Development of waste water management in Solina Municipality – extension of waste water treatment plant and construction of sewage sewage in the Solina agglomeration. (Q118912)
Jump to navigation
Jump to search
Project Q118912 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Development of waste water management in Solina Municipality – extension of waste water treatment plant and construction of sewage sewage in the Solina agglomeration. |
Project Q118912 in Poland |
Statements
6,676,408.1 zloty
0 references
7,854,597.81 zloty
0 references
85.0 percent
0 references
10 February 2014
0 references
30 November 2017
0 references
GMINA SOLINA
0 references
Przedmiotem projektu jest rozbudowa oczyszczalni ścieków oraz budowa kanalizacji ściekowej w Aglomeracji Solina. Celem bezpośrednim projektu jest "Rozwinięty system oczyszczania ścieków w Aglomeracji Solina". Osiągnięcie tego celu ma umożliwić realizacji 3 zadań inwestycyjnych, które wchodzą w zakres projektu, tj.: 1. Rozbudowa istniejącej mechaniczno-biologicznej oczyszczalni ścieków zlokalizowanej w Solinie wykonanej w technologii żelbetowej. Zadanie obejmuje zakres prac, który wykonano w 2014 roku, w wyniku którego zakończono rozbudowęprzedmiotowej oczyszczalni do przepustowości Qśr.d=400m3/d przy Qmax.d=480m3/d. 2. Budowa sieci kanalizacji sanitarnej w miejscowości Myczków o długości 18,04km, w systemie grawitacyjno-ciśnieniowym (wykonanie w w okresie od 2014 do 2016 roku). 3. W związku z przebudową systemu kanalizacyjnego na Górze Jawor (zastąpienie istniejących oczyszczalni „Energetyk", „Góra Jawor" tłoczniami i przerzucie ścieków do oczyszczalni w Solinie) w tym budową kanalizacji dla miejscowości Jawor i części m. Bóbrka, a także zwiększonej ilości ścieków powstających w sezonie turystycznym nastąpi wzrost ilości dopływających ścieków do oczyszczalni w ilości około Qśr.d- 520m3/d stąd zaprojektowano kolejną przebudowę oczyszczalni ścieków, w wyniku której osiągnie ona przepustowość Qśr.d=920m3/d, przy Qmax.d=1196m3/d. (Polish)
0 references
The subject of the project is the extension of the sewage treatment plant and the construction of sewage in the Solina Agglomeration. The direct objective of the project is “Developed waste water treatment system in the Solina Agglomeration”. Achieving this objective is intended to enable the execution of 3 investment tasks that fall within the scope of the project, i.e.: 1. Expansion of the existing mechanical and biological sewage treatment plant located in Solina made in reinforced concrete technology. The task covers the scope of work that was carried out in 2014, as a result of which the extension of the subject treatment plant to Qśr.d=400 m³/d was completed at Qmax.d=480 m³/d. 2. Construction of a sewage system in Myczków with a length of 18.04 km, in a gravity-pressure system (performance in the period from 2014 to 2016). 3. In connection with the reconstruction of the sewage system on Mount Jawor (replacement of existing treatment plants “Energetyk”, “Góra Jawor” with pressing plants and transfer of sewage to the treatment plant in Solin) including the construction of sewage for Jawor and parts of m. Bóbrka, as well as the increased amount of sewage generated during the tourist season will increase the amount of sewage to the treatment plant in the amount of about Qśr.d- 520 m³/d from here. (English)
20 October 2020
0 references
Le projet concerne l’extension de la station d’épuration des eaux usées et la construction d’assainissement des eaux usées dans l’agglomération de Solina. L’objectif direct du projet est «Système élargi de traitement des eaux usées dans l’agglomération de Solina». Cet objectif est de permettre la réalisation de trois tâches d’investissement qui relèvent du champ d’application du projet, à savoir: 1. Extension de la station d’épuration mécanique et biologique des eaux usées située à Solin, réalisée en béton armé. L’activité couvre le champ des travaux réalisés en 2014, à la suite desquels l’extension de l’usine en cause à Qśr.d=400 m³/j a été achevée à Qmax.d=480 m³/j. Construction d’un réseau d’assainissement sanitaire à Myczków d’une longueur de 18,04 km, dans le système de gravité et de pression (exécuté entre 2014 et 2016). 3. En raison de la reconstruction du réseau d’assainissement du mont Jawor (remplacement des stations d’épuration existantes «Energetyk», «Góra Jawor» par des stations de compression et du transfert des eaux usées à la station d’épuration de Solin), y compris la construction d’égouts pour le village de Jawor et une partie de Bóbrka, ainsi que l’augmentation de la quantité d’eaux usées générées pendant la saison touristique, il y aura une augmentation de la quantité d’eaux usées entrant dans la station d’épuration dans la quantité de Qśr.d-520 m³/j, d’où une nouvelle reconstruction de la station d’épuration des eaux résiduaires, ce qui a donné lieu à un débit Qśr.d=920 m³/j, à Qmax.d=1196 m³/j. (French)
2 December 2021
0 references
Identifiers
RPPK.04.03.01-18-0022/16
0 references