Expansion of power station 110/15 kV Ostrów Północ (GPZ) (Q86128)

From EU Knowledge Graph
Revision as of 04:27, 26 July 2022 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in da, el, hr, ro, sk, mt, pt, fi, sl, cs, lt, lv, bg, hu, ga, sv, et, nl, fr, de, it, es, and other parts: Adding translations: da, el, hr, ro, sk, mt, pt, fi, sl, cs, lt, lv, bg, hu, ga, sv, et,)
Jump to navigation Jump to search
Project Q86128 in Poland
Language Label Description Also known as
English
Expansion of power station 110/15 kV Ostrów Północ (GPZ)
Project Q86128 in Poland

    Statements

    0 references
    0 references
    6,520,856.51 zloty
    0 references
    1,565,005.56 Euro
    13 January 2020
    0 references
    8,959,504.23 zloty
    0 references
    2,150,281.02 Euro
    13 January 2020
    0 references
    72.78 percent
    0 references
    1 August 2017
    0 references
    30 August 2019
    0 references
    ENERGA-OPERATOR SPÓŁKA AKCYJNA
    0 references
    0 references

    51°38'49.9"N, 17°48'13.7"E
    0 references

    51°40'22.1"N, 17°46'48.7"E
    0 references
    Celem projektu jest zapewnienie bezpieczeństwa dostaw energii elektrycznej dla ok.19,9 tys odbiorców z terenu Miasta i gminy Ostrów Wielkopolski. Zakres projektu obejmuje przebudowę istniejącej stacji elektroenergetycznej 110/15 kV Ostrów Północ. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na którym odbywa się transformacja energii elektrycznej na napięcie 15 kV. (Polish)
    0 references
    The aim of the project is to ensure security of electricity supply for about 19.9 thousand customers from the City and the Municipality of Ostrów Wielkopolski. The scope of the project includes the reconstruction of the existing 110/15 kV Ostrów Północ power station. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English)
    14 October 2020
    0 references
    L’objectif du projet est d’assurer la sécurité de l’approvisionnement en électricité pour environ 19 900 clients de la ville et de la municipalité d’Ostrów Wielkopolski. Le projet comprend la reconstruction de la centrale électrique existante de 110/15 kV Ostrów Północ. La station fait partie d’un réseau de distribution à une tension de 110 kV, sur laquelle l’électricité est transformée en une tension de 15 kV. (French)
    30 November 2021
    0 references
    Ziel des Projekts ist die Sicherung der Stromversorgung für rund 19.9 Tausend Kunden aus der Stadt und Gemeinde Ostrów Wielkopolski. Das Projekt umfasst den Wiederaufbau des bestehenden Kraftwerks 110/15 kV Ostrów Północ. Die Station ist Teil eines Verteilernetzes mit einer Spannung von 110 kV, auf dem Strom in eine Spannung von 15 kV umgewandelt wird. (German)
    7 December 2021
    0 references
    Het doel van het project is de continuïteit van de elektriciteitsvoorziening te waarborgen voor ongeveer 19.9 duizend klanten uit de stad en gemeente Ostrów Wielkopolski. Het project omvat de wederopbouw van de bestaande centrale van 110/15 kV Ostrów Północ. Het station maakt deel uit van een distributienet met een spanning van 110 kV, waarop elektriciteit wordt omgezet in een spanning van 15 kV. (Dutch)
    16 December 2021
    0 references
    L'obiettivo del progetto è garantire la sicurezza dell'approvvigionamento di energia elettrica per circa 19.9 mila clienti della città e del comune di Ostrów Wielkopolski. L'ambito del progetto comprende la ricostruzione dell'attuale centrale elettrica di Ostrów Północ a 110/15 kV. La stazione fa parte di una rete di distribuzione a una tensione di 110 kV, sulla quale l'elettricità viene trasformata in una tensione di 15 kV. (Italian)
    16 January 2022
    0 references
