Construction of a biogas CHP plant up to 1 MW in Zawady_2 (Q109082)

From EU Knowledge Graph
Revision as of 09:19, 20 October 2020 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in 1 language: translated_label)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a biogas CHP plant up to 1 MW in Zawady_2
Project in Poland financed by DG Regio

    Statements

    0 references
    7,538,590.12 zloty
    0 references
    1,809,261.63 Euro
    13 January 2020
    0 references
    12,564,316.86 zloty
    0 references
    3,015,436.05 Euro
    13 January 2020
    0 references
    60.0 percent
    0 references
    1 July 2019
    0 references
    30 June 2020
    0 references
    PGB ENERGETYKA 9 SP. Z O.O.
    0 references
    0 references

    52°22'30.0"N, 21°58'1.6"E
    0 references
    Projekt polega na budowie biogazowni rolniczej o mocy elektrycznej 0,999 MW i cieplnej 1,058 MW w miejscowości Zawady, gm. Liw, powiat węgrowski, woj. mazowiecki. Zakładana roczna produkcja energii elektrycznej wynosi 7992 MWh, cieplnej 8464 MWh. Proces jest wysokosprawną kogeneracją. Prąd będzie sprzedawany do sieci elektroenergetycznej, a ciepło w większości wykorzystane na potrzeby własne biogazowni. Zakres rzeczowy inwestycji obejmie 2 zadania, czyli budowę kompletnej biogazowi pod klucz oraz działania informacyjne. Obiekt składa się z następujących elementów: Węzeł ciepła wraz z instalacjami, Stacja trafo wraz z przyłączem, Stacja uzdatniania biogazu, Układ ko generacyjny, Stacja pomp, Sterownia PLC, Zbiorniki fermentacyjne z systemem mieszania, Zbiorniki na odcieki, Silosy, Zbiorniki na masę pofermentacyjną z systemem mieszania, Dozowniki, Pochodnia biogazu, Separator, Oprogramowanie SCADA. W ramach zadnia zostaną wykonane niezbędne roboty budowlane. Termin: 2019-07-01 2020-06-30. Sposób wdrażania: Nadrzędnym założeniem organizacyjnym w projekcie jest oparcie jego realizacji na zleceniu wykonawstwa kompletnej biogazowi pod klucz wyspecjalizowanemu wykonawcy gwarantującemu najwyższą jakość, efektywność cenową i dostarczenie kompleksowych rozwiązań spełniających oczekiwania Spółki i założone parametry. Wykonawca zostanie wybrany w postępowaniu konkurencyjnego wyboru. Grupa docelowa projektu to, lokalna społeczność, w szczególności rolnicy i przetwórcy, a szerzej mieszkańcy regionu i Polski korzystający z energii elektrycznej, a także władze Polski odpowiedzialne za osiągnięcie wskaźników udziału OZE w produkcji energii ogółem. (Polish)
    0 references
    The project consists of the construction of an agricultural biogas plant with an electrical capacity of 0.999 MW and 1.058 MW in Zawady, Liw, Węgrowski County, Mazowiecki Voivodeship. The estimated annual production of electricity is 7992 MWh, the heat output is 8464 MWh. The process is a high-performance cogeneration. Electricity will be sold to the power grid, and heat will be used mostly for the own needs of the biogas plant. The material scope of the investment will cover 2 tasks, i.e. the construction of complete turnkey biogas and information activities. The object consists of the following elements: Heat node with installations, Trafo station with connection, Biogas treatment station, Cogeneration system, Pump station, PLC control room, fermentation tanks with mixing system, Tanks for leaching, Silos, reservoirs for digestate with mixing system, Dispensers, Biogas torch, Separator, SCADA software. As part of the day, the necessary construction works will be done. Deadline for reply: 2019-07-01 2020-06-30. Method of implementation: The overarching organizational assumption in the project is to base its implementation on the execution order of a complete biogas turn key to a specialised contractor guaranteeing the highest quality, price efficiency and providing comprehensive solutions meeting the Company’s expectations and assumed parameters. The contractor will be selected in the competitive selection procedure. The target group of the project is the local community, in particular farmers and processors, and more broadly the inhabitants of the region and Poland using electricity, as well as the Polish authorities responsible for achieving the share of RES in total energy production. (English)
    20 October 2020
    0 references

    Identifiers

    RPMA.04.02.00-14-B474/18
    0 references