bénéficiaire ait besoin de conditions techniques valables pour connecter toutes les sources de production d’énergie incluses dans le projet au réseau électrique. Le demandeur dispose actuellement d’une connexion dont la puissance contractuelle est de 250 kW — parcelle 88/3 et 40 kW-plot 88/15. Le projet remplit toutes les conditions limites énoncées dans le SzOOP. L’investissement consiste à rassembler: parcelle 88/3-150 pcs de panneaux polycristallins, placette 88/15-150 pièces de panneaux polycristallins reliés dans des systèmes autonomes avec onduleurs et avec le câblage et les accessoires nécessaires. Les centrales électriques seront raccordées au réseau, mais il n’y aura pas besoin d’installer des batteries et des régulateurs de charge, car le réseau est capable d’absorber toute l’énergie produite par les systèmes photovoltaïques. L’électricité produite sera utilisée directement pour son propre usage et tout excédent sera injecté dans le réseau. (French)
2 December 2021
0 references
Identifiers
RPWM.04.01.00-28-0411/16
0 references