Water and wastewater management in Skaw Municipality — Stage II (Q85495)

From EU Knowledge Graph
Revision as of 16:45, 14 October 2020 by DG Regio (talk | contribs) (‎Created claim: summary (P836): The project includes the construction of a gravity sanitary sewer system with a total length of 22.72 km and a pressing system with a total length of 11.93 km in the area of the Skawina agglomeration, as well as the reconstruction of the SUW in Skawina. As a result of the project, 4 242 new users of the sewage network will be connected and water will be treated in the amount of 3071277 m³/year., translated_summary)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Water and wastewater management in Skaw Municipality — Stage II
Project in Poland financed by DG Regio

    Statements

    Q2524466 (Deleted Item)
    0 references
    0 references
    28,192,092.37 zloty
    0 references
    6,766,102.17 Euro
    13 January 2020
    0 references
    33,167,167.5 zloty
    0 references
    7,960,120.2 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    31 December 2021
    0 references
    ZAKŁAD WODOCIĄGÓW I KANALIZACJI SP. Z O.O.
    0 references
    0 references
    0 references

    49°58'29.3"N, 19°49'35.8"E
    0 references
    Projekt obejmuje budowę kanalizacji sanitarnej grawitacyjnej o łącznej długości 22,72 km oraz tłocznej o łącznej długości 11,93 km na obszarze aglomeracji Skawina, a także przebudowy SUW w Skawinie. W wyniku realizacji projektu zostanie podłączonych 4 242 nowych użytkowników sieci kanalizacyjnej oraz zostanie uzdatniona woda w ilości 3 071 277 m3/rok. (Polish)
    0 references
    The project includes the construction of a gravity sanitary sewer system with a total length of 22.72 km and a pressing system with a total length of 11.93 km in the area of the Skawina agglomeration, as well as the reconstruction of the SUW in Skawina. As a result of the project, 4 242 new users of the sewage network will be connected and water will be treated in the amount of 3071277 m³/year. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.02.03.00-00-0302/17
    0 references