Investments in RES in Rozogi Municipality (Q131943)

From EU Knowledge Graph
Revision as of 19:24, 2 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): OBJET DU PROJET: Construction de 5 installations de panneaux photovoltaïques dans la municipalité de Rozogi, district de pointe: 1. Équipe scolaire et pré-école à Clon 96 12-14 Rozogi, terrain: 613-1 installation 19.76 KW (76 panneaux PV, 260 W et 1 pcs. Inverseur 20 KW) 2. École primaire Jean-Paul II à Rozogy — ul. Marché 13 12-114 Rozogi, parcelles: 218, 219-1 installation de 30,94 KW (119 pièces de panneaux photovoltaïques, 260 W et 2 pcs. On...)
Jump to navigation Jump to search
Project Q131943 in Poland
Language Label Description Also known as
English
Investments in RES in Rozogi Municipality
Project Q131943 in Poland

    Statements

    0 references
    620,762.67 zloty
    0 references
    148,983.04 Euro
    13 January 2020
    0 references
    730,309.02 zloty
    0 references
    175,274.16 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    6 November 2017
    0 references
    31 October 2020
    0 references
    GMINA ROZOGI
    0 references
    0 references

    53°28'56.6"N, 21°21'34.9"E
    0 references
    PRZEDMIOT PROJEKTU: Budowa 5 instalacji paneli fotowoltaicznych w Gminie Rozogi, powiat szczycieński: 1. Zespół Szkolno-Przedszkolny w Klonie – Klon 96 12-14 Rozogi, działka: 613 - 1 instalacja 19,76 KW (76 szt. paneli fotowoltaicznych, 260W oraz 1 szt. Inwertera 20 KW) 2. Szkoła Podstawowa im. Jana Pawła II w Rozogach - ul. Rynek 13 12-114 Rozogi, działki: 218, 219 - 1 instalacja 30,94 KW (119 szt. paneli fotowoltaicznych, 260W oraz 2 szt. Inwerterów po 15 KW) 3. Zespół Szkół w Rozogach: – ul. Rynek 13 12-114 Rozogi, działki: 218, 219 - 2 instalacje po 30,94 KW (2 instalacje po 119 szt. paneli fotowoltaicznych, 260W oraz 2 szt. Inwerterów po 15 KW) 4. Szkoła Podstawowa w Dąbrowach - Dąbrowy 238 12-114 Rozogi, działki: 1481/1, 1481/2 - 1 instalacja 19,76 KW (76 szt. paneli fotowoltaicznych, 260W oraz 1 szt. Inwertera 20 KW) ETAPY REALIZACJI PROJEKTU: - złożenie wniosku o dofinansowanie - podpisanie umowy o dofinansowanie - wybór wykonawcy zgodnie z PZP - zawarcie umowy z wykonawcą i rozpoczęcie prac - realizacja prac zgodnie z założonym harmonogramem - zakończenie projektu i podpisanie protokołu końcowego - końcowe rozliczenie projektu Projekt wpisuje się w założenia wpisane w SzOOP RPO WWM realizując założony cel: Zwiększony udział OZE w ogólnym bilansie energetycznym regionu. Realizacja projektu pozwoli na zwiększenie udziału energii odnawialnej w bilansie energetycznym Wnioskodawcy, co wpłynie na zwiększenie udziału energii odnawialnej w bilansie energetycznym regionu Warmii i Mazur. Wpłynie to na ograniczenie emisji szkodliwych gazów i pyłów do atmosfery oraz dzięki wykorzystaniu lokalnych źródeł energii odnawialnej zwiększy konkurencyjność, ekonomiczną efektywność działania Wnioskodawcy. W wyniku realizacji inwestycji spadną ponoszone przez Wnioskodawcę koszty związane z zużyciem energii. (Polish)
    0 references
