Construction of the Regional Road Racibórz-Pszczyna on the section from the incorporation into DK No. 45 in Rudnik commune to the border of the town on the rights of Rybnik district – stage 4 and stage 5 of the Eastern Raciborza Circuit (Q124486)

From EU Knowledge Graph
Revision as of 07:12, 8 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
Jump to navigation Jump to search
Project Q124486 in Poland
Language Label Description Also known as
English
Construction of the Regional Road Racibórz-Pszczyna on the section from the incorporation into DK No. 45 in Rudnik commune to the border of the town on the rights of Rybnik district – stage 4 and stage 5 of the Eastern Raciborza Circuit
Project Q124486 in Poland

    Statements

    0 references
    146,000,000.0 zloty
    0 references
    35,040,000.0 Euro
    13 January 2020
    0 references
    171,764,705.9 zloty
    0 references
    41,223,529.42 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2018
    0 references
    31 December 2020
    0 references
    WOJEWÓDZTWO ŚLĄSKIE
    0 references

    50°5'25.4"N, 18°12'54.4"E
    0 references

    50°9'15.8"N, 18°10'13.8"E
    0 references
    Przedmiotem projektu jest budowa nowego odcinka drogi o długości 7,83 km, który stanowić będzie nowy przebieg drogi wojewódzkiej nr 935 od DK 45 w gminie Rudnik do ul. Piaskowej w Raciborzu. Zaprojektowano drogę jednojezdniową, na odcinkach szczególnie obciążonych ruchem poszerzoną do dwóch jezdni. W ramach inwestycji planowana jest realizacja następujących zadań: -budowa nowego przebiegu drogi wojewódzkiej nr 935, -budowa punktów węzłowych, -budowa obiektów inżynierskich, -budowa sieci, w tym: budowa odwodnienia drogi, przebudowa sieci wodociągowych, przebudowa sieci gazowych, sanitarnych, -przebudowa sieci elektroenergetycznych, -budowa oświetlenia ulicznego, -budowa sieci teletechnicznych, Rzeczową realizację projektu zaplanowano na lata 2018-2020. Odcinek objęty opracowaniem stanowi obwodnicę Raciborza i jest realizacją budowy drogi Regionalnej w nowym śladzie biegnącej ze wschodu na zachód od DK 1 w Pszczynie do DK 45 w m. Rudnik. (Polish)
    0 references
    The subject of the project is the construction of a new section of the road with a length of 7.83 km, which will constitute a new course of the Voivodeship Road No. 935 from DK 45 in the commune Rudnik to ul. Sandstone in Raciborz. A single-road road was designed, on sections that were particularly loaded with traffic extended to two carriageways. As part of the investment, the following tasks are planned: —construction of the new course of the voivodship road No. 935, – construction of nodes, -construction of engineering facilities, -construction of the network, including: construction of road drainage, reconstruction of water supply networks, reconstruction of gas, sanitary networks, -construction of electricity grids, -street lighting construction, – construction of teletechnical networks, real implementation of the project is planned for the years 2018-2020. The section covered by the study is the Raciborz bypass and is the construction of the Regional Road in a new trail running from the east to the west from DK 1 in Pszczyna to DK 45 in Rudnik. (English)
    21 October 2020
    0 references
    L’objet du projet est la construction d’un nouveau tronçon de la route d’une longueur de 7,83 km, qui constituera un nouvel itinéraire de la route provinciale no 935 de DK 45 dans la municipalité de Rudnik à ul. Sandy à Raciborz. Une route à un seul wagon a été conçue sur des tronçons particulièrement chargés de trafic étendu vers deux chaussées. Dans le cadre de l’investissement, les tâches suivantes sont prévues: construction d’un nouveau tracé de la route provinciale no 935, construction de nœuds, construction de structures d’ingénierie, construction de réseaux, y compris: la construction du drainage routier, la reconstruction des réseaux d’approvisionnement en eau, la reconstruction des réseaux gaziers et sanitaires, la reconstruction des réseaux électriques, la construction d’éclairage public, la construction de réseaux télétechniques, la mise en œuvre physique du projet est prévue pour 2018-2020. La section en cours de développement est le contournement de Raciborz et est la construction de la route régionale sur une nouvelle voie qui va d’est en ouest de DK 1 à Pszczyna à DK 45 à Rudnik. (French)
    2 December 2021
    0 references
    Gegenstand des Projekts ist der Bau eines neuen Abschnitts der Straße mit einer Länge von 7,83 km, der eine neue Route der Provinzstraße Nr. 935 von DK 45 in der Gemeinde Rudnik nach ul bilden wird. Sand in Raciborz. Auf Abschnitten, die besonders mit erweitertem Verkehr auf zwei Fahrbahnen beladen sind, wurde eine Einfahrstraße entworfen. Im Rahmen der Investition sind folgende Aufgaben geplant: Bau einer neuen Route der Provinzstraße Nr. 935, Bau von Knoten, Bau von Ingenieurbauten, -Bau von Netzen, einschließlich: der Bau der Straßenentwässerung, der Wiederaufbau von Wasserversorgungsnetzen, der Wiederaufbau von Gas- und Sanitärnetzen, der Wiederaufbau von Stromnetzen, der Bau der Straßenbeleuchtung, der Bau teletechnischer Netze, die physische Umsetzung des Projekts sind für den Zeitraum 2018-2020 geplant. Der in Entwicklung befindliche Abschnitt ist die Umgehungsstraße Raciborz und ist der Bau der Regionalstraße in einer neuen Strecke von Osten nach Westen von DK 1 in Pszczyna bis DK 45 in Rudnik. (German)
    8 December 2021
    0 references

    Identifiers

    RPSL.06.01.00-24-09G0/16
    0 references