Expansion and reconstruction with retrofitting of the H. Klimontowicz Specialist Hospital in Gorlice with the use of energy-efficient technological solutions (Q86340)

From EU Knowledge Graph
Revision as of 09:45, 7 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
Jump to navigation Jump to search
Project Q86340 in Poland
Language Label Description Also known as
English
Expansion and reconstruction with retrofitting of the H. Klimontowicz Specialist Hospital in Gorlice with the use of energy-efficient technological solutions
Project Q86340 in Poland

    Statements

    0 references
    3,281,291.43 zloty
    0 references
    787,509.94 Euro
    13 January 2020
    0 references
    3,860,342.87 zloty
    0 references
    926,482.29 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    28 February 2018
    0 references
    SZPITAL SPECJALISTYCZNY IM. H. KLIMONTOWICZA W GORLICACH
    0 references
    0 references

    49°39'58.7"N, 21°9'48.6"E
    0 references
    Zakres przedmiotowy projektu: 1) Przebudowa istniejącego SOR, 2) Dobudowa łącznika pomiędzy ogólnodostępną strefą SOR a ciągiem komunikacji ogólnej segmentu B szpitala, 3) Dobudowa zewnętrznego pomostu wejścia do pomieszczenia dekontaminacji, 4) Wymiana central wentylacyjnych, 5) Zastosowanie energooszczędnych lamp oświetlenia, 6) Ustawienie dwóch central klimatyzacyjnych, 7) Ustawienie agregatu wody lodowej, 8) Zakup i montaż monitoringu, 9) Zakup sprzętu. (Polish)
    0 references
    The scope of the project: 1) Reconstruction of the existing SOR, 2) addition of a connector between the public SOR zone and the communication network of the general section B of the hospital, 3) the addition of an external entrance bridge to the decontamination room, 4) Replacement of ventilation units, 5) Use of energy-saving lighting lamps, 6) Setting two air-conditioning centers, 7) Setting the ice water unit, 8) Purchase and monitoring installation, 9) Purchase of equipment. (English)
    15 October 2020
    0 references
    Portée matérielle du projet: 1) la reconstruction d’un SOR existant, 2) l’ajout d’un connecteur entre la zone publique SOR et la séquence générale de communication du segment B de l’hôpital, 3) la construction d’une plate-forme d’entrée extérieure à la salle de décontamination, 4) le remplacement des unités de ventilation, 5) l’utilisation de lampes d’éclairage à économie d’énergie, 6) la mise en place de deux unités de climatisation, 7) la mise en place du refroidisseur, 8) l’achat et l’installation de surveillance, 9) l’achat d’équipement. (French)
    30 November 2021
    0 references
    Materieller Geltungsbereich des Projekts: 1) Umbau einer bestehenden SOR, 2) Hinzufügen eines Anschlusses zwischen der öffentlichen SOR-Zone und der allgemeinen Kommunikationssequenz des Segments B des Krankenhauses, 3) Bau einer externen Eingangsplattform zum Dekontaminationsraum, 4) Austausch von Lüftungsgeräten, 5) Verwendung von energiesparenden Beleuchtungslampen, 6) Einstellung von zwei Klimaanlagen, 7) Einstellung des Kühlers, 8) Kauf und Installation von Überwachungseinrichtungen, 9) Anschaffung von Geräten. (German)
    7 December 2021
    0 references

    Identifiers

    POIS.09.01.00-00-0075/16
    0 references