Thermomodernisation of Public Basic Schools in Dołuje and Rzędzina in the Municipality of Good (Q137640)

From EU Knowledge Graph
Revision as of 16:02, 26 October 2022 by DG Regio (talk | contribs) (‎Changed an Item: Import item from Poland)
Jump to navigation Jump to search
Project Q137640 in Poland
Language Label Description Also known as
English
Thermomodernisation of Public Basic Schools in Dołuje and Rzędzina in the Municipality of Good
Project Q137640 in Poland

    Statements

    0 references
    578,416.98 zloty
    0 references
    128,582.09 Euro
    13 January 2020
    0 references
    680,490.59 zloty
    0 references
    151,273.06 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    16 November 2018
    0 references
    31 December 2020
    0 references
    GMINA DOBRA
    0 references
    0 references

    53°31'55.63"N, 14°26'10.28"E
    0 references
    Przedmiotem opracowania jest dokonanie prac termomodernizacyjnych budynków szkół publicznych w Dołujach i Rzędzinach w Gminie Dobra.Zaplanowany zakres prac będzie jednocześnie etapami rzeczowymi inwestycji,a mianowicie:(1)dokumentacja projektowa:studium,audyty,dokumentacja,opinie ornitologiczne i chiropterologiczne;(2)Roboty termomodernizacyjne,w tym:(a)Termomodernizacja SP w Dołujach:1.drzwi nowe (Drzwi do wymiany):zamurowania stolarki:9,44 m2;2.docieplenie-stropodach (GRUPA stropodach),Powierzchnia docieplenia:680m2;3.docieplenie-ściana zewnętrzna (GRUPA ściana zewnętrzna +fundamentowa; Powierzchnia docieplenia:591m2;;(b)Termomodernizacja SP w Rzędzinach:1. Nowa stolarka drzwiowa (GRUPA stolarka 3,400);2. docieplenie - ściana zewnętrzna (GRUPA ściana zewnętrzna),Powierzchnia docieplenia: 306,00m2.W ramach prac wykonane będą także liczniki ciepła z montażem (energii cieplnej) oraz niezbędne (wynikające z Warunków Technicznych) koszty dodatkowe przy dociepleniu elewacji (zadaszenia oraz oświetlenie wejść)dla budynków szkół(3)Inspektor nadzoru;(4)Promocja projektu oraz (5)Koszty pośrednie.Dzięki przeprowadzonym pracom modernizacyjnym oszczędność zapotrzebowania ciepłą wyniesie powyżej 25%.Efektem realizacji będzie bowiem wdrożenie działań związanych z głęboką, kompleksową modernizacją energetyczną obiektów oświatowych, które służą dzisiaj zarówno dzieciom jak i nauczycielom pracującym w obiekcie jako obiekt oświatowo-kulturalny.Szczegóły prac opisano w SW 2.1.1.1 oraz 3.1.3.1 (Polish)
    0 references
    The planned scope of works will be both material stages of the investment, namely:(1)project documentation:study,audyty,documentation,ornithological opinions and chiropterological opinions;(2)thermomodernisationworks,including:(a)Modernisation of SP in Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Permomodernisation of the SP in Doples:44. Warming area:591m2;;(b)Thermomodernisation of SP in Rzędzin:1. New door carpentry (GRUPA carpentry 3.400);2. warming – outer wall (GRUPA outer wall), Warm area: 306.00 m².The works will also include heat meters with installation (heat energy) and necessary (resulting from the Technical Conditions) additional costs for insulation of facades (closing and lighting of entrances) for school buildings(3)Supervisory inspector;(4)Promotion of the project and (5)Intermediate costs. (English)
    21 October 2020
    0 references
