Decarbonisation of public utility buildings in Pułtusk Municipality (Q108941)

From EU Knowledge Graph
Revision as of 10:39, 1 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): L’objet et le but du projet sont la thermomodernisation, l’utilisation des SER et le remplacement de l’éclairage pour 8 bâtiments publics économes en énergie: École primaire publique à Bobach, école primaire publique Bl. Jean-Paul II à Płocochów et Pułtusk: Bibliothèque publique Joachim Lelewel, gymnase public no 1, salle de sport au ZS no 4, MOSiR, ZS no 2 et gymnase. Dans le cadre du projet, des audits d’énergie et d’éclairage ont été réalisés...)
Jump to navigation Jump to search
Project Q108941 in Poland
Language Label Description Also known as
English
Decarbonisation of public utility buildings in Pułtusk Municipality
Project Q108941 in Poland

    Statements

    0 references
    5,920,304.63 zloty
    0 references
    1,420,873.11 Euro
    13 January 2020
    0 references
    7,401,305.95 zloty
    0 references
    1,776,313.43 Euro
    13 January 2020
    0 references
    79.99 percent
    0 references
    12 August 2015
    0 references
    31 January 2019
    0 references
    GMINA PUŁTUSK
    0 references

    52°42'18.4"N, 21°5'2.4"E
    0 references
    Przedmiotem, a zarazem celem projektu jest termomodernizacja wraz z wykorzystaniem OZE i wymianą oświetlenia na energooszczędne 8 budynków użyteczności publicznej: Publiczna Szkoła Podstawowa w Bobach, Publiczna Szkoła Podstawowa im. bł. Jana Pawła II w Płocochowie oraz w Pułtusku: Biblioteka Publiczna im. Joachima Lelewela, Publiczne Gimnazjum nr 1, Hala Sportowa przy ZS Nr 4, MOSiR, ZS nr 2 i Siłownia. W ramach projektu zostały sporządzone audyty energetyczne i oświetlania wskazujące, iż budynki będące przedmiotem projektu nie spełniają aktualnych norm termoizolacyjnych, przyczyniając się do niekorzystnego wpływu na jakość środowiska atmosferycznego. Przewidziane w projekcie działania skutkują poprawą efektywności energetycznej określonej dla energii końcowej o 67,96%. Dzięki realizacji projektu nastąpi zmniejszenie zapotrzebowania na energię, co poza wymierną korzyścią ekonomiczną związaną z obniżeniem kosztów eksploatacyjnych, przyczyni się do zmniejszenia ilości zanieczyszczeń wprowadzanych do powietrza. Projekt będzie realizowany na terenie Gminy Pułtusk, jednakże oddziaływał będzie pozytywnie na cały region, grupą docelową będą natomiast mieszkańcy Gminy. Prace w projekcie polegać będą: na ociepleniu ścian zewnętrznych warstwą styropianu, wymianie stolarki okiennej i drzwiowej, ociepleniu stropodachów, modernizacji instalacji c.o., modernizacji instalacji wentylacji, zastosowaniu pomp ciepła, wymianie oświetlenia na energooszczędne, montażu instalacji fotowoltaicznej i modernizacji źródeł ciepła. Zakres prac niezbędnych do wykonania na poszczególnych obiektach został określony w audytach energetycznych oraz audytach oświetlenia. W projekcie wykonane będą działania informacyjno-promocyjne i opracowanie: Programu Funkcjonalno-Użytkowego, Studium Wykonalności, audytów energetycznych i oświetlenia oraz ex post. Projekt będzie podzielony na etapy: przygotowawczy(opracowanie dokumentacji), realizacji przetargów, budowy, rozliczenia (Polish)
    0 references
    The subject of the project and at the same time the aim of the project is to modernise with the use of RES and to replace lighting with energy-efficient 8 public buildings: Public Elementary School in Boby, Public Primary School Bl. John Paul II in Płocochów and Pułtusk: Joachim Lelewel Public Library, Public High School No. 1, Sports Hall at ZS Nr 4, MOSiR, ZS No. 2 and Siłownia. As part of the project, energy audits and lighting have been prepared indicating that the buildings concerned by the project do not meet current thermal insulation standards, contributing to adverse effects on the quality of the environment. The measures provided for in the project result in an improvement of the energy efficiency defined for final energy by 67.96 %. The implementation of the project will reduce the demand for energy, which in addition to the measurable economic advantage of reducing operating costs, will help to reduce the amount of pollutants entering the air. The project will be implemented in Pułtusk commune, but will have a positive impact on the whole region, while the target group will be local residents. The project’s work will consist of: on insulation of external walls with a polystyrene layer, replacement of window and door joinery, insulation of stropodache, modernisation of central heating system, modernisation of ventilation system, use of heat pumps, exchange of lighting for energy efficient, installation of photovoltaic installation and modernisation of heat sources. The scope of work needed to be carried out on individual facilities has been defined in energy audits and lighting audits. The project will carry out information and promotion activities and develop: Functional and utility programme, feasibility study, energy audits and lighting and ex post. The project will be divided into stages: preparatory (development of documentation), execution of tenders, construction and settlement (English)
    20 October 2020
    0 references
    L’objet et le but du projet sont la thermomodernisation, l’utilisation des SER et le remplacement de l’éclairage pour 8 bâtiments publics économes en énergie: École primaire publique à Bobach, école primaire publique Bl. Jean-Paul II à Płocochów et Pułtusk: Bibliothèque publique Joachim Lelewel, gymnase public no 1, salle de sport au ZS no 4, MOSiR, ZS no 2 et gymnase. Dans le cadre du projet, des audits d’énergie et d’éclairage ont été réalisés indiquant que les bâtiments couverts par le projet ne répondent pas aux normes actuelles d’isolation thermique, ce qui contribue à des effets négatifs sur la qualité de l’environnement atmosphérique. Les mesures envisagées dans le projet de mesure entraînent une amélioration de l’efficacité énergétique spécifiée pour l’énergie finale de 67,96 %. La mise en œuvre du projet entraînera une réduction de la demande d’énergie qui, outre l’avantage économique mesurable de la réduction des coûts d’exploitation, contribuera à réduire la quantité de polluants entrant dans l’air. Le projet sera mis en œuvre dans la municipalité de Pułtusk, mais il aura un impact positif sur l’ensemble de la région, tandis que le groupe cible sera des résidents de la municipalité. Le projet consistera en: sur le réchauffement des murs extérieurs avec une couche de mousse de mousse, le remplacement de la menuiserie des fenêtres et des portes, le réchauffement des roseaux, la modernisation des installations de chauffage central, la modernisation des systèmes de ventilation, l’application de pompes à chaleur, le remplacement de l’éclairage pour les économies d’énergie, l’installation d’installations photovoltaïques et la modernisation des sources de chaleur. L’étendue des travaux nécessaires à l’exécution de chaque installation est définie dans les audits énergétiques et les audits d’éclairage. Le projet mènera des activités d’information et de promotion et développera: Programme fonctionnel et des services publics, étude de faisabilité, vérification de l’énergie et de l’éclairage et ex post. Le projet sera divisé en étapes: préparation (élaboration de la documentation), exécution des appels d’offres, construction, colonisation (French)
    1 December 2021
    0 references

    Identifiers

    RPMA.04.02.00-14-4565/16
    0 references