Expansion of power station 110/15 kV Ostrów Północ (GPZ) (Q86128)

From EU Knowledge Graph
Revision as of 21:27, 30 November 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in fr: translated_label)
Jump to navigation Jump to search
Project Q86128 in Poland
Language Label Description Also known as
English
Expansion of power station 110/15 kV Ostrów Północ (GPZ)
Project Q86128 in Poland

    Statements

    0 references
    0 references
    0 references
    6,520,856.51 zloty
    0 references
    1,565,005.56 Euro
    13 January 2020
    0 references
    8,959,504.23 zloty
    0 references
    2,150,281.02 Euro
    13 January 2020
    0 references
    72.78 percent
    0 references
    1 August 2017
    0 references
    30 August 2019
    0 references
    ENERGA-OPERATOR SPÓŁKA AKCYJNA
    0 references
    0 references

    51°38'49.9"N, 17°48'13.7"E
    0 references

    51°40'22.1"N, 17°46'48.7"E
    0 references
    Celem projektu jest zapewnienie bezpieczeństwa dostaw energii elektrycznej dla ok.19,9 tys odbiorców z terenu Miasta i gminy Ostrów Wielkopolski. Zakres projektu obejmuje przebudowę istniejącej stacji elektroenergetycznej 110/15 kV Ostrów Północ. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na którym odbywa się transformacja energii elektrycznej na napięcie 15 kV. (Polish)
    0 references
    The aim of the project is to ensure security of electricity supply for about 19.9 thousand customers from the City and the Municipality of Ostrów Wielkopolski. The scope of the project includes the reconstruction of the existing 110/15 kV Ostrów Północ power station. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.07.01.00-00-0012/17
    0 references