Modernisation of the thermal economy for municipalities: Bytom and Radzionków – 2015-2020 (Q85012)

From EU Knowledge Graph
Revision as of 16:59, 14 October 2020 by DG Regio (talk | contribs) (‎Removed claim: summary (P836): the project involves upgrading the pre-insulated 3.1 km of existing district heating networks, replacing them and converting to pre-insulated approximately 13.4 km of existing external reception facilities.It also includes the liquidation of 10 group thermal nodes and the simultaneous construction of around200 individual nodes., remove_old_english_translation)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Modernisation of the thermal economy for municipalities: Bytom and Radzionków – 2015-2020
Project in Poland financed by DG Regio

    Statements

    0 references
    16,399,894.45 zloty
    0 references
    3,935,974.67 Euro
    13 January 2020
    0 references
    37,464,065.0 zloty
    0 references
    8,991,375.6 Euro
    13 January 2020
    0 references
    43.77 percent
    0 references
    30 September 2016
    0 references
    28 February 2021
    0 references
    PRZEDSIĘBIORSTWO ENERGETYKI CIEPLNEJ BYTOM SP. Z O.O.
    0 references
    0 references
    0 references
    projekt obejmuje modernizację na preizolowaną 3,1 km istniejących sieci ciepłowniczych, wymianę oraz przebudowę na preizolowane ok 13,4 km istniejących zewnętrznych instalacji odbiorczych. Obejmuje również likwidację 10 grupowych węzłów cieplnych i równoczesna budowę ok. 200 indywidualnych węzłów. (Polish)
    0 references

    Identifiers

    POIS.01.07.02-00-0006/16
    0 references