To raise energy efficiency of public buildings at 12 Bauska Street, Bauska (Q3056997)

From EU Knowledge Graph
Revision as of 11:54, 27 September 2021 by DG Regio (talk | contribs) (‎Removed claim: co-financing rate (P837): 0.85 percent)
Jump to navigation Jump to search
Project Q3056997 in Latvia
Language Label Description Also known as
English
To raise energy efficiency of public buildings at 12 Bauska Street, Bauska
Project Q3056997 in Latvia

    Statements

    0 references
    0 references
    580,480.71 Euro
    0 references
    682,918.48 Euro
    0 references
    27 October 2020
    0 references
    26 October 2022
    0 references
    Nodrošinājuma valsts aģentūra
    0 references
    0 references

    56°24'21.13"N, 24°11'52.73"E
    0 references
    Projekta mērķis ir veikt valsts ēku Zaļā ielā 12, Bauskā, energoefektivitātes paaugstināšanas un nepieciešamos ēku atjaunošanas pasākumus, tādējādi uzlabojot ēku siltumnoturību un pozitīvi ietekmējot energoresursu efektīvu izmantošanu Latvijā. Nekustamā īpašuma sastāvā ir vairākas funkcionāli saistītas ēkas, tai skaitā: administratīvā ēka (4001 002 0185 001), Zaļā ielā 12A, Bauskā, kopējā platība 2 152,90 m² un administratīvā ēka (4001 002 0203 043), Zaļā ielā 12, Bauskā, kopējā platība 1 378,60 m², (turpmāk–Ēkas). Ēkas lieto Valsts policijas Zemgales reģiona pārvaldes Bauskas iecirknis, kā arī telpas izmanto Tiesu administrācija, LR Prokuratūra un Bauskas zvērinātu advokātu birojs, nodrošinot valsts pārvaldes funkcijas. 2016.gadā Ēku tehniskās apsekošanas rezultātā secināts, ka Ēku norobežojošās konstrukcijas neatbilst Ministru kabineta 30.06.2015. noteikumu Nr.339 “Noteikumi par Latvijas būvnormatīvu LBN 002-15 “Ēku norobežojošo konstrukciju siltumtehnika”” prasībām, konstatētas vairākas problēmas, kuru dēļ ir siltuma enerģijas zudumi, zema energoefektivitāte. Projekta ietvaros plānots veikt šādus galvenos Ēku energoefektivitāti paaugstinošus pasākumus: 1) ēka lit. 001: a) Pārskata 6.sadaļā iekļauti darbi: ārsienu, pagraba un augšējā pārseguma, pamatu, bēniņu grīdas, ārdurvju un lūku nomaiņa; b) Būvprojektā paredzētie darbi: jumta seguma, pieslēguma elementu atjaunošana, būvkonstrukciju stiprināšana, pandusa izbūve, zibensaizsardzības atjaunošana, lietus kanalizācijas, drenāžas darbi; c) Projekta neattiecināmās izmaksas: iekšsienu izbūve, grīdas, durvis. 2) ēka lit. 043: a) Pārskata 6.sadaļā iekļauti darbi: ārsienu un pamatu siltināšana; logu un durvju aiļu siltināšana; esošo lieveņu un metāla kāpņu pagaidu demontāža, atjaunošana; esošajos PVC logu rāmjos izveido svaigā gaisa pieplūdes vārstus; bēniņu grīdas siltināšana; jumta esošā seguma nomaiņa; pārsegumu siltināšana; 2.stāva grīdas pārseguma siltināšana; veco koka, metāla ārdurvju un bēniņu lūkas nomaiņa.; b) Būvprojektā paredzētie darbi: aizsargapmales, pieslēguma elementu atjaunošana, notekcauruļu un notekreņu atjaunošana. Pēc projekta īstenošanas sagaidāmie rezultāti: - siltumenerģijas patēriņa samazinājums kopā divām ēkām – 56,40 %; - primārās enerģijas patēriņa samazinājums kopā divām ēkām – 50,18 %; - CO2 emisijas samazinājums gadā kopā divām ēkām – 46,25 %. Projekta ieviešanas laiks no 2020.gada novembra – 2022.gada 31.oktobrim. Projekta kopējās izmaksas: 713 480,66 EUR, kur attiecināmās izmaksas ir 682 918,48 (85% ERAF finansējums 580 480,71 EUR; 15% valsts budžeta līdzfinansējums 102 437,77 EUR) un neattiecināmās izmaksas 30 562,18 EUR. (Latvian)
    0 references
    The aim of the project is to implement the state building at 12 Bauska, energy efficiency improvement and necessary building renovation measures, thus improving the thermal stability of buildings and having a positive impact on the efficient use of energy resources in Latvia. Real estate consists of several functionally connected buildings, including: Administrative building (4001 002 0185 001), Zaļā iela 12A, Bauska, total area 2152.90 m² and administrative building (4001 002 0203 043), Zaļā street 12, Bauska, total area 1378.60 m², (hereinafter – Buildings). The buildings are used by the Bauska District of Zemgale Region Administration of the State Police, as well as premises are used by the Court Administration, the Prosecutor’s Office of the Republic of Latvia and the Bauska Law Office, providing state administration functions. In 2016, as a result of technical inspection of buildings, it was concluded that building delimiting structures do not comply with the requirements of Cabinet Regulation 30.06.2015 No.339 "Regulations Regarding the requirements of Latvian Building Norms LBN 002-15 "Heat Engineering of Building Buildings", several problems due to loss of heat energy, low energy efficiency were identified. Within the framework of the project it is planned to implement the following main measures to increase the energy efficiency of buildings: 1) Building lit. 001: Section 6 of the report includes works: Replacement of exterior walls, basement and top cover, basements, attic floors, exterior doors and hatchways; The works envisaged in the construction project: Renewal of roofing, connection elements, strengthening of construction structures, construction of pandus, restoration of lightning protection, rain sewers, drainage works; Ineligible costs of the project: Interior wall construction, floors, doors. 2) Building lit. 043: Section 6 of the report includes works: Insulation of exterior walls and foundations; Insulation of windows and doorways; Temporary dismantling and renovation of existing porcelain and metal stairs; Existing PVC window frames shall be fitted with fresh air inlet valves; Floor insulation of attic; Replacement of existing roofing; Insulation of divisions; Insulation of floor covering of the 2nd floor; Replacement of old wooden, metal door and attic hatch; The works envisaged in the construction project: Reconditioning of protective coamings, connection elements, restoration of gutters and scuppers. Results expected after implementation of the project: — a reduction in heating consumption for a total of two buildings: 56,40 %; A reduction in primary energy consumption for a total of two buildings: 50,18 %; — annual CO2 reduction for two buildings – 46.25 %. Project implementation period from November 2020 – October 31, 2022. Total cost of the project: EUR 713480,66, where the eligible costs are 682 918,48 (85 % ERDF contribution EUR 580480,71; 15 % co-financing from the state budget EUR 102437,77) and ineligible costs EUR 30562,18. (English)
    15 July 2021
    0 references
    Zaļā iela 12, Bauska, Bauskas nov., LV-3901
    0 references
    Zaļā iela 12, Bauska, Bauskas nov., LV-3901
    0 references

    Identifiers

    4.2.1.2/19/I/024
    0 references