Construction and reconstruction of the district road no. 3903P on the section from the 305 voivodeship road to the junction of the S 5 – Nietążkowo road (Q135181)

From EU Knowledge Graph
Revision as of 19:53, 2 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): L’objet de l’investissement est la construction et la reconstruction d’une route à partir de la route de district no 3903P à partir de l’intersection avec la route 305 Wschowa-Wolsztyn, à travers Wijewo, Brenno,m.Zaborówiec,m.Włoszakowice,m.Bukówiec Górny,m.Boguszyn,m.Bronikowo, Podśmigiel, jusqu’à la jonction prévue pour la construction de l’autoroute S5 (Poznań-Wrocław reliant les deux autoroutes A2 et A4) faisant partie du réseau RTE-T. Le pr...)
Jump to navigation Jump to search
Project Q135181 in Poland
Language Label Description Also known as
English
Construction and reconstruction of the district road no. 3903P on the section from the 305 voivodeship road to the junction of the S 5 – Nietążkowo road
Project Q135181 in Poland

    Statements

    0 references
    36,200,931.5 zloty
    0 references
    8,688,223.56 Euro
    13 January 2020
    0 references
    48,267,908.68 zloty
    0 references
    11,584,298.08 Euro
    13 January 2020
    0 references
    75.0 percent
    0 references
    26 February 2016
    0 references
    23 January 2019
    0 references
    POWIAT LESZCZYŃSKI
    0 references
    0 references
    Przedmiotem inwestycji jest budowa oraz przebudowa drogi na odcinku od drogi powiatowej nr 3903P od skrzyżowania z drogą wojewódzką 305 relacji Wschowa-Wolsztyn,przez m.Wijewo,m.Brenno,m.Zaborówiec,m.Włoszakowice,m.Bukówiec Górny,m.Boguszyn,m.Bronikowo,m. Podśmigiel,do węzła planowanej do budowy drogi ekspresowej S5(Poznań–Wrocław łączącej dwie autostrady A2 i A4)stanowiącej element sieci TEN-T.Projekt realizowany będzie w granicach administracyjnych Woj. Wlkp.,na terenie dwóch powiatów:leszczyńskiego oraz kościańskiego w obrębie trzech gmin Wijewo,Włoszakowice(powiat leszczyński) i gminy Śmigiel(powiat kościański).Powstały w ramach projektu ciąg drogowy będzie ciągiem jednorodnym,a więc tą samą drogą lokalną (kończącą się na węźle do drogi ekspresowej)posiadająca tę samą kategorię i numer (3903 P).Całkowita długość odcinka wynosić będzie 29 km,natomiast w ramach projektu zrealizowana zostanie budowa oraz przebudowa 28 085 m odcinka drogi (wg szczegółowego opisu w podziale na odcinki zawartego w Studium Wykonalności).Na odcinku ponad 600 m (wpisujących się w przedmiotowy ciąg)znajduje się odcinek drogi na przebudowę którego Powiat Leszczyński uzyskał dofinansowanie w ramach PROW 2014-2020 oraz rondo,którego nie obejmuje konieczność przebudowy(wg opisu z pkt 3.6.1).Projekt będzie realizowany przez dwa samorządy:Powiat Leszczyński oraz Powiat Kościański (partner projektu)-wg zapisów umowy partnerskiej zawartej na potrzeby realizacji projektu.W ramach projektu planuje się osiągnąć następujące wskaźniki:Długość przebudowanych dróg powiatowych -21,525 km Dł. wybudowanych dróg powiatowych-6559,1km Dł. wspartej infrastruktury rowerowej -6,722 km Liczba wybudowanych obwodnic -1 szt. Dł. wyb. lub przeb.chodników-6,7 kmL. wyb. lub przeb.drogowych obiektów inzynierskich - 7 szt. L. wyb. lub przeb. punktów oświetleniowych-32szt.l.wyb. lub przeb.skrzyzowań-27szt.L.wyb./ przeb.przejść przez jezdnię-21 szt.L. wyb./przeb. zatok autobusowych-2 szt. (Polish)
    0 references
    The object of the investment is the construction and reconstruction of the road on the section from the district road no.3903P from the intersection with the voivodeship road 305 of the Wschów-Wolsztyn relations, through Wijewo,m.Brenno,m.Zaborówiec,m.Włoszakowice,m.Bukówiec Górny,m.Boguszyn,m.Bronikowo,m.Podśmigiel,m.Podśmigiel,to the junction to the junction to the construction of the expressway S5, will be two interstate in Boguszyn,m.Bronikowo,m.Podśmigiel,m.Podśmigiel,to the junction for the construction of the expressway S5 and the construction of an expressway S5 In the course of the project there will be a detailed description of the road in the framework of the project, which will be carried out in the framework of the project will be a homogeneous sequence, and thus the same local road will be built (ending on the nodes to the express road) having the same category and number (3903 P).The total length of the section will be 29 km, the total length of the section will be equal to 6559 km. Lengths or walkways-6.7 kmL. or via road engineering objects – 7 pcs. L. or pass lighting points-32pc.l.j. or crossovers-27pc.L.V.b./pass through the road-21 pcs L./bus bays-2 pcs. (English)
    21 October 2020
    0 references
    L’objet de l’investissement est la construction et la reconstruction d’une route à partir de la route de district no 3903P à partir de l’intersection avec la route 305 Wschowa-Wolsztyn, à travers Wijewo, Brenno,m.Zaborówiec,m.Włoszakowice,m.Bukówiec Górny,m.Boguszyn,m.Bronikowo, Podśmigiel, jusqu’à la jonction prévue pour la construction de l’autoroute S5 (Poznań-Wrocław reliant les deux autoroutes A2 et A4) faisant partie du réseau RTE-T. Le projet sera mis en œuvre à l’intérieur des frontières administratives. Wlkp., sur le territoire de deux powiatów:leszczyńskiego et Kościanski dans les trois communes de Wijewo, Włoszakowice (arrondissement de Leszczyński) et la commune de Śmigiel (arrondissement de Kościański).La route tracée dans le cadre du projet sera une ligne homogène, et donc la même route locale (finissant à la jonction avec la route express) avec la même catégorie et le même numéro (3903 P).La longueur totale du tronçon sera de 29 km, D’autre part, le projet réalisera la construction et la reconstruction du tronçon de 28 085 m de la route (selon la description détaillée en sections contenues dans l’étude de faisabilité).Sur le tronçon de plus de 600 m (inclus dans la route en question), il y a un tronçon de la route pour la reconstruction dont le district de Leszczyński a bénéficié d’un financement au titre du PDR 2014-2020 et d’un rond-point, ce qui n’inclut pas la nécessité de la reconstruction (comme décrit au point 3.6.1).Le projet sera mis en œuvre par deux samorządy:Powiat Leszczyński et le district de Kościanski (partenaire du projet) — conformément à la description figurant au point 3.6.1. les dispositions de l’accord de partenariat conclu pour la mise en œuvre du projet.Dans le cadre du projet, il est prévu de réaliser les routes de district reconstruites ci-après -21,525 km. de routes de district construites-6 559,1 km L. d’infrastructures cyclables soutenues — 6,722 km Nombre de contournements construits -1 pcs. Longueur ou trottoirs de 6,7 kmL. ou à travers des objets d’ingénierie routière — 7 pièces. L. points d’éclairage-32 unités ou sections transversales-27pcs L. Wyb./passer à travers la chaussée-21 pcs L./bus baies-2 pcs. (French)
    2 December 2021
    0 references

    Identifiers

    RPWP.05.01.02-30-0010/16
    0 references