No label defined (Q112992)

From EU Knowledge Graph
Revision as of 11:54, 20 October 2020 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in 1 language: remove_english_label)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
No label defined
Project in Poland financed by DG Regio

    Statements

    0 references
    28,436,664.15 zloty
    0 references
    6,824,799.40 Euro
    13 January 2020
    0 references
    33,454,899.0 zloty
    0 references
    8,029,175.76 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    20 December 2017
    0 references
    31 December 2019
    0 references
    WOJEWÓDZTWO MAŁOPOLSKIE
    0 references
    Przedmiotem projektu jest zadanie polegające na opracowaniu dokumentacji projektowej wraz z uzyskaniem zgody właściwego organu na prowadzenie robót w oparciu o obowiązujące przepisy oraz wykonanie robót budowlanych.Roboty budowlane objęte projektem będą realizowane w oparciu o dwa zadaniaetapy:ZadanieEtap I obejmuje: rozbudowę DW 948, jako drogi klasy G, jednojezdniowej, 2pasowej i przebudowębudowę chodników oraz ciągów pieszo rowerowych, przebudowę skrzyżowań z drogami bocznymi na ronda, wzmocnienie skarp nasypów drogowych, przebudowę przepustów oraz oczyszczenie odmulenie pozostałych przepustów, budowę oświetlenia ulicznego oraz przebudowę obiektów inżynierskich na ciekach krzyżujących się z DW 948. Łączna długość odcinków, w tym przebudowa skrzyżowań, objętych rozbudową wynosi około 5,8 km. rozbudowę DW 949, jako drogi klasy G, jednojezdniowej, 2pasowej i poszerzenie jezdni, wzmocnienie skarp nasypów drogowych, przebudowę przepustów przebudowę drogi bocznej oraz przebudowę obiektów inżynierskich na ciekach krzyżujących się z DW 949, budowęrozbudowę odwodnienia drogi. Łączna długość odcinka objętego rozbudową wynosi około 1,3 km. ZadanieEtap II obejmuje: budowę nowego obiektu mostowego w ciągu DW 949 wraz z dojazdami, budowęprzebudowę przepustów oraz zjazdów, przebudowę ok. 0,6 km drogi DW 949 o parametrach określonych w PFU oraz koncepcji i spełniającymi wymagania parametrów drogi klasy G, o konstrukcji nawierzchni odpowiadającej 20letniemu okresowi eksploatacji, prawidłowego odwodnienia oraz rozwiązania obsługi komunikacyjnej przyległego terenu w zakresie ruchu kołowego i pieszego. Ponadto w zakresie inwestycji planowana jest przebudowa skrzyżowania DW 949 z DW 948 w m. Łęki wraz z odcinkiem drogi DW 949 obejmująca budowę pasa do prawoskrętu na DW 949 i pasa włączenia do DW 948.Z uwagi na ograniczoną ilość znaków w polu C.2.2. dodatkowe informacje zawarto w pkt Q. (Polish)
    0 references
    The object of the project is the task of drawing up project documentation together with obtaining the consent of the competent authority to carry out works on the basis of applicable regulations and execution of construction works.The construction works covered by the project will be carried out on the basis of two tasks of the stage:TaskStage I includes: the extension of DW 948, as G-class roads, one-way, 2pass roads and reconstruction of walkways and bicycle tracks, reconstruction of crossroads with side roads into a roundabout, reinforcement of road embankments, reconstruction of culverts and cleansing of remaining culverts, construction of street lighting and reconstruction of engineering facilities on rivers crossing with DW 948. The total length of the sections, including the reconstruction of intersections covered by the extension, is about 5.8 km. expansion of DW 949, as G-class road, one-way, 2pass road extension, reinforcement of road embankments, reconstruction of culverts reconstruction of the side road and reconstruction of engineering facilities on watercourses crossing with DW 949, construction of the drainage of the road. The total length of the section covered by the extension is about 1.3 km. TaskStage II shall include: construction of a new bridge facility in the course of DW 949 with access, construction of culverts and exits, reconstruction of approx. 0,6 km of road DW 949 with the parameters specified in the PFU and the concept and meeting the requirements of the G road, with a surface structure corresponding to 20 years of service life, proper drainage and communication solutions for the adjacent road and pedestrian traffic. In addition, the investment is planned to reconstruct the junction of DW 949 with DW 948 in m. Łęki, together with the section of the DW 949 road, including the construction of the right-turn belt on DW 949 and the incorporation belt into DW 948.Due to the limited number of characters in field C.2.2, additional information is provided in point Q. (English)
    20 October 2020
    0 references

    Identifiers

    RPMP.07.01.01-12-1123/17
    0 references