    L’objet de l’étude est de réaliser des travaux de thermomodernisation des bâtiments des écoles publiques de Dołuje et Rzędziny dans la commune de Dobra.Le champ d’action prévu sera en même temps les étapes matérielles de l’investissement, à savoir: (1) la documentation projektowa:studium,audyty,dokumentacja,opinie ornithologique et chiropterologique;(2)Les travaux de modernisation thermique, y compris:a)Termomodernisation SP en Dołujach:1.drzwi nouveau (porte de remplacement):Camping stolarki:9,44 m²;2.stropod heat (GRUPA stropodach),Outdoor Surface (GRUPA extérieur mur + Fondation; Surface docieplenia:591m2; b)Termomodernisation SP dans les cotes:1. Nouvelle menuiserie de porte (GRUPA menuiserie 3,400);2. isolation — mur extérieur (mur extérieur GRUPA), Surface chauffante: 306,00 m².Les travaux comprendront également des compteurs de chaleur avec montage (énergie thermique) et nécessaires (résultant des conditions techniques) sur les coûts supplémentaires lors du réchauffement de la façade (entrées de couverture et d’éclairage) pour les bâtiments scolaires(3)Superviseur;(4)Promotion du projet et (5) coûts indirects. Grâce aux travaux de modernisation, les économies de chaleur seront supérieures à 25 %. La mise en œuvre se traduira par la mise en œuvre d’activités liées à la modernisation énergétique profonde et complète des installations éducatives, qui servent aujourd’hui à la fois les enfants et les enseignants travaillant dans l’établissement en tant qu’objet éducatif et culturel. Les détails des travaux sont décrits dans SW 2.1.1.1 et 3.1.3.1. (French)
    2 December 2021
    0 references
    Gegenstand der Studie ist die Durchführung von Thermomodernisierungsarbeiten an öffentlichen Schulgebäuden in Dołuje und Rzędziny in der Kommune Dobra.Der geplante Arbeitsumfang wird gleichzeitig materielle Phasen der Investition sein, nämlich:(1) Dokumentation projektowa:studium,audyty,dokumentacja,opinie ornithologisch und chiropterologisch;(2)Thermalmodernisierungsarbeiten, darunter:(a)Termomodernisierung SP in Dołujach:1.drzwi neu (Replacement Door):Camping ◆ m²;2.stropodenerwärmung (GRUPA stropodach),Außenfläche (GRUPA Außenwand + Stiftung; Surface docieplenia:591m2; b)Termomodernisierung SP in den Ratings:1. Neue Türtischlerei (GRUPA Tischlerie 3.400);2. Isolierung – Außenwand (GRUPA Außenwand), Wärmefläche: 306,00 m².Die Arbeiten umfassen auch Wärmezähler mit Montage (Wärmeenergie) und notwendigen (aus technischen Bedingungen resultierenden) zusätzlichen Kosten bei der Erwärmung der Fassade (Abdeckungs- und Lichteingänge) für Schulgebäude(3)Betreuer;(4)Förderung des Projekts und (5)Indirekte Kosten. Dank der Modernisierungsarbeiten werden die Wärmebedarfseinsparungen über 25 % betragen. (German)
    13 December 2021
    0 references
    Het onderwerp van de studie is het uitvoeren van thermomoderniseringswerken van openbare schoolgebouwen in Dołuje en Rzędziny in de gemeente Dobra.De geplande omvang van de werkzaamheden zal tegelijkertijd materiële fasen van de investering zijn, namelijk:(1) documentatie projektowa:studium,audyty,dokumentacja,opinie ornithologische en chiropterologische;(2)Thermische moderniseringswerken, waaronder:a)Termomodernisering SP in Dołujach:1.drzwi nieuw (vervangingsdeur):Camping ※ m²;2.stropod warming (GRUPA stropodach),Outdoor Surface (GRUPA outdoor wall + Foundation); Oppervlakte docieplenia:591m2;b) Termomodernisering SP in de Ratings:1. Nieuw deurschrijnwerk (GRUPA schrijnwerk 3.400);2. isolatie — buitenmuur (GRUPA buitenmuur), Opwarmoppervlak: 306,00 m².Het werk omvat ook warmtemeters met montage (warmteenergie) en noodzakelijke (als gevolg van technische omstandigheden) extra kosten bij het opwarmen van de gevel (bekleding en verlichtingsingangen)voor schoolgebouwen(3)Toezichthouder;(4)Bevordering van het project en (5)Indirecte kosten. Dankzij de moderniseringswerken zal de warmtevraagbesparing meer dan 25 % bedragen. De uitvoering zal resulteren in de uitvoering van activiteiten in verband met een diepe, uitgebreide energie-modernisering van onderwijsvoorzieningen, die vandaag de dag zowel kinderen als docenten die in de faciliteit werken als educatief en cultureel object dienen. De details van het werk zijn beschreven in SW 2.1.1.1 en 3.1.3.1. (Dutch)
