Revision as of 13:21, 7 July 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): MATERIAL SCOPE: 5940 photovoltaic panels with a nominal power of 330 Wp, with a total capacity of 1.96 MW, will be installed on the supporting structures located on the ground. The height of ground structures will not exceed 4 m. Construction of a shelter for dehydrated sediment with a photovoltaic installation with a total power of 222,75 kW, together with the necessary electricity infrastructure in the existing Lewy Brzeg Wastewater Treatment...)
Jump to navigation Jump to search
Project Q2692708 in Poland
Language Label Description Also known as
English
No label defined
Project Q2692708 in Poland

    Statements

    0 references
    8,307,919.24 zloty
    0 references
    1,846,850.45 Euro
    0.2223 Euro
    0 references
    9,774,022.64 zloty
    0 references
    2,172,765.23 Euro
    0.2223 Euro
    0 references
    85.0 percent
    0 references
    1 October 2018
    0 references
    31 May 2022
    0 references
    PRZEDSIĘBIORSTWO WODOCIĄGÓW I KANALIZACJI SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    52°10'53.0"N, 18°12'55.4"E
    0 references
    ZAKRES RZECZOWY : Na konstrukcjach wsporczych zlokalizowanych na gruncie zamontowane zostanie 5940 szt. paneli fotowoltaicznych o mocy nominalnej 330 Wp, o łącznej mocy 1,96 MW. Wysokość konstrukcji naziemnych nie przekroczy 4 m. Budowy wiaty na osad odwodniony z instalacją fotowoltaiczną o łącznej mocy 222,75 kW wraz z niezbędną infrastrukturą elektroenergetyczną na terenie istniejącej Oczyszczalni Ścieków Lewy Brzeg. Na dachu wiaty na osad odwodniony zamontowane zostanie 675 szt. paneli fotowoltaicznych o mocy nominalnej 330 Wp. Montaż towarzyszącej infrastruktury elektroenergetycznej tj. instalacji niskiego napięcia, dwóch kontenerów technologicznych z transformatorami, konstrukcji wsporczych dla paneli PV, instalacji teletechnicznych, AKPiA i monitoringu oraz przyłączy kablowych SN. (Polish)
    0 references
    MATERIAL SCOPE: 5940 photovoltaic panels with a nominal power of 330 Wp, with a total capacity of 1.96 MW, will be installed on the supporting structures located on the ground. The height of ground structures will not exceed 4 m. Construction of a shelter for dehydrated sediment with a photovoltaic installation with a total power of 222,75 kW, together with the necessary electricity infrastructure in the existing Lewy Brzeg Wastewater Treatment Plant. 675 photovoltaic panels with a nominal power of 330 Wp will be installed on the roof of the drained sediment roof. Installation of associated electricity infrastructure, i.e. low-voltage installation, two process containers with transformers, supporting structures for PV panels, teletechnical installations, ACPiA and monitoring, and cable connections of the SN. (English)
    7 July 2021
    0 references

    Identifiers

    POIS.01.01.01-00-0006/18