CONSTRUCTION OF A PHOTOVOLTAIC INSTALLATION AT THE PRODUCTION PLANT IN M. SOKOŁÓWKA WITH A CAPACITY OF UP TO 200 KWP (Q2702261)

From EU Knowledge Graph
Revision as of 19:57, 21 September 2021 by DG Regio (talk | contribs) (‎Changed claim: EU contribution (P835): 142,961.13 euro)
Jump to navigation Jump to search
Project Q2702261 in Poland
Language Label Description Also known as
English
CONSTRUCTION OF A PHOTOVOLTAIC INSTALLATION AT THE PRODUCTION PLANT IN M. SOKOŁÓWKA WITH A CAPACITY OF UP TO 200 KWP
Project Q2702261 in Poland

    Statements

    0 references
    643,100.0 zloty
    0 references
    142,961.13 Euro
    0.2223 Euro
    0 references
    1,090,000.0 zloty
    0 references
    242,307.0 Euro
    0.2223 Euro
    0 references
    59.0 percent
    0 references
    1 January 2021
    0 references
    30 June 2021
    0 references
    P.P.H.U. RASKO BIS RAFAŁ SKORZYCKI
    0 references
    0 references

    51°42'40.7"N, 20°2'7.1"E
    0 references
    Zakres rzeczowy obejmuje budowę dachowej instalacji oze (fotowoltaiczna szt. 1) z okablowaniem, monitoringiem i innymi elementami infrastruktury towarzyszącej oraz promocję projektu. Moce zainstalowane w projekcie (1 x 190,02 kW), ilość wytworzonej energii w projekcie (1 x 190,00 MWh/rok). Wartość netto zakresu rzeczowego – 1101500,00 zł (1354845,00 zł brutto), w tym wyd. kwalifikowane – 1090000,00 zł, dotacja 643100,00 zł. Cele projektu są zbieżne z celami strategicznymi rozwoju woj. oraz celami gospodarki niskoemisyjnej, w tym przede wszystkim zwiększona produkcja energii ze źródeł odnawialnych i ograniczenie emisji CO2 i innych gazów, podwyższenie poziomu ochrony środowiska. Instalacja będzie podłączona do istniejącej sieci operatora – projekt zakłada dystrybucje energii do sieci, co zrealizuje w ramach umowy z operatorem. Celem działań w projekcie jest budowa instalacji i uruchomienie produkcji energii ze źródeł odnawialnych i ograniczenie emisji CO2, wzrost wykorzystania OZE w produkcji energii, przejście na gospodarkę niskoemisyjną i zmniejszenie udziału energetyki konwencjonalnej. Cele projektu odzwierciedlają zdefiniowane potrzeby interesariuszy i zostały określone mierzalnymi wskaźnikami zgodnie z celami RPO WŁ 2014-2020 (wskaźniki produktu i rezultatu). Realizacja projektu obejmuje fazę budowy oraz eksploatacji (w okresie trwałości 3 lat od daty płatności końcowej). Projekt zapewnia ograniczenie emisji jako emisja uniknięta (nowa instalacja) służąc realizacji celów strategicznych poprzez produkcję energii ze źródeł odnawialnych (zgodność z SZOOP). W projekcie zachowano zasady koncepcji projektowania uniwersalnego (dbałość aby efekty projektu w jak największym stopniu były użyteczne dla wszystkich interesariuszy projektu). Grupę docelową projektu stanowi – wnioskodawca (użytkownik) i mieszkańcy regionu. Status przedsiębiorstwa wnioskodawcy (MŚP). Wnioskodawca uprawniony do otrzymania wsparcia. Projekt zgodny z zasadami pomocy publicznej. (Polish)
    0 references
    The material scope includes the construction of a roof oze installation (photovoltaic pcs. 1) with wiring, monitoring and other elements of accompanying infrastructure and promotion of the project. Installed capacity in the project (1 x 190.02 kW), amount of energy generated in the project (1 x 190.00 MWh/year). Net value of the material range – PLN 1101500.00 (PLN 1354845.00 gross), including the eligible value – PLN 1090000.00, subsidy PLN 643100.00. The objectives of the project are in line with the strategic objectives of the development of the province and the objectives of the low-carbon economy, including, above all, increased production of energy from renewable sources and the reduction of CO2 and other emissions of gases, increasing the level of environmental protection. The installation will be connected to the existing network of the operator – the project assumes distribution of energy to the grid, which it will perform as part of an agreement with the operator. The aim of the project’s activities is to build installations and launch renewable energy production and reduce CO2 emissions, increase the use of RES in energy production, move towards a low-carbon economy and reduce the share of conventional energy. The objectives of the project reflect the defined needs of stakeholders and have been defined by measurable indicators in line with the objectives of the 2014-2020 ROP (output and result indicators). The implementation of the project involves the construction and operation phase (during a lifetime of 3 years from the date of final payment). The project provides emission reductions as avoided emissions (new installation) in order to achieve strategic objectives through the production of energy from renewable sources (compliant with SZOOP). The project maintains the principles of the universal design concept (to ensure that the project results are as useful as possible for all project stakeholders). The target group of the project is the applicant (user) and residents of the region. The status of the applicant company (SMEs). The applicant entitled to receive support. Project compatible with state aid rules. (English)
    7 July 2021
    0 references

    Identifiers

    RPLD.04.01.02-10-0091/18
    0 references