    17 December 2021
    0 references
    Oggetto dello studio è quello di realizzare opere di termomodernizzazione degli edifici scolastici pubblici a Dołuje e Rzędziny nella comune di Dobra.L'ambito di lavoro previsto sarà allo stesso tempo fasi materiali dell'investimento, vale a dire:(1) documentazione projektowa:studium,audyty,dokumentacja,opinie ornitologico e chiropterologico;(2)Lavori termici di modernizzazione, tra cui:a)Termomodernizzazione SP in Dołujach:1.drzwi nuovo (Porta di sostituzione):Camping stolarki:9,44 m²;2.Riscaldamento astropodi (GRUPA stropodach), superficie esterna (GRUPA parete esterna + Fondazione; Superficie docieplenia:591m2;b)Termomodernizzazione SP nelle valutazioni:1. Nuova falegnameria per porte (GRUPA falegnameria 3.400); 2. isolamento — parete esterna (parete esterna GRUPA), superficie di riscaldamento: 306,00 m².I lavori comprenderanno anche contatori di calore con montaggio (energia termica) e necessari (derivanti dalle Condizioni Tecniche) costi aggiuntivi per il riscaldamento della facciata (copertura e illuminazione degli ingressi) per gli edifici scolastici(3)Supervisore;(4)Promozione del progetto e (5) Costi indiretti. Grazie ai lavori di ammodernamento, il risparmio di calore sarà superiore al 25 %. L'attuazione si tradurrà nella realizzazione di attività legate alla profonda e completa modernizzazione energetica delle strutture didattiche, che oggi servono sia i bambini che gli insegnanti che lavorano nella struttura come oggetto educativo e culturale. I dettagli dei lavori sono descritti in SW 2.1.1.1 e 3.1.3.1. (Italian)
    15 January 2022
    0 references
    El objeto del estudio es llevar a cabo trabajos de termomodernización de los edificios de escuelas públicas de Dołuje y Rzędziny en la Comuna de Dobra. El ámbito de trabajo previsto será al mismo tiempo fases materiales de la inversión, a saber: (1) documentación projektowa:studium,audyty,dokumentacja,opinie ornitológica y quiropterológica;(2)Las obras de modernización térmica, incluyendo:(a)Termomodernización SP en Dołujach:1.drzwi nuevo (Puerta de sustitución):Camping stolarki:9,44 m²;2.calentamiento de los estropodos (estropodach GRUPA), Superficie exterior (GRUPA pared exterior + Fundación; Superficie docieplenia:591m2;(b)Termomodernization SP en las Ratings:1. Ebanistería de puertas nuevas (cartera GRUPA 3,400);2. aislamiento — pared exterior (pared exterior de GRUPA), superficie de calentamiento: 306,00 m².El trabajo incluirá también contadores de calor con montaje (energía térmica) y necesarios (resultados de las Condiciones Técnicas) costes adicionales al calentar la fachada (entradas de cubierta e iluminación) para edificios escolares(3)Supervisor;(4)Promoción del proyecto y (5) Costes indirectos. Gracias a las obras de modernización, el ahorro de demanda de calor será superior al 25 %. La implementación dará lugar a la realización de actividades relacionadas con la modernización energética profunda y integral de las instalaciones educativas, que hoy en día sirven tanto a los niños como a los profesores que trabajan en la instalación como objeto educativo y cultural. Los detalles de la obra se describen en SW 2.1.1.1 y 3.1.3.1 (Spanish)
    19 January 2022
    0 references
