Implementation of innovative cutting technology 3D with additional IT system for the metal sector (Q123098)

From EU Knowledge Graph
Revision as of 05:58, 17 July 2020 by DG Regio (talk | contribs) (‎Changed an Item)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Implementation of innovative cutting technology 3D with additional IT system for the metal sector
Project in Poland financed by DG Regio

    Statements

    0 references
    763,178.85 zloty
    0 references
    183,162.924 Euro
    13 January 2020
    0 references
    1,695,953.0 zloty
    0 references
    407,028.72 Euro
    13 January 2020
    0 references
    45.0 percent
    0 references
    1 October 2018
    0 references
    31 December 2019
    0 references
    FIRMA MIK-STAL SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ SPÓŁKA KOMANDYTOWA
    0 references
    0 references

    50°46'55.2"N, 18°58'6.2"E
    0 references
    Przedmiotem projektu jest inwestycja początkowa o charakterze zasadniczej zmiany procesu produkcji, polegająca na wdrożeniu do procesu produkcji innowacyjnej wycinarki plazmowej oraz systemu IT do zarządzania procesem produkcji i świadczenia usług. Projekt umożliwi wdrożenie innowacji procesowej, produktowej i nie technologicznej nie stosowanej w skali świata dłużej niż 3 lata. Projekt będzie realizowany w okresie 2018-10-2019-12 i obejmie zakup i wdrożenie do procesu produkcji wycinarki plazmowej. Wartość projektu netto 1 695 953,00 zł, dotacja 763 178,85zł. Wkład własny: 1 341 293,34zł. Stworzone zostaną 2 etaty (2 epc w 2019r.). (Polish)
    0 references
    The project consists of an initial investment of a fundamental change in the production process, consisting of the implementation in the production process of an innovative plasma extract and an IT system for the management of the process of production and provision of services. The project will enable the process of process, product and non-technological innovation not used at world level for more than 3 years. The project will be implemented in the 2018-10-2019-12 period and will cover the purchase and the implementation of the plasma cutting process. Net project value PLN 1 695 953,00, subsidy of PLN 763 178,85. Own resources: PLN 1 341 293,34. 2 posts will be created (2 FTE in 2019). (English)
    0 references

    Identifiers

    RPSL.03.02.00-24-011A/18
    0 references