Construction of a mechanical and biological sewage treatment plant and a sanitary sewage network with associated infrastructure and technical facilities for the agglomeration of Mineral Oil (Q118892)

From EU Knowledge Graph
Revision as of 21:01, 22 June 2020 by DG Regio (talk | contribs) (‎Removed claims)
Jump to navigation Jump to search
Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a mechanical and biological sewage treatment plant and a sanitary sewage network with associated infrastructure and technical facilities for the agglomeration of Mineral Oil
Project in Poland financed by DG Regio

    Statements

    0 references
    13,780,253.35 zloty
    0 references
    3,307,260.804 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 August 2018
    0 references
    30 April 2020
    0 references
    GMINA OLSZANICA
    0 references
    Celem realizacji przedsięwzięcia jest uporządkowanie gospodarki ściekowej na terenie Gminy Olszanica, zwłaszcza wyeliminowanie przedostawania się do gruntu ścieków gromadzonych w zbiornikach bezodpływowych. Projekt obejmuje zadania bezpośrednio związane z zagospodarowaniem ścieków tj. kanalizacji, usuwania i oczyszczania ścieków komunalnych. Celem bezpośrednim projektu jest wzrost liczby ludności korzystającej z systemu oczyszczania ścieków w Aglomeracji Uherce Mineralne. Do celów ogólnych projektu należą: poprawa jakości życia mieszkańców Aglomeracji Uherce Mineralne, poprawa atrakcyjności obszaru dla inwestycji gospodarczych, spadek zachorowalności mieszkańców na choroby związane z zanieczyszczeniem środowiska, zmniejszone zanieczyszczenie środowiska naturalnego.Przedmiotem projektu jest budowa sieci kanalizacji sanitarnej i oczyszczalni ścieków na terenie Aglomeracji Uherce Mineralne. W ramach projektu planowana jest budowa biologiczno-mechanicznej oczyszczalni ścieków w Uhercach Mineralnych – Etap I o przepustowości 637 m3/d, oraz budowa sieci kanalizacyjnej sanitarnej (grawitacyjnej (PCV o średnicach: 315, 250, 200 i 160mm, PE o średnicach: 250 i 160mm) i tłocznej (PE o średnicach: 140 i 90mm) o łącznej długości 19,46 km wraz z przyłączami oraz infrastrukturą towarzyszącą i obiektami technicznymi. W ramach zadania powstaną: budynki technologiczne, budynki techniczne, budynek socjalno-administracyjny, pełna infrastruktura techniczna sieci i instalacje sanitarne, elektryczne i AKPiA, gazowe, sieci technologiczne, przyłącze elektryczne, przyłącze wodociągowe od studni kopanej stanowiącej ujęcie wody, doprowadzenie ścieków surowych do oczyszczalni, odprowadzenie ścieków oczyszczonych oraz wód deszczowych z wylotem do odbiornika, którym będzie potok Kiniańskiego, droga dojazdowa do oczyszczalni, wewnętrzne drogi, place manewrowe i postojowe, oraz ogrodzenie terenu oczyszczalni. (Polish)
    0 references
    The purpose of the project is the cleaning up of the wastewater management in the municipality of Olszica, in particular the removal of waste water collected in septic tanks. The project includes tasks that are directly related to the management of waste water, i.e. the urban waste water collection, the disposal and the treatment of the urban waste water. The direct objective of the project is an increase in the population using the wastewater treatment system in the Mineral Mineral Water Treatment Facility. The general objectives of the project are to: improving the quality of life of the residents of the Mineral Oil Area, improving the attractiveness of the area for economic investment, falling population incidence of diseases related to environmental pollution, reduced environmental pollution of the natural environment. Within the framework of the project, a biological/mechanical sewage treatment plant is planned to be built in the Mineral Oil, Stage I, with a capacity of 637 m³/d, and the construction of a gravitational sewage system (PCV with diameters: 315, 250, 200 and 160 mm, EP in diameter: 250 and 160 mm) and pressure piston (PE of diameter: 140 and 90 mm) of a total length of 19.46 km with connections and associated infrastructure and technical facilities. The task will be to: the technological buildings, technical buildings, the social and administrative building, the full technical infrastructure of the network and sanitary, electrical and AKPiA networks, gas networks, technology networks, electrical connection, water connection, water connection from the digging of the water, the discharge of waste water to the treatment plant, the discharge of treated wastewater and rainwater with the outlet to the receiver, which will be the Kiniai stream, the access road to the treatment plant, internal roads, shunting and parking areas, and the fence of the sewage treatment plant. (English)
    0 references

    Identifiers

    RPPK.04.03.01-18-0007/17
    0 references