    Det planlagte omfang af arbejdet vil være begge væsentlige faser af investeringen, nemlig:(1)projekt documentation:study,audyty,documentation,ornithological udtalelser og kiropterologiske udtalelser;(2)termomoderniseringsarbejder, herunder:a)Modernisering af SP i Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permomodernisering af SP i Doples:44. Opvarmning area:591m2;b)Thermomodernisering af SP i RzÄdzin:1. Ny dør tømrerarbejde (GRUPA tømrerarbejde 3.400);2. opvarmning âEUR ydre væg (GRUPA ydre væg), Varmt område: 306,00 m². Arbejdet vil også omfatte varmemålere med installation (varmeenergi) og nødvendige (som følge af de tekniske betingelser) ekstra omkostninger til isolering af facader (lukning og belysning af indgange) til skolebygninger(3)tilsynsinspektør;(4)Forfremme af projektet og (5)mellemomkostninger. (Danish)
    3 July 2022
    0 references
    Το προγραμματισμένο πεδίο των εργασιών θα είναι και τα δύο υλικά στάδια της επένδυσης, και συγκεκριμένα:(1)σχέδιο documentation:study,audyty,documentation,ornithological γνωμοδοτήσεις και χειροποίητες γνώμες, (2)θερμοεκσυγχρονιστικά έργα, συμπεριλαμβανομένων:α) Εκσυγχρονισμός του SP στο Doples:9.44doors-Rounds:,therthermomodernisation,including:α)Περμοεκσυγχρονισμός του SP in Doples:44. Υπερθέρμανση area:591m2· β)Thermomodernization of SP in RzÄdzin:1. Νέα ξυλουργική πόρτα (GRUPA ξυλουργική 3.400);2. θέρμανση â EUR εξωτερικό τοίχο (GRUPA εξωτερικό τοίχο), Ζεστή περιοχή: 306,00 m².Τα έργα θα περιλαμβάνουν επίσης μετρητές θερμότητας με εγκατάσταση (θερμική ενέργεια) και απαραίτητο (που προκύπτει από τους Τεχνικούς Όρους) πρόσθετο κόστος μόνωσης προσόψεων (κλείσιμο και φωτισμό εισόδων) για σχολικά κτίρια(3)Ελεγκτικός Επιθεωρητής, (4)Προώθηση του έργου και (5)Ενδιάμεσες δαπάνες. (Greek)
    3 July 2022
    0 references
    Planirani opseg radova bit će i materijalne faze ulaganja, a to su:(1)projekt documentation:study,audyty,documentation,ornithological mišljenja i kiropterološka mišljenja;(2)termomodernizacija radova, uključujući: (a)Modernizaciju SP-a na Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Permodernizacija SP-a u Dopulju:44. Zagrijavanje area:591m2; (b)Thermodernizacija SP-a u RzÄdzinu:1. Novi stolarija vrata (GRUPA stolarija 3.400);2. zagrijavanje â EUR vanjski zid (GRUPA vanjski zid), Toplo područje: 306,00 m². Radovi će uključivati i brojila topline s instalacijom (toplinskom energijom) i potrebnim (koji proizlaze iz tehničkih uvjeta) dodatne troškove izolacije fasada (zatvaranje i osvjetljenje ulaza) za školske zgrade(3)nadzorni inspektor;(4)Promicanje projekta i (5) Intermedijerni troškovi. (Croatian)
    3 July 2022
    0 references
    Domeniul de aplicare planificat al lucrărilor va fi ambele etape materiale ale investiției, și anume:(1)proiectul documentation:study,audyty,documentation,ornithological avize și opinii chiropterologice;(2)lucrări de termomodernizare, inclusiv:(a)Modernizarea SP în Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Permomodernizarea SP în Doples:44. Încălzirea area:591m2;(b)Thermomodernizarea SP în RzÄdzin:1. Tâmplărie nouă pentru uși (GRUPA tâmplărie 3.400);2. încălzirea peretelui exterior (perete exterior GRUPA), zonă caldă: 306,00 m². Lucrările vor include, de asemenea, contoare de căldură cu instalație (energie termică) și necesare (rezultate din Condițiile tehnice) costuri suplimentare pentru izolarea fațadelor (închiderea și iluminarea intrărilor) pentru clădirile școlare(3)Inspector de supraveghere; (4)Promovarea proiectului și (5) Costuri intermediare. (Romanian)
    3 July 2022
    0 references
