Pavement of the communication system through the construction of the P&R parking lot on the route of the Rapid Agglomeration Railway in Miechów (Q113042)

From EU Knowledge Graph
Revision as of 20:16, 1 December 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): Le projet sera mis en œuvre dans la formule Conception et construction. Les tâches du projet sont:1. Exécution de la documentation technique;2. Travaux de construction liés à la construction de parkings PR et BR ainsi que des infrastructures d’accompagnement d’une superficie totale d’env. 4 540 m².3. Supervision des investisseurs. Aucune des activités prévues ne concerne les travaux de rénovation et ne concernera pas l’entretien de l’infrastruct...)
Jump to navigation Jump to search
Project Q113042 in Poland
Language Label Description Also known as
English
Pavement of the communication system through the construction of the P&R parking lot on the route of the Rapid Agglomeration Railway in Miechów
Project Q113042 in Poland

    Statements

    0 references
    2,368,259.61 zloty
    0 references
    568,382.31 Euro
    13 January 2020
    0 references
    2,786,187.79 zloty
    0 references
    668,685.07 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 March 2018
    0 references
    28 February 2020
    0 references
    GMINA MIECHÓW
    0 references
    Q2524748 (Deleted Item)
    0 references
    Projekt realizowany będzie w formule Zaprojektuj i wybuduj. Zadania w ramach projektu to:1. Wykonanie dokumentacji technicznej;2. Prace budowlane związane z wykonaniem parkingów PR oraz BR wraz z infrastrukturą towarzyszącą o łącznej powierzchni ok. 4540 m2.3. Nadzór inwestorski.Żadne z zaplanowanych działań nie dotyczą prac remontowych oraz nie będą dotyczyły utrzymania powstałej infrastruktury.Powstała infrastruktura służyć będzie wyłącznie obsłudze podróżnych korzystających z połączeń kolejowych dworca PKP w Miechowie. Powstały parking zlokalizowany będzie na przedmieściach Miechowa, z daleka od centrum oraz w dalekiej odległości od innych punktów typu punkty handlowe, kościół, restauracje itd. W związku z taką lokalizacją parkingu nie będą z niego korzystały inne osoby niż zainteresowane podróżą koleją.Nowa infrastruktura PR posiada potencjał integracyjny względem innych środków transportu. Przy dworcu PKP w Miechowie zatrzymują się prywatne busy linii MiechówMostek w Gołcza. Parking PR będzie położony w odległości ok. 5 minut pieszo od dworca autobusowego obsługiwanego przez prywatnych przewoźników oraz MPK. Na nowym parkingu utworzony będzie przystanek autobusowy, udostępniony wszystkim zainteresowanym przewoźnikom. Planuje się też uruchomienie miejskiej komunikacji autobusowej, wykorzystującej ww przystanek przy dworcu i skoordynowanej z kursami SKA. Jednocześnie parking BikeRide utworzony w ramach projektu zachęci mieszkańców do częstszego korzystania z roweru celem dojazdu do dworca i dalszej kontynuacji podróży koleją.Projekt odpowiada na potrzeby komunikacyjne mieszkańców Miechowa i gminy Miechów w zakresie możliwości przesiadki z transportu indywidualnego na pociąg. Całość zmierza do redukcji wykorzystania samochodów osobowych w codziennym funkcjonowaniu mieszkańców i zastąpienie ich transportem ekologicznym. Spodziewanym efektem będzie przede wszystkim redukcja zanieczyszczeń powietrza emitowanych z nadmiernego ruchu samochodowego. (Polish)
    0 references
    The project will be implemented in the Build and Design formula. The project’s tasks are:1. The implementation of the technical documentation;2. Construction works related to the construction of PR and BR car parks together with the accompanying infrastructure with a total area of approx. 4540 m².3. None of the planned activities concern repair work and will not concern the maintenance of the infrastructure.The infrastructure will be used exclusively for the service of travellers using the railway connections of the railway station in Miechów. The car park will be located on the outskirts of Miechów, far from the centre and in a long distance from other points such as shopping malls, church, restaurants, etc. As a result of this location, the car park will not be used by people other than interested in rail travel.The new PR infrastructure has an integration potential for other modes of transport. Private buses of MiechówMostek line in Gołcza stop at the railway station in Miechów. The PR car park will be located in a distance of approx. 5 minutes walk from the bus station operated by private carriers and MPK. There will be a bus stop available to all interested carriers in the new car park. It is also planned to launch a public bus service, using at the stop at the station and coordinated with the SKA courses. At the same time, the BikeRide car park created as part of the project will encourage residents to use their bicycle more frequently to get to the station and continue to travel by rail.The project responds to the communication needs of residents of Miechów and Miechów commune in terms of switching from individual transport to train. The whole aims to reduce the use of passenger cars in the everyday functioning of residents and replace them with green transport. The expected effect will be mainly the reduction of air pollutants emitted from excessive car traffic. (English)
    20 October 2020
    0 references
    Le projet sera mis en œuvre dans la formule Conception et construction. Les tâches du projet sont:1. Exécution de la documentation technique;2. Travaux de construction liés à la construction de parkings PR et BR ainsi que des infrastructures d’accompagnement d’une superficie totale d’env. 4 540 m².3. Supervision des investisseurs. Aucune des activités prévues ne concerne les travaux de rénovation et ne concernera pas l’entretien de l’infrastructure qui en résulte. L’infrastructure établie ne desservira que les voyageurs utilisant les liaisons ferroviaires de la gare de Miechów. Le parking sera situé dans la banlieue de Miechów, loin du centre et loin d’autres points tels que les points commerciaux, église, restaurants, etc. En raison de cet emplacement du parking, il ne sera pas utilisé par des personnes autres que celles qui s’intéressent au transport ferroviaire. La nouvelle infrastructure PR a le potentiel de s’intégrer à d’autres modes de transport. Les bus privés de la ligne MiechówMostek à Gołcza s’arrêtent à la gare de Miechów. Le parking PR sera situé env. 5 minutes à pied de la gare routière exploitée par des transporteurs privés et MPK. Un arrêt de bus sera créé dans le nouveau parking, qui sera mis à la disposition de tous les transporteurs intéressés. Il est également prévu de lancer des transports en commun par autobus, en utilisant l’arrêt susmentionné à la gare et en coordination avec les cours SKA. Dans le même temps, le parking BikeRide créé dans le cadre du projet encouragera les résidents à utiliser leur vélo plus fréquemment pour atteindre la gare et poursuivre leur voyage en train. Le projet répond aux besoins de transport des habitants de Miechów et de la municipalité de Miechów en ce qui concerne la possibilité de se connecter du transport individuel au train. L’ensemble vise à réduire l’utilisation des voitures particulières dans le fonctionnement quotidien des résidents et à les remplacer par des transports écologiques. L’effet escompté sera principalement la réduction des polluants atmosphériques émis par un trafic excessif. (French)
    1 December 2021
    0 references

    Identifiers

    RPMP.07.02.04-12-0361/17
    0 references