Construction of the “Drzeńsko” photovoltaic power plant in the municipality of Rzepin (Q2699817)

From EU Knowledge Graph
Revision as of 18:11, 21 September 2021 by DG Regio (talk | contribs) (‎Changed claim: budget (P474): 506,360.35 euro)
Jump to navigation Jump to search
Project Q2699817 in Poland
Language Label Description Also known as
English
Construction of the “Drzeńsko” photovoltaic power plant in the municipality of Rzepin
Project Q2699817 in Poland

    Statements

    0 references
    1,825,559.45 zloty
    0 references
    405,821.87 Euro
    0.2223 Euro
    0 references
    2,277,824.32 zloty
    0 references
    506,360.35 Euro
    0.2223 Euro
    0 references
    80.14 percent
    0 references
    1 October 2018
    0 references
    30 June 2022
    0 references
    BUWITA - ENERGIA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    52°20'39.5"N, 14°50'17.9"E
    0 references
    Przedmiotem projektu jest budowa elektrowni fotowoltaicznej do wytwarzania energii elektrycznej o sumarycznej mocy do 1MWp w gminie Rzepin, woj. lubuskie przez BUWITA - ENERGIA Sp. z o.o. Projekt nie będzie realizowany w systemie zaprojektuj-wybuduj. Tytuł projektu: Budowa elektrowni fotowoltaicznej „Drzeńsko” w gminie Rzepin. Głównym celem projektu jest: Wzrost produkcji energii elektrycznej pochodzącej z odnawialnych źródeł energii na terenie gminy Rzepin. W ramach projektu zostaną osiągnięte poniższe wskaźniki: Liczba wybudowanych jednostek wytwarzania energii elektrycznej z OZE - Szt.1 Liczba przedsiębiorstw otrzymujących wsparcie Przedsiębiorstwa (podmioty)-1 Dodatkowa zdolność wytwarzania energii elektrycznej ze źródeł odnawialnych- MWe 0,99978 Długość nowo wybudowanych sieci elektroenergetycznych dla odnawialnych źródeł energii- 0 Długość zmodernizowanych sieci elektroenergetycznych dla odnawialnych źródeł energii- 0 Liczba przedsiębiorstw wykorzystujących technologie informacyjno-komunikacyjne- 1 Grupy docelowe projektu stanowią: mieszkańcy gminy Rzepin, władze gminy Rzepin oraz instytucje ochrony środowiska. Działania zaplanowane w projekcie przypadają do realizacji, zgodnie z harmonogramem na lata 2018-2020. Nakłady inwestycyjne projektu dotyczą wydatków na przygotowanie projektu, czyli: Przygotowanie dokumentacji technicznej wraz z kosztorysami oraz Opracowanie Studium Wykonalności (IV kw. 2018); wydatków na realizację inwestycji, czyli Przetarg na wykonanie robót budowlanych w zakresie budowy elektrowni fotowoltaicznej (I kw. 2020), Zakup materiałów budowlanych (I kw. 2020) oraz Wykonanie prac budowlanych (II i III kw. 2020) oraz wydatki na wdrażanie projektu, czyli Promocja projektu (II i III kw. 2020) i Doradztwo techniczne związane z obsługą projektu – Inżynier kontraktu (I-IV kw. 2020). Całkowita wartość projektu wynosi 4 101 115,20 zł w tym 2 277 824,32 zł stanowią koszty kwalifikowalne. Wartość dofinansowania wynosi 1 825 559,45 zł[...] (Polish)
    0 references
    The object of the project is the construction of a photovoltaic power plant for the production of electricity with a total capacity up to 1MWp in the municipality of Rzepin, Lubuskie province by BUWITA – ENERGIA Sp. z o.o. The project will not be implemented in the design-construction system. Project title: Construction of the “Drzeńsko” photovoltaic power plant in the municipality of Rzepin. The main objective of the project is: Increase in the production of electricity from renewable energy sources in the municipality of Rzepin. The project will achieve the following indicators: Number of RES electricity generation units built – Part.1 Number of enterprises receiving support Enterprises (entities)-1 Additional renewable electricity generation capacity- MWe 0.99978 Length of newly built electricity networks for renewable energy sources- 0 Length of upgraded electricity grids for renewable energy sources- 0 Number of enterprises using information and communication technologies – 1 Project target groups: residents of the municipality of Rzepin, the authorities of the municipality of Rzepin and environmental protection institutions. The activities planned in the project are implemented, according to the timetable for 2018-2020. The investment expenditure of the project concerns expenditure on the preparation of the project, i.e.: Preparation of technical documentation with cost estimates and development of Feasibility Study (Q4) 2018); expenditure on the implementation of the investment, i.e. Tender for the execution of construction works for the construction of a photovoltaic power plant (Q1 2020), Purchase of building materials (Q1 2020) and Construction work (Q2 and Q3 2020) and expenditure on project implementation, i.e. Project Promotion (Q2 and Q3 2020) and Technical Advice related to project service – Contract Engineer (I-IVQ) 2020). The total value of the project is PLN 4 101 115.20, of which PLN 2 277 824.32 are eligible costs. The value of the co-financing is PLN 1 825 559.45[...] (English)
    7 July 2021
    0 references

    Identifiers

    RPLB.03.01.00-08-0100/19
    0 references