    Plánovaný rozsah prác bude predstavovať podstatné etapy investície, a to:(1)projekt documentation:study,audyty,documentation,ornithological stanoviská a chiropterologické stanoviská;(2)termmomodernizačné práce vrátane:a)Modernizácie SP v Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permomodernizácia SP v Doples:44. Otepľovanie area:591m2;b)Thermomodernizácia SP v RzÄdzine:1. Nové dvere tesárstva (GRUPA tesár 3.400);2. otepľovanie vonkajšie steny (GRUPA vonkajšia stena), Teplá plocha: 306,00 m².Pracovné budú zahŕňať aj merače tepla s inštaláciou (tepelná energia) a potrebné (vyplývajúce z technických podmienok) dodatočné náklady na izoláciu fasád (uzavretie a osvetlenie vchodov) pre školské budovy(3)Dozorný inšpektor;(4)Podpora projektu a (5) Medziľahlé náklady. (Slovak)
    3 July 2022
    0 references
    L-ambitu ppjanat tax-xogħlijiet se jkun iż-żewġ stadji materjali tal-investiment, jiġifieri:(1) opinjonijiet tal-proġett documentation:study,audyty,documentation,ornithological u opinjonijiet kiropteroloġiċi; (2)xogħlijiet ta’ modernizzazzjoni, inklużi:(a)Modernizzazzjoni tal-SP f’Doples:9.44doors-Rounds:,therthermomodernisation,including: (a)Il-modernizzazzjoni tal-SP f’Dopli:44. Tisħin area:591m2; (b)Thermomodernization ta ‘SP f’RzÄdzin:1. Karpenterija ġdida bieb (karpenterija GRUPA 3.400); 2. tisħin â EUR ħajt ta ‘barra (ħajt ta’ barra GRUPA), Żona sħuna: 306.00 m².Ix-xogħlijiet se jinkludu wkoll miters tas-sħana bl-installazzjoni (enerġija tas-sħana) u meħtieġa (li jirriżultaw mill-Kundizzjonijiet Tekniċi) spejjeż addizzjonali għall-iżolament tal-faċċati (għeluq u dawl ta’ daħliet) għall-bini tal-iskola(3)Spettur superviżorju; (4)Promozzjoni tal-proġett u (5) Spejjeż intermedji. (Maltese)
    3 July 2022
    0 references
    O âmbito previsto das obras será ambas as fases materiais do investimento, nomeadamente:(1)pareceres do projeto documentation:study,audyty,documentation,ornithological e pareceres quiropterológicos;(2) obras de termomodernização,incluindo:(a)Modernização da SP em Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permomodernização do SP em Doples:44. Aquecimento area:591m2;;b)Termomodernização de SP em RzÄdzin:1. Carpintaria nova da porta (carpintaria GRUPA 3.400);2. parede exterior do aquecimento (parede exterior de GRUPA), área quente: 306,00 m².As obras incluirão também contadores de calor com instalação (energia térmica) e necessários (resultantes das Condições Técnicas) custos adicionais de isolamento de frontarias (fechamento e iluminação de entradas) para edifícios escolares(3)Inspetor de supervisão;(4)Promoção do projeto e (5) Custos intermédios. (Portuguese)
    3 July 2022
    0 references
    Suunnitellut työt ovat sekä investoinnin olennaisia vaiheita: 1)hankkeen documentation:study,audyty,documentation,ornithological lausunnot ja kiropterologiset lausunnot; 2)termodernisointityöt, mukaan lukien a) SP:n nykyaikaistaminen Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permodernization of SP in Doples:44. Lämpeneminen area:591m2;;b) SP: n lämpömodernisointi RzÄdzinissä:1. Uusi ovi kirvesmies (GRUPA puusepäntyö 3.400);2. lämpeneminen ulkoseinä (GRUPA ulkoseinä), Lämmin alue: 306,00 m².Työt sisältävät myös lämpömittarit, joissa on asennus (lämpöenergia) ja välttämättömät (teknisistä ehdoista johtuvat) lisäkustannukset, jotka aiheutuvat julkisivujen eristämisestä (sisäänkäyntien sulkeminen ja valaistus) koulurakennuksissa(3)Valvontatarkastaja,(4)hankkeen edistäminen ja 5) Välikustannukset. (Finnish)
    3 July 2022
    0 references
    Načrtovani obseg del bo zajemal obe vsebinski fazi naložbe, in sicer:(1)projekt documentation:study,audyty,documentation,ornithological mnenja in kiropterološka mnenja;(2)dela osveževanja, vključno z:(a)Posodabljanjem SP v Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Posodobitev SP v Doplesu:44. Segrevanje area:591m2; (b)Thermomodernizacija SP v RzÄdzin:1. Nova tesarska vrata (GRUPA tesarstvo 3.400); 2. ogrevanje zunanje stene (GRUPA zunanja stena), Toplo območje: 306,00 m².Dela bodo vključevala tudi toplotne števce z inštalacijo (toplotno energijo) in potrebne (zaradi tehničnih pogojev) dodatne stroške za izolacijo fasad (zapiranje in osvetlitev vhodov) za šolske stavbe(3)Nadzorni inšpektor;(4)Promocija projekta in (5) Vmesni stroški. (Slovenian)