    El objetivo del proyecto es garantizar la seguridad del suministro eléctrico para aproximadamente 199.000 clientes de la ciudad y municipio de Ostrów Wielkopolski. El alcance del proyecto incluye la reconstrucción de la actual central eléctrica de Ostrów Północ de 110/15 kV. La estación forma parte de una red de distribución a una tensión de 110 kV, en la que la electricidad se transforma en una tensión de 15 kV. (Spanish)
    19 January 2022
    0 references
    Formålet med projektet er at sikre elforsyningssikkerheden for omkring 19.9 000 kunder fra byen og Ostrów Wielkopolski kommune. Projektets omfang omfatter genopbygningen af det eksisterende 110/15 kV Ostrów PóÅnoc kraftværk. Stationen er en del af et distributionsnet ved en spænding på 110 kV, hvor elektricitet omdannes til en spænding på 15 kV. (Danish)
    26 July 2022
    0 references
    Στόχος του έργου είναι η διασφάλιση της ασφάλειας του εφοδιασμού με ηλεκτρική ενέργεια για περίπου 19,9 χιλιάδες πελάτες από την πόλη και τον δήμο Ostrów Wielkopolski. Το αντικείμενο του έργου περιλαμβάνει την ανακατασκευή του υφιστάμενου σταθμού παραγωγής ηλεκτρικής ενέργειας 110/15 kV Ostrów Púnoc. Ο σταθμός αποτελεί μέρος δικτύου διανομής με τάση 110 kV, όπου η ηλεκτρική ενέργεια μετατρέπεται σε τάση 15 kV. (Greek)
    26 July 2022
    0 references
    Cilj projekta je osigurati sigurnost opskrbe električnom energijom za oko 19,9 tisuća kupaca iz Grada i Općine Ostrów Wielkopolski. Opseg projekta uključuje rekonstrukciju postojeće 110/15 kV Ostrów PóÅnoc elektrane. Stanica je dio distribucijske mreže pri naponu od 110 kV, gdje se električna energija pretvara u napon od 15 kV. (Croatian)
    26 July 2022
    0 references
    Scopul proiectului este de a asigura securitatea aprovizionării cu energie electrică pentru aproximativ 19,9 mii de clienți din oraș și municipalitatea Ostrów Wielkopolski. Domeniul de aplicare al proiectului include reconstrucția centralei electrice existente 110/15 kV Ostrów PĂ³Ånoc. Stația face parte dintr-o rețea de distribuție la o tensiune de 110 kV, unde energia electrică este transformată într-o tensiune de 15 kV. (Romanian)
    26 July 2022
    0 references
    Cieľom projektu je zabezpečiť bezpečnosť dodávok elektrickej energie pre približne 19,9 tisíc zákazníkov z mesta a obce Ostrów Wielkopolski. Rozsah projektu zahŕňa rekonštrukciu existujúcej elektrárne 110/15 kV Ostrów PóÅnoc. Stanica je súčasťou distribučnej siete s napätím 110 kV, kde sa elektrická energia transformuje na napätie 15 kV. (Slovak)
    26 July 2022
    0 references
    L-għan tal-proġett huwa li jiżgura s-sigurtà tal-provvista tal-elettriku għal madwar 19.9 elf klijent mill-Belt u l-Muniċipalità ta’ Ostrów Wielkopolski. L-ambitu tal-proġett jinkludi r-rikostruzzjoni tal-impjant tal-enerġija eżistenti 110/15 kV Ostrów PóÅnoc. L-istazzjon huwa parti minn netwerk ta’ distribuzzjoni b’vultaġġ ta’ 110 kV, fejn l-elettriku jinbidel għal vultaġġ ta’ 15 kV. (Maltese)
    26 July 2022
    0 references
    O objetivo do projeto é garantir a segurança do fornecimento de eletricidade para cerca de 19,9 mil clientes da Cidade e do Concelho de Ostrów Wielkopolski. O âmbito do projeto inclui a reconstrução da atual central elétrica de 110/15 kV Ostrów PóÅnoc. A estação faz parte de uma rede de distribuição a uma tensão de 110 kV, onde a eletricidade é transformada a uma tensão de 15 kV. (Portuguese)
    26 July 2022
    0 references
    Hankkeen tavoitteena on varmistaa sähkön toimitusvarmuus noin 19,9 tuhannelle asiakkaalle kaupungista ja Ostrów Wielkopolskin kunnasta. Hankkeen piiriin kuuluu nykyisen 110/15 kV Ostrów PóÅnocin voimalaitoksen jälleenrakentaminen. Asema on osa jakeluverkkoa 110 kV:n jännitteellä, jossa sähkö muunnetaan 15 kV:n jännitteeksi. (Finnish)
