Construction of a photovoltaic farm with installed capacity of 0,99 MW together with the necessary technical infrastructure and connection to the power grid in Kraśnik Koszaliński (Q137714)
Jump to navigation
Jump to search
Project Q137714 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a photovoltaic farm with installed capacity of 0,99 MW together with the necessary technical infrastructure and connection to the power grid in Kraśnik Koszaliński |
Project Q137714 in Poland |
Statements
1,951,914.64 zloty
0 references
2,741,693.98 zloty
0 references
71.19 percent
0 references
28 February 2017
0 references
31 July 2018
0 references
ES JUTRZENKA 2 SP. Z O.O.
0 references
Przedmiotem projektu jest budowa farmy fotowoltaicznej o mocy 0,99 MW w miejscowości Kraśnik Koszaliński na działce ew. nr 153. Projekt ma charakter stacjonarny. W ramach realizacji projektu Wnioskodawca dokona zakupu instalacji fotowoltaicznej z niezbędnymi elementami oraz przeprowadzi prace w obrębie infrastruktury elektrycznej niezbędne z punktu widzenia uruchomienia farmy. Projekt będzie składał się z jednego etapu polegającego na budowie farmy fotowoltaicznej. W wyniku realizacji projektu Wnioskodawca rozpocznie produkcję energii elektrycznej ze słońca, dzięki czemu możliwe będzie osiągnięcie określonych w we wniosku wskaźników rezultatu. (Polish)
0 references
The subject of the project is the construction of a photovoltaic farm with a capacity of 0.99 MW in Kraśnik Koszaliński on plot no. 153. The project is stationary. As part of the project, the applicant will purchase a photovoltaic installation with the necessary elements and carry out works within the electrical infrastructure necessary for the start-up of the farm. The project will consist of one stage consisting of the construction of a photovoltaic farm. As a result of the project, the Applicant will start the production of electricity from the sun, so that it will be possible to achieve the result indicators specified in the proposal. (English)
21 October 2020
0 references
Le projet concerne la construction d’une ferme photovoltaïque de 0,99 MW à Kraśnik Koszaliński sur la parcelle no 153. Le projet est stationnaire. Dans le cadre de la mise en œuvre du projet, la requérante achètera une installation photovoltaïque avec les éléments nécessaires et réalisera les travaux au sein de l’infrastructure électrique nécessaire au démarrage de l’exploitation. Le projet consistera en une phase de construction d’une ferme photovoltaïque. À la suite du projet, la requérante commencera à produire de l’électricité à partir du soleil afin que les indicateurs de résultat spécifiés dans la demande puissent être atteints. (French)
2 December 2021
0 references
Identifiers
RPZP.02.10.00-32-A109/16
0 references