    3 July 2022
    0 references
    Plánovaným rozsahem prací budou jak materiální fáze investice, a sice:(1)stanoviska projektu documentation:study,audyty,documentation,ornithological a chiropterologická stanoviska;(2)termomodernizační práce, včetně:a)Modernizace SP v Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permomodernizace SP v Doples:44. Oteplování area:591m2;b)Termomodernizace SP v RzÄdzin:1. Nové dveře tesařství (GRUPA tesařství 3.400);2. oteplování â EUR vnější stěna (GRUPA vnější stěna), Teplá plocha: 306,00 m².Výkony budou zahrnovat také měřiče tepla s instalací (tepelnou energii) a nezbytné (vyplývající z technických podmínek) dodatečné náklady na izolaci fasád (uzavírání a osvětlení vchodů) pro školní budovy(3)dohledný inspektor;(4)Podpora projektu a (5) Mezistřední náklady. (Czech)
    3 July 2022
    0 references
    Planuojama darbų apimtis bus abu esminiai investicijų etapai, t. y.:(1)projekto documentation:study,audyty,documentation,ornithological nuomonės ir chiropterologinės nuomonės;(2)termomodernizavimo darbai, įskaitant:a) SP modernizavimą Doples:9.44doors-Rounds:,therthermomodernisation,including:a) SP daugiamodernizavimas Doplese:44. Atšilimas area:591m2; b) Termomodernizacija SP RzÄdzin:1. Naujos durys dailidžių (GRUPA dailidžių 3.400);2. atšilimo â EUR išorinė siena (GRUPA išorinė siena), Šiltas plotas: 306,00 m². Darbai taip pat apims šilumos skaitiklius su instaliavimu (šilumos energija) ir būtinus (dėl techninių sąlygų) papildomas išlaidas fasadų izoliacijai (įėjimų uždarymui ir apšvietimui) mokyklos pastatams(3)Priežiūros inspektorius;(4)Projekto skatinimas ir (5) Tarpinės išlaidos. (Lithuanian)
    3 July 2022
    0 references
    Plānotais darbu apjoms būs abi ieguldījuma būtiskie posmi, proti:(1)projekta documentation:study,audyty,documentation,ornithological atzinumi un chiropteroloģiskie atzinumi;(2) termomodernizācijas darbi, tai skaitā:a) SP modernizācija Doples:9.44doors-Rounds:,therthermomodernisation,including:a) SP Permomodernizācija Doples:44. Sasilšana area:591m2; b) SP termomodernizācija RzÄdzinā:1. Jauna durvju galdniecība (GRUPA galdniecība 3.400); 2. ārējo sienu sasilšana (GRUPA ārsiena), Siltā zona: 306,00 m². Darbos tiks iekļauti arī siltuma skaitītāji ar uzstādīšanu (siltuma enerģiju) un nepieciešamajiem (izriet no tehniskajiem nosacījumiem) papildu izmaksas par ēku fasāžu izolāciju (ieeju aizvēršana un apgaismojums)(3)Uzraudzības inspektors;(4)Projekta veicināšana un (5) Starpizmaksas. (Latvian)
    3 July 2022
    0 references
    Планираният обхват на строителните работи ще бъде както материален етап на инвестицията, а именно:(1)проект documentation:study,audyty,documentation,ornithological становища и хироптерологични становища;(2)термомодернизаводи, включително:(a)Модернизиране на SP в Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Пермомодернизация на SP в Doples:44. Затопляне area:591m2;;б)Термомодернизация на SP в RzÄdzin:1. Нова дърводелска врата (GRUPA дърводелство 3.400);2. затопляне â EUR външната стена (GRUPA външна стена), Топла площ: 306.00 кв.м. Строителните работи ще включват и топломери с монтаж (топлинна енергия) и необходими (в резултат на техническите условия) допълнителни разходи за изолация на фасади (затваряне и осветление на входове) за училищни сгради (3) Надзорен инспектор;(4)Популяризиране на проекта и (5)Междинни разходи. (Bulgarian)
    3 July 2022
    0 references