    SUBJECT MATTER OF THE PROJECT: Construction of 5 installation of photovoltaic panels in Rozogi commune, Górny county: 1. Klon – Klon 96 12-14 Rozogi, plot: 613-1 installation 19,76 KW (76 pcs. photovoltaic panels, 260 W and 1 pcs. Inverter 20 KW) 2. John Paul II Primary School in Rozogy – ul. Marketplace 13 12-114 Rozogi, plots: 218, 219-1 installation of 30.94 KW (119 pcs. photovoltaic panels, 260 W and 2 pcs. Inverters after 15 KW) 3. School team in Rozogach: — ul. Marketplace 13 12-114 Rozogi, plots: 218, 219-2 installations of 30.94 KW (2 installations of 119 PV panels, 260 W and 2 pcs. Inverters after 15 KW) 4. Primary School in Dąbrowa – Dąbrowa 238 12-114 Rozogi, plots: 1481/1, 1481/2-1 installation 19.76 KW (76 pcs. photovoltaic panels, 260 W and 1 pcs. Inverter 20 KW) ETAPY OF PROJECT REALISATION: — submission of an application for funding – signing of the grant agreement – selection of the contractor in accordance with the PZP – conclusion of an agreement with the contractor and commencement of works – implementation of works according to the planned schedule – completion of the project and signing of the final protocol – final settlement of the project The project is part of the assumptions entered in the RPO WWM’s SzOOP, fulfilling the objective of: Increased share of RES in the overall energy balance of the region. The project will increase the share of renewable energy in the Applicant’s energy balance, which will increase the share of renewable energy in the energy balance of the region of Warmia and Mazury. This will reduce emissions of harmful gases and dust into the atmosphere and by using local renewable energy sources will increase the competitiveness and economic efficiency of the Applicant. As a result of the investment, the costs related to energy consumption will fall for the applicant. (English)
    21 October 2020
    0 references
    OBJET DU PROJET: Construction de 5 installations de panneaux photovoltaïques dans la municipalité de Rozogi, district de pointe: 1. Équipe scolaire et pré-école à Clon 96 12-14 Rozogi, terrain: 613-1 installation 19.76 KW (76 panneaux PV, 260 W et 1 pcs. Inverseur 20 KW) 2. École primaire Jean-Paul II à Rozogy — ul. Marché 13 12-114 Rozogi, parcelles: 218, 219-1 installation de 30,94 KW (119 pièces de panneaux photovoltaïques, 260 W et 2 pcs. Onduleurs après 15 KW) 3. Complexe scolaire à Rozogy: — St. Marché 13 12-114 Rozogi, parcelles: 218, 219-2 installations de 30,94 KW (2 installations de 119 unités de panneaux photovoltaïques, 260 W et 2 pièces. Onduleurs de 15 KW) 4. École primaire à Dąbrowa — Dąbrowy 238 12-114 Rozogi, parcelles: 1481/1, 1481/2-1 installation 19.76 KW (76 panneaux PV, 260 W et 1 pcs. Onduleur 20 KW) PROJET DE RÉALISATION ETAP: — soumission de la demande de financement — signature de la convention de subvention — sélection du contractant conformément au PHP — conclusion du contrat avec le contractant et début des travaux — exécution des travaux selon le calendrier prévu — achèvement du projet et signature du protocole final — règlement final du projet Le projet est conforme aux hypothèses figurant dans le SzOOP ROP MPW aux fins: Augmentation de la part des SER dans le bilan énergétique global de la région. La mise en œuvre du projet augmentera la part des énergies renouvelables dans le bilan énergétique de la requérante, ce qui augmentera la part des énergies renouvelables dans le bilan énergétique de la région de Warmia et de Mazury. Cela permettra de réduire les émissions de gaz et de poussières nocifs dans l’atmosphère et d’accroître la compétitivité et l’efficacité économique de la requérante grâce à l’utilisation de sources d’énergie renouvelables locales. À la suite de l’investissement, les coûts liés à la consommation d’énergie supportés par la requérante diminueront. (French)
    2 December 2021
    0 references

    Identifiers

    RPWM.04.01.00-28-0333/17
    0 references