    26 July 2022
    0 references
    Cilj projekta je zagotoviti zanesljivost oskrbe z električno energijo za približno 19,9 tisoč odjemalcev iz mesta in občine Ostrów Wielkopolski. Obseg projekta vključuje obnovo obstoječe elektrarne Ostrów Pów PóÅnoc 110/15 kV. Postaja je del distribucijskega omrežja pri napetosti 110 kV, kjer se električna energija pretvori v napetost 15 kV. (Slovenian)
    26 July 2022
    0 references
    Cílem projektu je zajistit bezpečnost dodávek elektřiny pro přibližně 19,9 tisíc zákazníků z města a obce Ostrów Wielkopolski. Součástí projektu je rekonstrukce stávající elektrárny 110/15 kV Ostrów PóÅnoc. Stanice je součástí distribuční sítě o napětí 110 kV, kde je elektřina přeměněna na napětí 15 kV. (Czech)
    26 July 2022
    0 references
    Projekto tikslas – užtikrinti elektros energijos tiekimo saugumą apie 19,9 tūkst. klientų iš miesto ir Ostrów Wielkopolski savivaldybės. Projekto apimtis apima esamos 110/15 kV Ostrów PóÅnoc elektrinės rekonstrukciją. Stotis yra 110 kV įtampos skirstomojo tinklo dalis, kurioje elektros energija transformuojama į 15 kV įtampą. (Lithuanian)
    26 July 2022
    0 references
    Projekta mērķis ir nodrošināt elektroapgādes drošību aptuveni 19,9 tūkst. klientu no pilsētas un Ostró³w Wielkopolski pašvaldības. Projekta darbības joma ietver esošās 110/15 kV Ostrów Pów elektrostacijas rekonstrukciju. Stacija ir daļa no sadales tīkla ar spriegumu 110 kV, kur elektrība tiek pārveidota par 15 kV spriegumu. (Latvian)
    26 July 2022
    0 references
    Целта на проекта е да се гарантира сигурността на електроснабдяването за около 19,9 хиляди клиенти от града и община Ostrów Wielkopolski. Обхватът на проекта включва реконструкцията на съществуващата електроцентрала Ostrów PóÅnoc 110/15 kV. Станцията е част от разпределителна мрежа с напрежение 110 kV, където електроенергията се преобразува в напрежение 15 kV. (Bulgarian)
    26 July 2022
    0 references
    A projekt célja, hogy a város és Ostrów Wielkopolski önkormányzata mintegy 19,9 ezer fogyasztója számára biztosítsa a villamosenergia-ellátás biztonságát. A projekt kiterjed a meglévő 110/15 kV-os Ostrów Pónoc erőmű újjáépítésére. Az állomás 110 kV feszültségű elosztóhálózat része, ahol a villamos energiát 15 kV feszültségre alakítják át. (Hungarian)
    26 July 2022
    0 references
    Is é aidhm an tionscadail slándáil an tsoláthair leictreachais a chinntiú ar feadh thart ar 19.9 míle custaiméir ón gCathair agus ó Bardas Ostrów Wielkopolski. Cuimsíonn raon feidhme an tionscadail atógáil an stáisiúin chumhachta 110/15 kV Ostrów PóÅnoc atá ann cheana féin. Tá an stáisiún mar chuid de ghréasán dáileacháin ag voltas 110 kV, áit a ndéantar leictreachas a chlaochlú go voltas 15 kV. (Irish)
    26 July 2022
    0 references
    Syftet med projektet är att trygga elförsörjningen för cirka 19,9 tusen kunder från staden och kommunen Ostrów Wielkopolski. Projektet omfattar återuppbyggnad av det befintliga kraftverket 110/15 kV Ostrów PóÅnoc. Stationen är en del av ett distributionsnät med en spänning på 110 kV, där el omvandlas till en spänning på 15 kV. (Swedish)
    26 July 2022
    0 references
    Projekti eesmärk on tagada elektrivarustuskindlus umbes 19,9 tuhandele kliendile linnast ja Ostrów Wielkopolski omavalitsusest. Projekt hõlmab olemasoleva 110/15 kV Ostrów P³Ånoci elektrijaama rekonstrueerimist. Jaam on osa jaotusvõrgust pingega 110 kV, kus elekter muundatakse pingeks 15 kV. (Estonian)
    26 July 2022
    0 references

    Identifiers

    POIS.07.01.00-00-0012/17
    0 references