    A munkálatok tervezett hatóköre a beruházás mindkét lényeges szakasza, nevezetesen:(1)Projekt documentation:study,audyty,documentation,ornithological vélemények és csontkovácsolási vélemények; 2)termmomodernizációs munkák, beleértve:a)Az SP modernizálása Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Az SP Permomodernizációja a Doples:44-ben. Felmelegedés area:591m2;b)Az SP termomodernizálása RzÄdzin:1-ben. Új ajtó asztalos (GRUPA ács 3.400);2. melegítő â EUR külső fal (GRUPA külső fal), Meleg terület: 306,00 m².A munkálatok magukban foglalják az iskolai épületek homlokzatainak szigetelésével kapcsolatos többletköltségeket (bejáratok zárása és megvilágítása) az iskolai épületek homlokzatainak szigetelésével kapcsolatos többletköltségeket (bejáratok zárása és világítása) is.(3)Felügyelő ellenőr;(4)A projekt támogatása és (5)Köztes költségek. (Hungarian)
    3 July 2022
    0 references
    Is éard a bheidh i raon feidhme beartaithe na n-oibreacha an dá chéim ábhartha den infheistíocht, eadhon:(1)tionscadal documentation:study,audyty,documentation,ornithological tuairimí agus tuairimí círeaseolaíocha;(2) Oibreacha teirmeacha-nuachóirithe, lena n-áirítear: (a)Nuachóiriú SP i Doples:9.44doors-Rounds:,therthermomodernisation,including:(a)Permomodernization of the SP in Doples:44. Teocht Téamh: (b)Teirmeodrú SP i RzÄdzin:1. Siúinéireacht doras nua (GRUPA siúinéireacht 3.400); 2. Téamh balla seachtrach (balla seachtrach GRUPA), limistéar te: 306.00 m².Áireofar leis na hoibreacha freisin méadair teasa le suiteáil (fuinneamh teasa) agus riachtanach (mar thoradh ar na Coinníollacha Teicniúla) costais bhreise d’insliú aghaidheanna (dúnadh agus soilsiú bealaí isteach) d’fhoirgnimh scoile(3)Cigire maoirseachta;(4)Cur chun cinn an tionscadail agus (5) Costais idirmheánacha. (Irish)
    3 July 2022
    0 references
    Den planerade omfattningen av arbetena kommer att vara båda väsentliga steg i investeringen, nämligen(1) projekt documentation:study,audyty,documentation,ornithological yttranden och kiropterologiska yttranden,(2)termmoderniseringverk, inklusivea)Modernisering av SP i Doples:9.44doors-Rounds:,therthermomodernisation,including:a)Permomodernisering av SP i Doples:44. Uppvärmning area:591m2;(b)Thermomodernisering av SP i RzÄdzin:1. Ny dörr snickeri (GRUPA snickeri 3.400);2. uppvärmning â EUR yttervägg (GRUPA yttervägg), Varmt område: 306,00 m².Arbeten kommer också att omfatta värmemätare med installation (värmeenergi) och nödvändiga (till följd av de tekniska villkoren) extra kostnader för isolering av fasader (stängning och belysning av entréer) för skolbyggnader(3)Övervakningsinspektör,(4)Främjande av projektet och (5) Mellankostnader. (Swedish)
    3 July 2022
    0 references
    Tööde kavandatud ulatus on mõlemad investeeringu olulised etapid, nimelt: 1)projekt documentation:study,audyty,documentation,ornithological arvamused ja chiropteroloogilised arvamused;(2)termomoderniseerimistööd, sealhulgas:a) SP moderniseerimine Doples:9.44doors-Rounds:,therthermomodernisation,including:a) SP permomoderniseerimine Doplesis:44. Soojenemine area:591m2;b) SP termomoderniseerimine RzÄdzinis:1. Uus uks puusepatöö (GRUPA puusepatöö 3.400); 2. soojenemine välissein (GRUPA välissein), Sooja ala: 306,00 m². Tööde hulka kuuluvad ka soojusarvestid koos paigaldusega (soojusenergiaga) ja vajalikud (tehnilistest tingimustest tulenevad) lisakulud fassaadide isolatsiooniks (sissepääsude sulgemine ja valgustus) koolihoonete jaoks(3)Järelevalveinspektor;(4) Projekti edendamine ja (5) Vahekulud. (Estonian)
    3 July 2022
    0 references
    WOJ.: ZACHODNIOPOMORSKIE, POW.: policki
    0 references

    Identifiers

    RPZP.02.06.00-32-B003/18
    0 references